<regulation prefix="Regulation" num=".06" citation="COMAR 14.39.04.06" title_num="14" subtitle_num="39" chapter_num="04" heading="Construction Management at Risk.">
  <paragraph num="A.">
    <text>General.</text>
    <paragraph num="(1)">
      <text>Construction management at risk means a project delivery method in which the LEA engages a construction manager at risk (CMR) to:</text>
      <paragraph num="(a)">
        <text>Contract directly with trade contractors; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Provide a guaranteed maximum price for project procurement and construction.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>The CMR warrants that the work will be completed at or below the guaranteed maximum price with provisions for change order adjustments for work that is outside the agreed-upon work scope.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Cost savings resulting from projects completed below the guaranteed maximum price may be shared between the LEA and the CMR.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Guaranteed Maximum Price.</text>
    <paragraph num="(1)">
      <text>Guaranteed maximum price (GMP) means an arrangement between the LEA and the CMR in which the total amount payable to the CMR for the project is restricted to a pre-agreed maximum and includes the cost of construction and construction management services that is generally determined before the design is complete.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The LEA and CMR may determine the guaranteed maximum price as follows:</text>
      <paragraph num="(a)">
        <text>In competitive sealed bidding or quality based selection, the guaranteed maximum price is based on construction documents that are sufficiently developed to allow bidders to reasonably estimate and include costs for unspecified items, and includes:</text>
        <paragraph num="(i)">
          <text>Cost of the work;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Construction management fee; and</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>General conditions; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>In competitive negotiation, including projects in which a construction manager has provided pre-GMP services, the LEA may begin negotiations to establish a guaranteed maximum price with the construction manager only after:</text>
        <paragraph num="(i)">
          <text>The LEA has provided public notice of its intent and a request for competing proposals; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>At least 28 days have elapsed for receipt of competing proposals.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>If the LEA receives competing proposals, the proposals shall be evaluated in accordance with COMAR 14.39.03.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Notice to IAC.</text>
    <paragraph num="(1)">
      <text>Not later than 2 months before the release of solicitation documents to offerors, the LEA shall provide written notice to the IAC or its designee that the CMR method will be used.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The LEA shall acknowledge in the notice that the State is not responsible for any project cost overruns.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Not later than 1 month before release to offerors, the LEA shall submit the solicitation documents to the IAC or its designee for approval.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>State Reimbursement.</text>
    <paragraph num="(1)">
      <text>State funds may be used to reimburse:</text>
      <paragraph num="(a)">
        <text>Allowable pre-GMP costs only if related to the solicitation of trade packages; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Allowable post-GMP costs.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Allowable post-GMP construction management services, as determined by the IAC, shall be included in total construction cost as if the CMR were a general contractor for purposes of determining the maximum State construction allocation, payment of requisitions, and project close out.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Total State reimbursement of eligible costs may not exceed the lesser of:</text>
      <paragraph num="(a)">
        <text>The State's share of the guaranteed maximum price based on the cost-share formula; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The maximum State construction allocation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>If an LEA intends to seek State reimbursement of any of the construction management services, the services shall be procured through one of the procurement methods provided in COMAR 14.39.03.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Trade Contracts.</text>
    <paragraph num="(1)">
      <text>The CMR assumes all risk for cost, schedule, and performance of the trade contracts except for a trade contract that the LEA separately procures.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Trade contracts may be procured concurrently or over the life of the project.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>After the guaranteed maximum price is finalized, any trade contract previously awarded by the LEA may be assigned to the CMR who then assumes all risk for coordination and completion of the trade contracts.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Subcontracts solicited by the CMR as components of the final guaranteed maximum price do not require IAC approval.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>If the LEA intends to award a separate trade contract, the LEA shall submit the trade contract to the IAC for approval notwithstanding the subsequent inclusion of the trade contract in the guaranteed maximum price.</text>
    </paragraph>
  </paragraph>
</regulation>