<?xml version='1.0' encoding='utf-8'?>
<chapter num="01" heading="Procurement Procedures" title_num="14" subtitle_num="13">
  <regulation prefix="Regulation" num=".01" heading="Purpose.">
    <text>The procedures established in this chapter are applicable to the procurement of supplies, services, and construction including leasing personal property as a lessee. The Authority is not subject to the State Finance and Procurement Article, Annotated Code of Maryland.</text>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Conflict of Interest.">
    <text>The members of the Authority, its Executive Director, and staff members are required to comply with the conflict of interest provisions found in the General Provisions Article, Title 5, Subtitle 5, Annotated Code of Maryland.</text>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Scope.">
    <paragraph num="A.">
      <text>This chapter does not apply to the following:</text>
      <paragraph num="(1)">
        <text>Contracts with or procurement from:</text>
        <paragraph num="(a)">
          <text>A State agency or unit,</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A political subdivision of the State,</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An agency of a political subdivision of the State,</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A government, including the government of another state or the United States,</text>
        </paragraph>
        <paragraph num="(e)">
          <text>An agency or political subdivision of the State, or</text>
        </paragraph>
        <paragraph num="(f)">
          <text>A bistate, multistate, bicounty, or multicounty governmental agency;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Acquisition of real property or a permanent or temporary interest in real estate;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Disposal of real or personal property; or</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Contracts or purchases that were originally procured by a federal, state or local government agency or entity, pursuant to the procurement laws and regulations of the procuring entity.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Definitions.">
    <paragraph num="A.">
      <text>In this chapter, the following terms have the meanings indicated.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Terms Defined.</text>
      <paragraph num="(1)">
        <text>"Authority" means the Northeast Maryland Waste Disposal Authority.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>“Board” means the Board of Directors of the Authority.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>“Executive Director” means the Executive Director of the Northeast Maryland Waste Disposal Authority.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>“Person” has the meaning stated in Natural Resources Article, §3-101(j), Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Proposal.</text>
        <paragraph num="(a)">
          <text>“Proposal” means the response by an offeror to a request for proposals to obtain supplies, services, or construction.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Proposal” may include, without limitation, an offeror's price, description of technical expertise, work experience, and other information requested in the solicitation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>“Responsible” means a person who has the capability in all respects to dutifully perform fully the contract requirements, and the integrity and reliability that ensures good faith performance.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>“Responsive” means a bid or offer submitted in response to a solicitation that conforms in all material respects to the requirements contained in the solicitation.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>“Services” means the rendering of time, effort, or work, rather than the furnishing of a specific physical product other than reports incidental to the required performance.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>“Supplies” means all tangible personal property, including equipment, leases of equipment, and insurance, including any incidental services.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Procurement Authority.">
    <text>The power to contract on behalf of the Authority for the procurement of materials, supplies, or services and construction shall be vested in the Executive Director. The Executive Director may, with the approval of the Authority, delegate this power to other staff members. The Executive Director may exercise any responsibility of the Authority set forth in these regulations. However, contracts and orders involving the expenditure of more than $10,000 shall be awarded only by resolution of the Authority upon recommendation of the Executive Director.</text>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Advertising.">
    <text>Advertising, when used, shall be placed in one or more newspapers of general circulation serving the area where the procurement is required, or e-Maryland Marketplace. Wider range advertising, including advertising in professional and trade publications, may be employed at the discretion of the Executive Director. The advertisement shall describe the materials, supplies, equipment, or services required, pertinent information as to submission of bids, proposals or qualification statements, and shall identify a staff member of the Authority who can respond to inquiries concerning the procurement.</text>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Methods of Procurement.">
    <paragraph num="A.">
      <text>All purchases shall be awarded by one of the following methods:</text>
      <paragraph num="(1)">
        <text>Competitive sealed bidding;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Competitive negotiation;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Small procurement procedures, when permitted by Regulation .14 of this chapter;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Revised bids after competitive sealed bidding where all bids are rejected;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Sole source procurement, when permitted by Regulation .11 of this chapter;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Emergency procurement, when permitted by Regulation .12 of this chapter; or</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Intergovernmental cooperative purchasing as that term is defined in State Finance and Procurement Article, §13-110, Annotated Code of Maryland, and COMAR 21.05.09.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The Authority shall select the method of procurement which in its discretion best meets the needs of the Authority.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Prequalification.">
    <paragraph num="A.">
      <text>The Authority may require prequalification of bidders regardless of the method of procurement selected.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Method of Prequalification.</text>
      <paragraph num="(1)">
        <text>The Authority shall issue a request for qualifications.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Authority may invite some or all persons and entities seeking to become qualified to participate in oral interviews. The interviews will become part of the responses to a request for qualifications.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Authority may require some or all persons and entities seeking to become qualified to submit additional data and information, which will become part of the responses.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Authority shall evaluate the responses and shall rank each response in accordance with evaluation criteria.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>By applying the evaluation criteria, the Authority shall establish a short-list composed of a minimum of two and, in general, a maximum of five persons or entities.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The Authority shall notify those who qualified for the short-list that they have qualified and that they can anticipate a request for proposals, an invitation to bid, or, depending on the method of procurement selected by the Authority, an invitation to participate in negotiations.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>The Authority shall notify those who did not qualify.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>The requirement for competition may be satisfied by the prequalification process.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".09" heading="Guidelines for Competitive Sealed Bidding.">
    <paragraph num="A.">
      <text>Bids shall be submitted in a sealed envelope marked with the bidder's name. All bids will be publicly opened at the time and place stated in the request.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Award shall be made with reasonable promptness after the date of bid opening to that person or entity with the lowest bid which is both responsible and responsive.</text>
    </paragraph>
    <paragraph num="C.">
      <text>All bids may be rejected if the Authority determines that it is in the public interest to do so.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".10" heading="Guidelines for Competitive Negotiation.">
    <paragraph num="A.">
      <text>A special form or procedure is not prescribed for procurement by competitive negotiation. The request shall be in writing and shall describe the procurement in sufficient detail to provide an understanding of what is required, but should not be unnecessarily restrictive so as to preclude or limit competition. The request shall state applicable dates for the submission of proposals, and any other information which may be necessary and useful, including evaluation criteria.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Precautions shall be taken to avoid prejudice in the selection of a source of supply, and to assure that a fair and reasonable price is obtained. This section does not preclude the Authority from making an award when only one proposal is received by the Authority after advertising.</text>
    </paragraph>
    <paragraph num="C.">
      <text>The Authority may conduct oral negotiations before or after the receipt of proposals. The purpose of the negotiation is to promote understanding of the Authority's requirements and the offerors' proposals and to facilitate arrival at a contract that is most advantageous to the Authority. The Authority may require offerors to submit best and final offers after negotiations.</text>
    </paragraph>
    <paragraph num="D.">
      <text>The Authority shall make an award to the offeror whose proposal or, if applicable, best and final offer, after giving effect to the understanding gained during negotiations, is determined to be most advantageous to the Authority.</text>
    </paragraph>
    <paragraph num="E.">
      <text>The Authority may abandon a procurement by competitive negotiation if it is determined to be in the public interest to do so.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".11" heading="Sole Source Procurement.">
    <paragraph num="A.">
      <text>Condition for Use. Sole source procurement is not permissible unless a requirement is available from only a single vendor.</text>
    </paragraph>
    <paragraph num="B.">
      <text>The determination as to whether a procurement shall be made as a sole source shall be made by the Executive Director, and approved by the Board. The determination and the basis for it shall be in writing. The Authority may not award a contract to a sole source before the Board's approval, except as allowed in Regulation .14 of this chapter.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".12" heading="Emergency Procurement.">
    <paragraph num="A.">
      <text>Application. The Authority may award an emergency contract by means other than competitive sealed bidding or competitive negotiation under Regulation .09 or .10 of this chapter.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Scope. “Emergency” means a sudden and unexpected occurrence or condition which the Authority could not reasonably foresee and which requires an action to avoid or to mitigate damage to the environment or to health, safety, or welfare. An emergency procurement is limited to the procurement of only those items necessary to avoid or to mitigate the damage to the environment or to health, safety, or welfare.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Competition. The Authority shall reasonably attempt to obtain such competition as is consistent with meeting the time requirements of the emergency.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".13" heading="Supplemental Work.">
    <text>The Authority need not follow the procurement process as set forth in these regulations when the procurement is for supplemental work, substantially related to work previously awarded by the Authority by competitive sealed bidding or competitive negotiation, and where further competitive procurement would not enhance the public interest.</text>
  </regulation>
  <regulation prefix="Regulation" num=".14" heading="Small Procurement Procedures.">
    <text>Materials, supplies, equipment, and services may be procured by open market purchase or sole source award when the amount involved is anticipated to be less than $2,500 in the aggregate on an annual basis for a particular procurement. Procurement by open market purchase or sole source award in amounts over $2,500, but less than $10,000, is permitted when the materials, supplies, equipment, and services are of a unique and special nature, or when public exigency will not permit the delay incident to competition. In this event, a memorandum justifying the action and signed by the Executive Director shall be filed with the official records of the Authority.</text>
  </regulation>
  <regulation prefix="Regulation" num=".15" heading="Contracts Voidable for Noncompliance.">
    <paragraph num="A.">
      <text>If the Board determines that a procurement violates this chapter, the Board may determine that the procurement contract is voidable rather than void if the Board finds that:</text>
      <paragraph num="(1)">
        <text>All parties have acted in good faith;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Ratification of the procurement contract would not undermine the purposes of this chapter; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The violation, or series of violations, was insignificant or otherwise did not prevent substantial compliance with this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>If the Board determines that a procurement contract is voidable under §A of this regulation and that the contractor has not acted in violation of this chapter, the Board may:</text>
      <paragraph num="(1)">
        <text>Ratify the contract if it determines that ratification is in the best interest of the Authority; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Void the contract.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>If the Board determines that a procurement contract is voidable under §A of this regulation and that the contractor has acted in violation of this chapter, the Authority:</text>
      <paragraph num="(1)">
        <text>May void the contract; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Without the prejudice to the Authority's right to appropriate damages, may ratify the contract if the Board determines that ratification is in the best interests of the Authority.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".16" heading="Bid Protests.">
    <paragraph num="A.">
      <text>Time Restrictions.</text>
      <paragraph num="(1)">
        <text>A protest based upon alleged improprieties in a solicitation that are apparent before bid opening or the closing date for receipt of initial proposals shall be submitted to the Director of Finance and Administration before bid opening or the closing date for receipt of initial proposals.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>For procurement by competitive sealed proposals, alleged improprieties that did not exist in the initial solicitation but which are subsequently incorporated in the solicitation shall be submitted to the Director of Finance and Administration not later than the next closing date for receipt of proposals following the incorporation.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>In all other cases, protests shall be submitted to the Director of Finance and Administration not later than 7 days after the basis for protest is known, or should have been known, whichever is earlier.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>A protest received by the Director of Finance and Administration after the time limits of §A(1)—(3) of this regulation may not be considered and shall be denied as untimely.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Form and Content of Bid Proposals.</text>
      <paragraph num="(1)">
        <text>To expedite the handling of protests, the envelope should be labeled “Protest”.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The written proposal shall include as a minimum the following content:</text>
        <paragraph num="(a)">
          <text>The name and address of the protestor;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Appropriate identification of the procurement and, if a contract has been awarded, its number if known;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A statement of the reasons for the protest;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Supporting exhibits, evidence, or documents to substantiate the reasons for the protest; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>If not available within the time restrictions:</text>
          <paragraph num="(i)">
            <text>A description of the nature and extent of the evidence and documents; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The expected availability date of the evidence and documents.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Any additional information or substantiation requested by the Director of Finance and Administration shall be submitted within 5 days after receipt of request, or other time as the Director of Finance and Administration may specify in order to expedite consideration of the protest. Failure of the protestant to comply with a request for information or substantiation by the Director of Finance and Administration may result in a resolution of the protest without consideration of any response to the request that is not timely filed.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Authority Determination and Finding.</text>
      <paragraph num="(1)">
        <text>After a protest is filed, the Director of Finance and Administration shall consider the protest, all supporting documentation, and any submissions from other bidders or offerors. This consideration is not a contested hearing, subject to State Government Article, Title 10, Subtitle 2, Annotated Code of Maryland. After consideration, the Director of Finance and Administration shall make a determination and finding regarding the protest.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>For contracts valued at less than $10,000, the Director of Finance and Administration may make the determination and finding without consultation with the Executive Director.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>For contracts valued at $10,000 or more, the Director of Finance and Administration shall provide a proposed determination and finding to the Executive Director. The Executive Director shall consider the protest and shall issue the determination and finding.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The determination and finding shall be forwarded by certified mail to the protestor.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Appeal.</text>
      <paragraph num="(1)">
        <text>The protestor may appeal the determination and finding to the Board of Directors within 10 days after receipt. The appeal shall be in writing, and include a copy of the protest and the determination and finding. In addition, the appeal shall contain all grounds for disagreement with the determination and finding. Appeals not received within 10 days after receipt by the protestor shall be dismissed as untimely.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If the protestor desires a hearing on its protest, a request for a hearing shall be made, in writing, at the time of the appeal. If a timely request for a hearing is received, the Board of Directors shall conduct a hearing in accordance with State Government Article, Title 10, Subtitle 2, Annotated Code of Maryland. In accordance with State Government Article, §10-205, Annotated Code of Maryland, the Board of Directors may delegate its authority to conduct this hearing to the Office of Administrative Hearings.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Board of Directors shall issue a final decision on the protest, which is the final Authority decision. This final decision of the Authority is subject to judicial review in accordance with the rules established by State Government Article, §10-222, Annotated Code of Maryland.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Contract Awards.</text>
      <paragraph num="(1)">
        <text>Generally, if a protest has been filed, the Authority may not award the contract until there is a final Authority decision on the protest.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Authority may award a contract before there is a final Authority decision after making a determination and finding which considers:</text>
        <paragraph num="(a)">
          <text>The merits of the protestor's complaint;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The need of the Authority for the procurement, which is the subject of the protest;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The fluctuations in the market, which may impact costs;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The unwillingness of the proposed awardee to extend its offer; or</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Other factors which impact on the public interest.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Natural Resources Article, §§3-905(b) and 3-921, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: December 26, 1980 (7:26 Md. R. 2424)</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised effective September 27, 1982 (9:19 Md. R. 1896)</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised effective March 19, 2001 (28:5 Md. R. 552)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02 amended effective December 21, 2015 (42:25 Md. R. 1546)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03A amended effective December 21, 2015 (42:25 Md. R. 1546)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06 amended effective December 21, 2015 (42:25 Md. R. 1546)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .16 adopted effective December 11, 2003 (30:24 Md. R. 1744)</annotation>
  </annotations>
</chapter>