# COMAR Title 14 — Independent Agencies

## Subtitle 39 — Interagency Commission on School Construction

### Chapter 02 — Administration of the Public School Construction Program

#### Regulation .09 Project Development and Design Funding Allocation.

*COMAR 14.39.02.09*

A. The project development and design funding allocation is the maximum amount the State may fund of eligible project development and design costs for a public school construction project.

B. The project development and design funding allocation for each approved public school project is set in the State capital improvement program.

C. The project development and design funding allocation may not exceed 10 percent of a preliminary maximum State construction allocation as set forth in Regulation .06 of this chapter and as calculated in the year of the request for project development and design funding.