    <text>These regulations establish the requirements for the design, construction, operation, and maintenance of agricultural drainage projects that are financed or managed by public drainage associations. To the maximum extent practicable, these regulations assure protection of natural resources and prevent water pollution by non-point source pollutants associated with agricultural drainage projects.</text>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Definitions.">
    <paragraph num="A.">
      <text>The following terms have the meanings indicated.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Terms Defined.</text>
      <paragraph num="(1)">
        <text>“Agricultural drainage project” (project) means the construction, reconstruction, repair, straightening, widening, or deepening of any ditch, drain, canal, or other watercourse, natural or man-made, financed or managed by a public drainage association to lower the water level in the soil of adjacent lands for agricultural purposes.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>“Association” and “public drainage association” mean an organization established to locate, construct or reconstruct, operate and maintain ditches, drains, and channels to provide agricultural drainage under Article 25, §52, Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>“Best management practice” (BMP) means a conservation or pollution practice that:</text>
        <paragraph num="(a)">
          <text>Reduces soil loss associated with farming practices; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Minimizes movement of sediment, animal wastes, nutrients, or agricultural chemicals into the waters of the State.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>“Cooperator's agreement” means a landowner's written agreement with a local soil conservation district to have a soil conservation and water quality plan prepared.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>“Department” means the Maryland Department of Agriculture, the Department of the Environment, or the Department of Natural Resources, or any combination of them.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>“Maintenance” means the periodic:</text>
        <paragraph num="(a)">
          <text>Control of woody growth or removal of shrubs and small trees which alter the flow, affect channel stability, or limit access to a channel;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Removal of channel obstructions, debris, and minor sediment deposits so long as the removal does not:</text>
          <paragraph num="(i)">
            <text>Alter the approved design of the channel; or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Consist of channel reconstruction or realignment;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>Cleaning out or installation of sediment traps;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Routine repair work needed to maintain the project in accordance with the approved design specifications; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Installation of water control structures and stabilization of soil to prevent erosion.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>“Off-sided construction or reconstruction” means a method of constructing channels through riparian or other woodland, characterized by the following:</text>
        <paragraph num="(a)">
          <text>Construction or reconstruction operations are performed from one side of the channel called the construction side, the other side of the channel being called the off-side;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Blowouts and treefalls are prevented by:</text>
          <paragraph num="(i)">
            <text>Clearing the off-side bank of trees and other vegetation up to 12 feet from top of bank, and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Selectively cutting diseased, damaged, and other problematic trees on the off-side that would fall into the channel from beyond the cleared area;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>After construction, the off-side berm is allowed to reestablish natural vegetation, while all maintenance to the channel is performed from the construction side.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(8)">
        <text>“Person” means any individual, receiver, trustee, guardian, personal representative, fiduciary, or representative of any kind any partnership, association, corporation, or other entity. Person includes the federal government, this State, any county, municipal corporation, or other political subdivision of this State or any of their units.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>“Pollution” means any contamination or other alteration of the physical, chemical, or biological properties of any waters of this State, including a change in temperature, taste, color, turbidity, or odor of the waters, or the discharge or deposit of any organic matter, harmful organism, or liquid, gaseous, solid, radioactive, or other substance into any waters of the State that will render the waters harmful, or detrimental to:</text>
        <paragraph num="(a)">
          <text>Public health, safety, or welfare;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Domestic, commercial, industrial, agricultural, recreational, or other legitimate beneficial uses;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Livestock, wild animals, or birds; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Fish or other aquatic life.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(10)">
        <text>“Secretary” means the Secretary of Agriculture unless the context indicates otherwise.</text>
      </paragraph>
      <paragraph num="(11)">
        <text>“Soil conservation and water quality plan” means a farm plan approved by a local soil conservation district to minimize soil erosion, and to minimize the movement of sediment, animal waste, nutrients, or agricultural chemicals into the waters of the State.</text>
      </paragraph>
      <paragraph num="(12)">
        <text>“Stable channel” means a channel where:</text>
        <paragraph num="(a)">
          <text>The following degradation does not occur:</text>
          <paragraph num="(i)">
            <text>Significant erosion of the channel banks and bottom,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Erosion around culverts, bridges, or water control structures along the channel, and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The formation or enlargement of gullies because of the uncontrolled entry of water flow;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>Significant aggregation to the channel occurs only within the designated limits on:</text>
          <paragraph num="(i)">
            <text>Sediment traps,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>In-stream wetlands designed for this purpose, and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Channel reaches designed for this purpose.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(13)">
        <text>“Water control structure” means a structure in an Agricultural drainage project that:</text>
        <paragraph num="(a)">
          <text>Conveys water;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Controls the direction or rate of flow of water; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Maintains a desired water surface elevation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(14)">
        <text>“Waters of the State” includes both surface and underground waters within the boundaries of the State subject to its jurisdiction, including that portion of the Atlantic Ocean within the boundaries of the State, the Chesapeake Bay and its tributaries, and all ponds, lakes, rivers, streams, public ditches, tax ditches, and public drainage systems within the State, other than those designed and used to collect, convey, or dispose of sanitary sewage.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="General Requirements.">
    <paragraph num="A.">
      <text>Required Plans.</text>
      <paragraph num="(1)">
        <text>For any project constructed or reconstructed before the effective date of this chapter, the following apply:</text>
        <paragraph num="(a)">
          <text>All associations which operate and maintain a project shall submit to the Secretary for approval:</text>
          <paragraph num="(i)">
            <text>Within 1 year of the effective date of this chapter, an inspection report for the project detailing the conditions of the association's drainage system, and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Within 5 years of the effective date of this chapter, an operation and maintenance plan for the project and an implementation schedule of needed corrective maintenance and repairs to the project;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>Until such time that an operation and maintenance plan for the project is approved by the Secretary, an association shall perform needed maintenance to the project in an environmentally sound manner;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An association shall operate and maintain a project according to the operation and maintenance plan for the project approved by the Secretary;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>If an association intends to perform any project maintenance not addressed in an existing operation and maintenance plan for a project approved by the Secretary, the association shall obtain the written approval of the Secretary, except that an association may make immediate corrective repairs to a project when necessary;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The Secretary shall make the final determination whether any proposed activity on a project is maintenance or reconstruction.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>For any project constructed or reconstructed after the effective date of this chapter, the following apply:</text>
        <paragraph num="(a)">
          <text>Before constructing or reconstructing a project, an association shall have a construction or reconstruction plan and an operation and maintenance plan for the project approved by the Secretary;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An association shall construct or reconstruct, operate and maintain a project according to the construction or reconstruction plan and the operation and maintenance plan for the project approved by the Secretary;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>If an association intends to perform any project maintenance not addressed in a existing operation and maintenance plan for the project approved by the Secretary, the association shall obtain the written approval of the Secretary, except that an association may make immediate corrective repairs to a project when necessary;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The Secretary shall make the final determination whether any proposed activity on a project is maintenance or reconstruction.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Land Use Requirements.</text>
      <paragraph num="(1)">
        <text>Before any project's construction or reconstruction plan is approved:</text>
        <paragraph num="(a)">
          <text>All of the association's taxable cropland acreage in a proposed project shall be under a:</text>
          <paragraph num="(i)">
            <text>Current, not more than 10 years old, soil conservation and water quality plan; or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Signed cooperator's agreement.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>If any landowner refuses to comply with §B(1)(a), the Secretary may:</text>
          <paragraph num="(i)">
            <text>Waive the requirement of §B(1)(a) for those uncooperative landowners in a proposed project; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Not waive this requirement for more than 20 percent of the association's taxable cropland acreage.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Those BMPs necessary to minimize non-point source water pollution shall be implemented on the cropland acreage within a proposed project.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Soil conservation and water quality plans for farms within a proposed project shall be implemented, if possible, according to a timetable established by the soil conservation and water quality plan.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Agricultural Drainage Project Plans.">
    <paragraph num="A.">
      <text>Construction or Reconstruction Plan Requirements. Before constructing or reconstructing a project, an association shall comply with the following:</text>
      <paragraph num="(1)">
        <text>Submit four copies of the construction or reconstruction plan to the Secretary for approval.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The construction or reconstruction plan shall include:</text>
        <paragraph num="(a)">
          <text>A transmittal letter to the Secretary, including:</text>
          <paragraph num="(i)">
            <text>The name of the association;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The name of the watershed and the drainage area involved; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A map indicating north arrow, watershed boundaries, scale, and any other information necessary to locate the project.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>The project design specifications, including:</text>
          <paragraph num="(i)">
            <text>A general description of the project's soil types;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The layout of the drainage channels;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The location of existing areas of trees and shrubs along the channel;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>The design and location of water control structures;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>The design and location of sediment traps;</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>A hydrological analysis if required under Regulation .05B; and</text>
          </paragraph>
          <paragraph num="(vii)">
            <text>A wetlands inventory map delineating the project. The association shall use the National Wetlands Inventory Maps available from the Department of Natural Resources. If the scale of the National Wetlands Inventory maps is inappropriate, the association may use maps of another scale, so long as the wetlands classification and mapping is consistent with the National Wetlands Inventory. Any lost wetlands required to be replaced under Regulation .05F and any wetlands, 1/4 acre or larger, created by the project shall be delineated on the wetlands inventory map.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>The construction methods, including:</text>
          <paragraph num="(i)">
            <text>Open channel construction techniques;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Measures to limit disturbance to the soil;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Spoil spreading techniques and information concerning the volume of spoil materials and the location of spoil disposal sites; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Temporary or permanent soil stabilization techniques for channel banks, berms, and soil disposal sites.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(d)">
          <text>Water quality protection measures including plans for:</text>
          <paragraph num="(i)">
            <text>Establishing vegetative strips along the channels;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Installing BMPs along the channels;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Retaining or reestablishing areas of trees, shrubs, and herbaceous growth along the channel in accordance with Regulation .05E; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Replacing wetlands in accordance with Regulation .05F.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>A signed statement from the local soil conservation district, stating that the project's farmland will meet the soil conservation and water quality plan requirements in accordance with Regulation .06.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The project's design shall comply with Regulation .05, and the construction or reconstruction of the project shall comply with Regulation .06.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Operation and Maintenance Plan Requirements. Before constructing or reconstructing a project, or as required in Regulation .03A(1) for operating and maintaining a project, an association shall comply with the following:</text>
      <paragraph num="(1)">
        <text>Submit four copies of the operation and maintenance plan to the Secretary for approval.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The operation and maintenance plan shall contain:</text>
        <paragraph num="(a)">
          <text>A transmittal letter to the Secretary, including:</text>
          <paragraph num="(i)">
            <text>The name of the association;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The name of the watershed and the drainage acreage involved; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A map indicating north arrow, watershed boundaries, scale, and any other information necessary to locate the property.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>The project's maintenance program, including a general description of the project's soil types and provisions to:</text>
          <paragraph num="(i)">
            <text>Perform routine, recurring maintenance such as mowing, seeding, and clean out;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Prevent project deterioration;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Install or replace project components when necessary; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Repair damage from normal deterioration, drought, flooding, or vandalism.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>Maintenance methods, including:</text>
          <paragraph num="(i)">
            <text>Open channel maintenance techniques;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Measures to limit soil disturbance;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Spoil spreading techniques; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Temporary or permanent soil stabilization techniques for the channel banks, berms, and spoil disposal areas.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(d)">
          <text>Water quality protection measures, including plans for:</text>
          <paragraph num="(i)">
            <text>Establishing and maintaining vegetative strips along a channel;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Installing BMPs along a channel;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Installing sediment traps;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Disposing of spoil; and</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Retaining or reestablishing areas of trees, shrubs and herbaceous growth along a channel in accordance with Regulation .05E(4).</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>An implementation schedule for the project's maintenance program.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The project's maintenance shall comply with Regulation .06, and the project's operation and maintenance program shall comply with Regulation .07.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Construction or Reconstruction Design Criteria.">
    <text>The design of a project shall conform to the following criteria:</text>
    <paragraph num="A.">
      <text>Channel Design.</text>
      <paragraph num="(1)">
        <text>An outlet shall be designated for each channel to permit the discharge of water by gravity flow or pumping.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>All channels shall be sloped and aligned to produce stable channels.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Water Control Structures.</text>
        <paragraph num="(a)">
          <text>The channel design shall include necessary water control structures for the efficient functioning of the channels. These structures include:</text>
          <paragraph num="(i)">
            <text>Water control devices and weirs;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Flood gates;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Pumping bays; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Other structures affecting the functioning of the channel.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>Water control structures shall be designed, where applicable, according to the provisions in Natural Resources Article, §4-501 et seq., Annotated Code of Maryland.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Flood Control.</text>
      <paragraph num="(1)">
        <text>A project shall be designed to minimize upstream and downstream flooding.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An association shall submit an analysis of a project's hydrological impact when downstream flooding exists or may result from a project and populated areas may be affected.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Hydrological analysis shall include hydrological models and hydraulic calculations necessary to determine the changes to a 100-year frequency flood including modifications to:</text>
        <paragraph num="(a)">
          <text>Water surface elevations;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Water velocities; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Hydrograph timing.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Formulae, models, and analysis methods for the hydrological analysis shall be subject to approval by the Secretary.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Erosion Control.</text>
      <paragraph num="(1)">
        <text>A project shall be designed to minimize erosion and sediment deposition.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Sediment traps shall be installed in key locations along channel reaches.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Water control structures shall be designed for the entry of concentrated flow of water into a channel without significant deposition or degradation.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>A channel shall be designed to minimize overbank wash of channel spoil by:</text>
        <paragraph num="(a)">
          <text>Diverting surface water around spoil banks;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Protecting channel bank stability by properly placing spoil; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Sloping the finished surface of the spoil away from a channel.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Vegetated Strips.</text>
      <paragraph num="(1)">
        <text>The following definitions describe the meaning of the terms used in §D:</text>
        <paragraph num="(a)">
          <text>“Main channel” means the primary water course constructed or maintained by an association that drains water from a subwatershed or watershed area and lateral channels.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Lateral channel” means any watercourse constructed or maintained by an association that transports water from segments of a subwatershed or watershed to the main channel.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Vegetated strips shall be designed, established, and maintained to stabilize the soil and to minimize the movement of sediment into a channel during operation.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Measurements for a vegetated strip shall be made from the top of a channel bank.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>A minimum 10-foot wide vegetated strip shall be established and maintained along each cleared side of a main channel.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>A minimum 4-foot wide vegetated strip shall be established and maintained along each cleared side of a lateral channel only if acceptable BMPs submitted to the Secretary for approval are implemented on adjoining cropland. The following apply:</text>
        <paragraph num="(a)">
          <text>Acceptable BMPs may include:</text>
          <paragraph num="(i)">
            <text>Minimum tillage;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Seasonal cover crops;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Reverse berms;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Permanent sediment traps in on-farm channels; and</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Other methods to achieve a level of water quality protection equivalent to a 10-foot wide vegetated strip.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>In the absence of BMPs approved by the Secretary, a minimum 10-foot wide vegetated strip shall be established and maintained along each cleared side of a lateral channel.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>Vegetation shall be established and maintained to stabilize the soil on the sides of both channel banks.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Water Temperature Controls.</text>
      <paragraph num="(1)">
        <text>One-sided or off-sided construction or reconstruction of a channel in woodland shall be used if practical.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Both-sided construction of a channel in woodland shall be allowed by the Secretary only when it is the only practical construction method.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Both-sided reconstruction of a channel in woodland shall be allowed by the Secretary when:</text>
        <paragraph num="(a)">
          <text>It is the only practical reconstruction method; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Both-sided construction or reconstruction was previously used and both right-of-ways are clear of woody growth.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Areas of trees, shrubs, and herbaceous growth that shade a channel shall be retained, replanted, or allowed to reestablish naturally, unless it can be demonstrated to the Secretary that the:</text>
        <paragraph num="(a)">
          <text>Presence of trees and shrubs will prevent adequate access to a channel for maintenance; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Absence of these areas of trees and shrubs will not elevate water temperature to levels that will adversely impact fish or other aquatic life.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Wetlands Replacement. An association shall replace drained or filled, non-tidal wetlands as required by this section. The following are included:</text>
      <paragraph num="(1)">
        <text>Land areas that are required to be replaced by an association under this section are those areas that:</text>
        <paragraph num="(a)">
          <text>Support a predominance of plants that grow in water or in periodically water saturated soils;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Have remained natural and uncultivated for at least 3 successive years; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>When drained or filled, will cause water pollution by significantly:</text>
          <paragraph num="(i)">
            <text>Increasing erosion and siltation, or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Reducing the area's ability to filter water pollutants.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Land areas required to be replaced under this section shall be replaced as follows:</text>
        <paragraph num="(a)">
          <text>One acre of land with equal soil-water conditions shall be created to replace each acre of drained or filled land when the:</text>
          <paragraph num="(i)">
            <text>Water table is near the soil surface for extended periods during the frost-free growing season of most years; or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Soil is water-saturated, or surface water is present for extended periods during the frost-free growing season of most years.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>In all other cases, 1 acre of temporarily to permanently flooded land shall be created to replace every 4 acres of drained or filled land.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The Secretary shall consult with the Secretaries of the Departments of Natural Resources and the Environment to determine if an association's construction or reconstruction plan adequately meets the requirement of this section.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Construction and Maintenance Criteria.">
    <paragraph num="A.">
      <text>In-stream Excavation. Except with the written permission of the Secretary of the Department of Natural Resources, in-stream excavation or clearing is prohibited between the following dates:</text>
      <paragraph num="(1)">
        <text>October 1 through April 30 in natural trout waters;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>March 1 through May 31 in recreational trout waters; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>March 15 through June 15 in anadromous fish spawning waters.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Clearing and Snagging.</text>
      <paragraph num="(1)">
        <text>Clearing and snagging of a channel may not endanger channel stability.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The areas to be cleared and snagged shall be limited to:</text>
        <paragraph num="(a)">
          <text>The channel bottom, banks, and berms;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Adjacent trees or other objects that may fall into a channel;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Access roads;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Temporary disposal areas; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Areas designated by a soil conservation district for planned conservation areas.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Revegetation.</text>
      <paragraph num="(1)">
        <text>On each project, a species of erosion controlling vegetation adapted to the area and a proven method of vegetation establishment shall be used for revegetation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Provisions shall be taken on a project to reduce soil erosion until effective revegetation can be accomplished.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>During the growing season, at a minimum:</text>
        <paragraph num="(a)">
          <text>Channel banks shall be seeded at the end of each day's excavation; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Other areas where soil has been disturbed shall be seeded within 7 days of final soil disturbance.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The progress of revegetation shall be monitored by the association and corrective action taken when necessary.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Operation and Maintenance Program Criteria.">
    <text>The operation and maintenance program for a project shall conform to the following:</text>
    <paragraph num="A.">
      <text>General Maintenance. General maintenance to a channel, maintenance areas, and right-of-ways includes the:</text>
      <paragraph num="(1)">
        <text>Removal of obstructions, debris, and sediment;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Control of woody growth;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Cleaning out of permanent sediment traps;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Installation of necessary sediment traps;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Installation of necessary water control structures where uncontrolled concentrated flow of water enters a channel;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Stabilization of eroding areas;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Routine repair of damaged structures and channel banks; and</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Observation of all other sound operation and maintenance practices.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Sediment Traps and Channel Clean Out.</text>
      <paragraph num="(1)">
        <text>Sediment traps shall be installed where necessary for the efficient operation of a channel.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The design and installation of a sediment trap shall include providing a stable channel bank slope.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The clean out of a channel or sediment trap includes:</text>
        <paragraph num="(a)">
          <text>Removal of silt bars and sediment;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Restoration of a stable channel bank slope; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Maintaining the approved channel or sediment trap design.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Channel spoil shall be placed in locations where the spoil does not:</text>
        <paragraph num="(a)">
          <text>Prevent watershed runoff from entering the natural flood plain;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Interfere with travel ways;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Endanger the stability of a channel;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Fill adjacent wetlands; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Wash back into a channel.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Disturbed areas shall be stabilized and seeded in accordance with Regulation .06C.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Vegetated Strips. Vegetated strips shall be established and maintained on all channels in accordance with Regulation .05D.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Water Temperature Control. Areas of trees, shrubs, and herbaceous growth shall be retained or reestablished in accordance with Regulation .05E(4).</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Agency Approval of a Plan.">
    <paragraph num="A.">
      <text>In this regulation, “plan” means a construction or reconstruction plan, or operation and maintenance plan, or both, as appropriate.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Plan Submission.</text>
      <paragraph num="(1)">
        <text>Within 14 days of receiving a project plan, the Secretary of Agriculture shall forward a copy to the Secretaries of Natural Resources and the Environment.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Departments of Natural Resources and the Environment shall have 60 calendar days from receipt to review a plan and respond in writing to the Secretary.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Secretary shall review the comments from the Departments of the Environment and Natural Resources. If there is any significant disagreement among the three Departments concerning the plan, the Secretary shall schedule a meeting between the Departments to resolve any disagreement.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Plan Approval. The Secretary shall make the final determination whether to approve a plan. The Secretary shall respond to the association within 30 days from receipt of comments from the Departments of Natural Resources and the Environment and either:</text>
      <paragraph num="(1)">
        <text>Approve the plan;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Approve the plan with modification;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Approve the plan conditioned upon the formation of the association;</text>
        <paragraph num="(a)">
          <text>Conditional approval may be issued for plans submitted by the county before an association is legally established,</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Final approval shall be given only when the Secretary is furnished a letter from the county government stating that it has approved the plan and established the association,</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Any changes in the plan by a county shall be submitted to the Secretary, who shall forward copies to the Secretaries of the Departments of Natural Resources and the Environment for review;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Disapprove the plan; or</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Extend the Secretary's review period.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".09" heading="Inspection and Enforcement.">
    <paragraph num="A.">
      <text>Channel Inspection by the Association.</text>
      <paragraph num="(1)">
        <text>The association managers or designee shall inspect the project within 2 weeks following any storm which results in water flow exceeding channel capacity.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An association shall send a written inspection report to the Secretary not later than 90 days following the storm event. The report shall:</text>
        <paragraph num="(a)">
          <text>Detail the damage to the channels, vegetation, and water control structures; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Describe needed repairs and corrective maintenance and the projected time when the work shall be accomplished.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The association managers or designee shall inspect the project at least once every 2 years. The following apply:</text>
        <paragraph num="(a)">
          <text>An association shall send a written inspection report to the Secretary by March 1st of the appropriate year. The report shall:</text>
          <paragraph num="(i)">
            <text>Outline the last inspection of the project performed not more than 6 months before submission;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Detail the condition of the channel, vegetation, and structures;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Describe needed maintenance and the projected time when the work shall be completed; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Describe the work completed in the previous 2 years.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>An association need not file the biennial written inspection report required in §A(3) if:</text>
          <paragraph num="(i)">
            <text>Storm damage occurred during the 6 months before March 1st of the appropriate year; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>An inspection report required in §A(1) was submitted.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>An association shall keep records on work performed on a project. These records shall:</text>
        <paragraph num="(a)">
          <text>Include the items of work, cost, and the date the work was completed; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Be made available upon request to the Secretary.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>State Inspection.</text>
      <paragraph num="(1)">
        <text>The Secretary shall coordinate on-site inspections of a project by the Departments of Agriculture, the Environment, and Natural Resources.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An association shall grant each Department the right of entry to inspect a project to ensure that it complies with an approved construction or reconstruction plan or an approved operation and maintenance plan for the project.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Enforcement.</text>
      <paragraph num="(1)">
        <text>The Secretaries of Agriculture, the Environment, or Natural Resources may pursue any sanction or remedy provided in Agriculture Article, §8-603, Annotated Code of Maryland. Before pursuing any sanction or remedy, however, the Secretaries of the Environment and Natural Resources shall:</text>
        <paragraph num="(a)">
          <text>Consult with the Secretary of Agriculture; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Provide the Secretary of Agriculture a reasonable period of time to solve any problem.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The Secretary of a Department may issue a written order for corrective measures to any person who violates this chapter, or who fails to follow any requirement of an approved project plan.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>A person ordered to comply with this chapter may request a hearing. The following apply:</text>
        <paragraph num="(a)">
          <text>The hearing request shall be made in writing to the Secretary who issued the order;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The hearing request shall be made not later than 10 days after the date the order is served;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>When different Departments have initiated administrative proceedings arising from the same or related activities, any person subject to more than one order may request a consolidated hearing;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The hearing shall be scheduled within 30 working days from the receipt of the request;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A decision shall be rendered within 30 working days from the hearing date;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The Administrative Procedure Act, State Government Article, §10-201 et seq., Annotated Code of Maryland, governs the practice and procedure in all hearings and appeals.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Whether an order for corrective measures has been issued or contested, the Secretary of a Department may, at any time, refer an alleged violation of this chapter or of any approved plan requirement directly to the Attorney General for appropriate legal action.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>In addition to any other sanction under Agriculture Article, §8-603, Annotated Code of Maryland, any person who constructs, reconstructs, operates, or maintains an agricultural drainage project without approved plans or in violation of approved plan requirements, shall be liable to the State in a civil action for damages in an amount equal to double the costs of that portion of constructing, reconstructing, operating, or maintaining the project that was not done in accordance with the requirements of this chapter.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>A civil action under Agriculture Article, §8-603, Annotated Code of Maryland, shall be prosecuted by the Attorney General on behalf of the appropriate Department. Damages recovered shall be deposited in a special fund to be used solely for:</text>
        <paragraph num="(a)">
          <text>First, correcting the deficiencies in the agricultural drainage project in question; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Second, supporting the Secretary of Agriculture's program for review and approval of the agricultural drainage projects.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>The Secretary of any Department may seek an injunction against any person who does not have or fails to follow an approved plan.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Agriculture Article, §§2-103 and 8-603, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: August 1, 1986 (13:14 Md. R. 1635)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02B amended effective August 2, 2004 (31:15 Md. R. 1186)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05F amended effective August 2, 2004 (31:15 Md. R. 1186)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08B, C amended effective August 2, 2004 (31:15 Md. R. 1186)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09B, C amended effective August 2, 2004 (31:15 Md. R. 1186)</annotation>
  </annotations>
</chapter>