  <paragraph num="A.">
    <text>Project Work-In-Progress. When the applicant’s project is work-in-progress, the applicant shall provide interim and final progress reports of the project including a detailed description of the use of award funds on a regular basis, as required from time to time by TEDCO.</text>
  </paragraph>
  <paragraph num="B.">
    <text>Project Completion. Upon completion of the project, the applicant shall provide impact reports to TEDCO annually for a period of up to 5 years following the completion, in such form as TEDCO may specify from time to time. Impact reports shall include an analysis of the achievement of the project’s metrics.</text>
  </paragraph>