<chapter num="04" heading="Project Delivery Methods" title_num="14" subtitle_num="39">
  <regulation prefix="Regulation" num=".01" heading="Scope.">
    <paragraph num="A.">
      <text>This chapter applies to a public school construction project for building, improvement, supplies, or equipment if it:</text>
      <paragraph num="(1)">
        <text>Exceeds $50,000 and has IAC planning or funding approval; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Requires review by the State Superintendent of Schools under Education Article, §2-303, Annotated Code of Maryland.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>This chapter does not apply to a project in a building that is not used primarily for the instruction of students, including an office building, warehouse, or vehicle maintenance or repair building.</text>
    </paragraph>
    <paragraph num="C.">
      <text>In this chapter, “IAC or its designee” includes “State Superintendent or designee” if State Superintendent approval is required by Education Article, §2-303(f), Annotated Code of Maryland.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Project Delivery Proposal Review Assistance.">
    <text>The State Superintendent or designee may request assistance from the IAC or its designee when reviewing project delivery proposals.</text>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Methods of Project Delivery.">
    <text>For a public school construction project, an LEA may use one of the following methods:</text>
    <paragraph num="A.">
      <text>General contracting; or</text>
    </paragraph>
    <paragraph num="B.">
      <text>Alternative project delivery including:</text>
      <paragraph num="(1)">
        <text>Construction management agency;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Construction management at risk;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Design build; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Job order contracting.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Other Requirements.">
    <paragraph num="A.">
      <text>The requirements of COMAR 14.39.03 apply to all projects conducted under this chapter.</text>
    </paragraph>
    <paragraph num="B.">
      <text>All projects regardless of delivery method shall comply with State procedures for project design review.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Regardless of project delivery method, the LEA may not begin construction until the IAC or its designee has authorized the LEA to proceed.</text>
    </paragraph>
    <paragraph num="D.">
      <text>The IAC may specifically designate an individual or group to act on requests, provide the State approvals on behalf of the IAC, or both, as required in this chapter.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Construction Management Agency.">
    <paragraph num="A.">
      <text>General. Construction management agency (CMA) means a project delivery method in which the LEA:</text>
      <paragraph num="(1)">
        <text>Directly contracts with trade contractors; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Either:</text>
        <paragraph num="(a)">
          <text>Engages a construction manager as its agent to manage the project; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Acts as the construction manager.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The LEA shall disclose in the solicitation documents if the project may be converted to the construction management at risk method or other project delivery method.</text>
    </paragraph>
    <paragraph num="C.">
      <text>State Reimbursement.</text>
      <paragraph num="(1)">
        <text>The IAC or its designee shall maintain a list of CMA services that are eligible for State reimbursement.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If the LEA intends to seek reimbursement of CMA costs with State funds, the LEA shall:</text>
        <paragraph num="(a)">
          <text>Submit the solicitation documents to the IAC or its designee for review not later than 1 month before the documents are released to offerors; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Identify in the solicitation documents the construction management services that are eligible for State reimbursement.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>An LEA intending to seek State reimbursement for construction manager services shall procure a construction manager in accordance with COMAR 14.39.03.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Trade Contracts.</text>
      <paragraph num="(1)">
        <text>Trade contracts may be procured concurrently or over the life of the project.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The LEA shall submit the bidding schedule for the trade packages with proposed bid dates to the IAC or its designee and provide notice of any changes.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The LEA shall procure each trade contract in accordance with COMAR 14.39.03.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The LEA shall submit each trade contract to the IAC for approval.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>If the project is subject to prevailing wage rate requirements, each trade contract within the project is subject to prevailing wage rate requirements.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>MBE goals shall be based on the total project price, but MBE goals may vary in individual trade contracts if the overall MBE project goal is acknowledged.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Construction Management at Risk.">
    <paragraph num="A.">
      <text>General.</text>
      <paragraph num="(1)">
        <text>Construction management at risk means a project delivery method in which the LEA engages a construction manager at risk (CMR) to:</text>
        <paragraph num="(a)">
          <text>Contract directly with trade contractors; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Provide a guaranteed maximum price for project procurement and construction.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The CMR warrants that the work will be completed at or below the guaranteed maximum price with provisions for change order adjustments for work that is outside the agreed-upon work scope.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Cost savings resulting from projects completed below the guaranteed maximum price may be shared between the LEA and the CMR.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Guaranteed Maximum Price.</text>
      <paragraph num="(1)">
        <text>Guaranteed maximum price (GMP) means an arrangement between the LEA and the CMR in which the total amount payable to the CMR for the project is restricted to a pre-agreed maximum and includes the cost of construction and construction management services that is generally determined before the design is complete.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The LEA and CMR may determine the guaranteed maximum price as follows:</text>
        <paragraph num="(a)">
          <text>In competitive sealed bidding or quality based selection, the guaranteed maximum price is based on construction documents that are sufficiently developed to allow bidders to reasonably estimate and include costs for unspecified items, and includes:</text>
          <paragraph num="(i)">
            <text>Cost of the work;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Construction management fee; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>General conditions; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>In competitive negotiation, including projects in which a construction manager has provided pre-GMP services, the LEA may begin negotiations to establish a guaranteed maximum price with the construction manager only after:</text>
          <paragraph num="(i)">
            <text>The LEA has provided public notice of its intent and a request for competing proposals; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>At least 28 days have elapsed for receipt of competing proposals.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>If the LEA receives competing proposals, the proposals shall be evaluated in accordance with COMAR 14.39.03.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Notice to IAC.</text>
      <paragraph num="(1)">
        <text>Not later than 2 months before the release of solicitation documents to offerors, the LEA shall provide written notice to the IAC or its designee that the CMR method will be used.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The LEA shall acknowledge in the notice that the State is not responsible for any project cost overruns.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Not later than 1 month before release to offerors, the LEA shall submit the solicitation documents to the IAC or its designee for approval.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>State Reimbursement.</text>
      <paragraph num="(1)">
        <text>State funds may be used to reimburse:</text>
        <paragraph num="(a)">
          <text>Allowable pre-GMP costs only if related to the solicitation of trade packages; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Allowable post-GMP costs.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Allowable post-GMP construction management services, as determined by the IAC, shall be included in total construction cost as if the CMR were a general contractor for purposes of determining the maximum State construction allocation, payment of requisitions, and project close out.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Total State reimbursement of eligible costs may not exceed the lesser of:</text>
        <paragraph num="(a)">
          <text>The State's share of the guaranteed maximum price based on the cost-share formula; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The maximum State construction allocation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>If an LEA intends to seek State reimbursement of any of the construction management services, the services shall be procured through one of the procurement methods provided in COMAR 14.39.03.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Trade Contracts.</text>
      <paragraph num="(1)">
        <text>The CMR assumes all risk for cost, schedule, and performance of the trade contracts except for a trade contract that the LEA separately procures.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Trade contracts may be procured concurrently or over the life of the project.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>After the guaranteed maximum price is finalized, any trade contract previously awarded by the LEA may be assigned to the CMR who then assumes all risk for coordination and completion of the trade contracts.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Subcontracts solicited by the CMR as components of the final guaranteed maximum price do not require IAC approval.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>If the LEA intends to award a separate trade contract, the LEA shall submit the trade contract to the IAC for approval notwithstanding the subsequent inclusion of the trade contract in the guaranteed maximum price.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Design-Build.">
    <paragraph num="A.">
      <text>General.</text>
      <paragraph num="(1)">
        <text>Design-build means a project delivery method in which a single entity is contractually responsible for both design and construction of a project.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The LEA provides sufficient information to the design-build entity to guide it in the design of the project and specifies the reviews and approvals that will be required of the project.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The design-build entity is responsible for the following:</text>
        <paragraph num="(a)">
          <text>Quality of the design;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Project costs;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Construction quality;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Adherence to the LEA's schedule for project completion and occupancy; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Other factors the LEA requires.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Design-build may extend beyond the design and construction phases of a project to include:</text>
        <paragraph num="(a)">
          <text>Financing, in which case the method is called finance-design-build; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Provision of furniture and equipment, occupant move-in, or other post-construction tasks, except as limited by §A(5) of this regulation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>The design-build entity may not perform the routine maintenance and operation of a school building after occupancy.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>IAC Approval.</text>
      <paragraph num="(1)">
        <text>If the LEA decides to use the design-build method, the LEA:</text>
        <paragraph num="(a)">
          <text>Shall request approval from the IAC or its designee 2 months prior to the release of the solicitation; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>May not proceed with the design-build method until approval is obtained from the IAC or its designee.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The request for approval shall at a minimum include the proposed:</text>
        <paragraph num="(a)">
          <text>Brief description of the scope of work;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Project phasing;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Schedule for the submission of plans and specifications for review by the IAC or its designee;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Solicitation schedule;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Procurement method;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Financing arrangement, if applicable; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Performance expectations.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The LEA shall acknowledge in the request for approval that the State is not responsible for any project cost overruns.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The LEA shall send the draft design-build solicitation to the IAC or its designee for approval not later than 1 month before it is released to bidders.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Authorization by the IAC or its designee to proceed with the design-build method is independent of approvals of project planning and funding. If the IAC or its designee authorizes the use of the design-build method but project planning is not approved, the project may proceed as a locally funded project.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Design-Build Procurement.</text>
      <paragraph num="(1)">
        <text>The LEA may develop a design-build solicitation based on:</text>
        <paragraph num="(a)">
          <text>Performance specification;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Performance specification combined with concept or schematic design; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Performance specification combined with the LEA's prototype design.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The performance specification shall include at a minimum:</text>
        <paragraph num="(a)">
          <text>Educational specifications;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Performance characteristics of the school facility;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A schedule for completion and occupancy; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>General conditions that clearly describe the respective responsibilities of the LEA and the design-build entity.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>State Reimbursement.</text>
      <paragraph num="(1)">
        <text>If the LEA intends to seek State reimbursement, the LEA shall distinguish between preconstruction and construction scopes of work to allow the IAC or its designee to determine the costs that are eligible for State reimbursement.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The State's maximum participation in the project is calculated when:</text>
        <paragraph num="(a)">
          <text>The construction documents are complete; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The full scope of the project is known including ineligible items.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Allowable preconstruction services, as determined by the IAC, shall be included in total construction cost.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Final adjustment of the State's participation shall be made at project closeout.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Total State reimbursement of eligible costs may not exceed the lesser of:</text>
        <paragraph num="(a)">
          <text>The State's share of the guaranteed maximum price based on the cost-share formula; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The maximum State construction allocation.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Job Order Contracting.">
    <paragraph num="A.">
      <text>In this regulation, the following term has the meaning indicated.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Term Defined. “Job order contracting (JOC)” means a project delivery method in which the LEA selects a contractor through a competitive procurement process based on a multiplier or coefficient that:</text>
      <paragraph num="(1)">
        <text>Reflects the bidder's determination of the actual cost to perform the work plus overhead and profit; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Is applied to a fixed-price list of construction items and activities.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>The fixed prices of the construction items and activities are defined by the LEA or through a standard project cost source.</text>
    </paragraph>
    <paragraph num="D.">
      <text>The schedule of fixed prices may include a construction escalation factor for multiyear contracts.</text>
    </paragraph>
    <paragraph num="E.">
      <text>Procurement and Award.</text>
      <paragraph num="(1)">
        <text>An LEA shall obtain a JOC through a competitive procurement process, whether or not the LEA intends to execute State-funded projects through the JOC.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The JOC may include extension clauses, but the State may not participate in a project executed under a JOC that:</text>
        <paragraph num="(a)">
          <text>Has more than three annual extensions; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Has been increased by change order above the maximum combined price indicated in the solicitation, including all potential extensions, except for changes of scope to individual projects already begun before completion of the final annual extension.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>When submitting a contract approval to the IAC, the LEA must acknowledge that the State is not responsible for any project cost overruns.</text>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Approvals. If an LEA intends to execute a State-funded project through a JOC, it:</text>
      <paragraph num="(1)">
        <text>Shall provide the IAC or its designee with a brief description of the anticipated scope of work, the duration of the JOC contract, the number of annual extensions, and the maximum combined cost of the projects to be performed under the JOC;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Shall submit the project for design review prior to the start of construction [shall be required] if it would be required for similar project funded through the same State funding program;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>May reference an earlier approval and the JOC solicitation if approval is requested for a project to be executed through a JOC under which a State-funded project was previously approved, but is not required to resubmit all relevant information;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Shall obtain approval of contract award, reimbursement, or both, in the manner and timeframe required for all projects funded under the relevant program;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Shall, for design-build JOC projects, clearly indicate on the request for approval of contract award or for reimbursement those portions of the project cost that are associated with preconstruction activities in order to allow the IAC or its designee to determine which costs are eligible for State reimbursement;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Shall include in the total construction cost allowable preconstruction services, as determined by the IAC; and</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Shall acknowledge that final adjustment of the State’s participation will be made at project closeout.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Education Article, §§4-126, 5-112, and 5-303, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: May 21, 2007 (34:10 Md. R. 891)</annotation>
    <annotation type="History" subtype="Administrative History">COMAR 23.03.04 recodified to be COMAR 14.39.04 under new subtitle, Interagency Commission on School Construction, effective November 4, 2019 (46:22 Md. R. 979)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01A amended effective November 4, 2019 (46:22 Md. R. 979)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03 amended effective June 28, 2021 (48:13 Md. R. 509)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04A amended effective November 4, 2019 (46:22 Md. R. 979)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05 amended effective August 18, 2025 (52:16 Md. R. 848)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05D, E amended effective November 4, 2019 (46:22 Md. R. 979)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06B, D amended effective November 4, 2019 (46:22 Md. R. 979)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08E, F amended effective August 18, 2025 (52:16 Md. R. 848)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09 repealed effective June 28, 2021 (48:13 Md. R. 509)</annotation>
  </annotations>
</chapter>