# COMAR Title 14 — Independent Agencies

## Subtitle 39 — Interagency Commission on School Construction

### Chapter 02 — Administration of the Public School Construction Program

#### Regulation .13 Ineligible Expenditures.

*COMAR 14.39.02.13*

The following expenditures are ineligible for State funding:

A. Site acquisition;

B. Offsite development costs except those listed as eligible in Regulation .10 of this chapter;

C. Master plans;

D. Projects proposed in buildings or portions of buildings that have been constructed or renovated within 15 years, except that building or portion of a building in which a renovation was performed is eligible for additional work within 15 years of the date that the renovation construction was completed;

E. Capital maintenance projects to replace, upgrade, or renovate building systems that have been replaced, upgraded, or renovated within 15 years;

F. Ancillary construction costs such as:

  (1) Permits;

  (2) Bid advertising;

  (3) Water and sewer connection charges;

  (4) Models; or

  (5) Renderings;

G. Leasing or purchasing school facilities except as provided in COMAR 14.39.05;

H. Construction inspection services;

I. Relocation costs for site occupants;

J. Salaries of local employees;

K. Construction of administrative or support facilities, including regional or central administrative offices, warehousing, resource, printing, vehicle storage, and maintenance facilities;

L. Equipment, furnishings, and artwork with a median useful life of less than 15 years as defined by the IAC;

M. Maintenance; and

N. Temporary storage.