<subtitle num="50" heading="Service Supplied by Electric Companies" title_num="20" title_heading="Public Service Commission">
  <chapter num="01" heading="General">
    <regulation prefix="Regulation" num=".01" heading="Authorization of Regulations.">
      <text>The Public Utilities Article, Annotated Code of Maryland, provides that the Commission shall have the power to make such reasonable regulations as it deems necessary to carry out the provisions of this law and any other law relating to the Commission.</text>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Application of Regulations.">
      <paragraph num="A.">
        <text>Application. These regulations apply to any electric utility operating within the State, under the jurisdiction of the Public Service Commission.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Purpose. These regulations are intended to promote safe and adequate service to the public, to provide standards for uniform and reasonable practices by utilities, and to outline the responsibility of the public in requesting and receiving service from the utilities.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Exemption. If unreasonable hardship to a utility or to a customer results from the application of any of these regulations, application may be made to the Commission for the modification of the regulation or for temporary or permanent exemption from its requirements.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Modification. The adoption of these regulations does not preclude the Commission from altering or amending them, or from making such modifications with respect to their application as may be found necessary to meet exceptional conditions.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Duties Under Other Statutes. These regulations do not relieve any utility from any of its duties under the laws of this State.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Definitions.">
      <paragraph num="A.">
        <text>In this subtitle, the following terms have the meanings indicated.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Terms Defined.</text>
        <paragraph num="(1)">
          <text>“Abandoned call” means a telephone call in which the customer has elected to speak to a customer service representative but the call is terminated before the customer service representative answers.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>“All-in vegetation management cost” means all vegetation management capital and operation and maintenance expenditures, including:</text>
          <paragraph num="(a)">
            <text>All direct contractual costs and internal staffing associated with yearly scheduled cyclical trimming and all corrective work; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>All indirect costs associated with vegetation management staff, supplies, and equipment.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Answer.</text>
          <paragraph num="(a)">
            <text>“Answer” means rendering assistance to a telephone caller or accepting information necessary to process a telephone call by a customer service representative or an automated voice response system.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Answer” does not include an acknowledgement that a telephone caller is waiting on the line.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>“Baseline annual usage” means:</text>
          <paragraph num="(a)">
            <text>The total of an eligible customer-generator’s previous 12 months of electric energy use in kilowatt hours at the time of the installation or upgrade of an eligible customer-generator’s generating system; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An estimate of 12 months electric use in kilowatt hours based on a methodology approved by the Commission for an eligible customer-generator that does not have 12 months of electric energy use in kilowatt hours at the time of the installation or upgrade of an eligible customer-generator’s generating system.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>“Billing period” means the period of time covered by a bill issued by an electric company.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>“Bordering jurisdiction” means the District of Columbia, Delaware, Pennsylvania, Virginia, and West Virginia.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>“Commission” means the Public Service Commission of Maryland.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>“Contact voltage” means a voltage condition that may result in an object or surface being inadvertently energized.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>“Contact voltage risk zone (CVRZ)” means the portions of each electric company’s service territory that:</text>
          <paragraph num="(a)">
            <text>Are served by an underground electric distribution plant; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Have substantial pedestrian traffic or population density, whether permanent, seasonal or varying by time of day.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(10)">
          <text>“Contact voltage survey” means a survey performed by an electric company to detect contact voltage consistent with the company’s Commission-approved voltage survey plan.</text>
        </paragraph>
        <paragraph num="(11)">
          <text>“Corrective maintenance” means maintenance performed to correct system equipment or component conditions that render them incapable of performing their designed function.</text>
        </paragraph>
        <paragraph num="(12)">
          <text>“Critical facilities” means a utility-specific list of electric system customers essential for public health and safety requiring restoration priority as determined in consultation with State and local jurisdictions.</text>
        </paragraph>
        <paragraph num="(13)">
          <text>“Cultural control practices” means control of vegetation through the establishment of compatible stable plant communities or the use of crops, pastures, mulching, or other managed landscapes.</text>
        </paragraph>
        <paragraph num="(14)">
          <text>“Customer” means a person, partnership, association, corporation, or governmental agency being supplied with electric service by a utility.</text>
        </paragraph>
        <paragraph num="(15)">
          <text>“Customer average interruption duration index (CAIDI)” means the system average interruption duration index (SAIDI) divided by the system average interruption frequency index (SAIFI).</text>
        </paragraph>
        <paragraph num="(16)">
          <text>“Customers experiencing multiple interruptions (CEMIn)” means the ratio of individual customers experiencing n or more sustained interruptions to the total number of customers served.</text>
        </paragraph>
        <paragraph num="(17)">
          <text>“Customer interruption hours” means an amount of time calculated by multiplying a sustained interruption duration by the total number of customers affected by the sustained interruption.</text>
        </paragraph>
        <paragraph num="(18)">
          <text>“Distribution transformer” has the meaning stated in 10 CFR §431.192, as amended, which is incorporated by reference.</text>
        </paragraph>
        <paragraph num="(19)">
          <text>“Electric company” has the meaning stated in Public Utilities Article, §1-101, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(20)">
          <text>“Electric distribution” plant means all electric company plant used to distribute electricity to its customers, including covers and protective structures and excluding customer meters and meter enclosures.</text>
        </paragraph>
        <paragraph num="(21)">
          <text>“Electric plant” means a plant and property owned by an electric utility, used in its business operations of providing electric service to its customers.</text>
        </paragraph>
        <paragraph num="(22)">
          <text>“Eligible customer-generator” has the meaning stated in Public Utilities Article, §7-306, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(23)">
          <text>Environmental surcharge means the charge in dollars and cents billed by an electric company under Public Utilities Article, §7-203, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(24)">
          <text>“Excess generation” means the amount of electricity produced by an eligible customer-generator that exceeds the electricity used by the eligible customer-generator in a monthly billing period.</text>
        </paragraph>
        <paragraph num="(25)">
          <text>“Feeder” means an electric plant that emanates from a substation, serves customers, and is normally electrically isolated at all endpoints.</text>
        </paragraph>
        <paragraph num="(26)">
          <text>“Global ETR” means a single estimated time for restoration for the entire service territory or the area of the service territory affected by the major outage event and should represent the time when at least 90 percent of all affected customers will have been restored.</text>
        </paragraph>
        <paragraph num="(27)">
          <text>“Government emergency responder” means fire and police personnel and government employees who:</text>
          <paragraph num="(a)">
            <text>Are working at the direction of fire, police, or 911 emergency dispatcher personnel to respond to an emergency; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Have been identified by fire, police, or 911 dispatcher personnel as responding to an emergency.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(28)">
          <text>“Hazard tree” means a structurally unsound tree or tree limb that could strike poles, substations, or energized overhead electric plant when it falls.</text>
        </paragraph>
        <paragraph num="(29)">
          <text>“Institute of Electrical and Electronics Engineers (IEEE) major event day” means a day determined to be a major event day using the IEEE method of determining excludable data for calculation of reliability indices under IEEE Std 1366TM  2003.</text>
        </paragraph>
        <paragraph num="(30)">
          <text>“Interruption duration” means the period of time, truncated or rounded to the nearest minute, during which a sustained interruption occurs.</text>
        </paragraph>
        <paragraph num="(31)">
          <text>“Maintenance” means an inspection, diagnostics test, and or physical maintenance performed with the intent of assessing or predicting equipment failure before it occurs or improving equipment condition and thus preventing an equipment component or sub-component performance failure.</text>
        </paragraph>
        <paragraph num="(32)">
          <text>“Major outage event” means an event when the following occurs:</text>
          <paragraph num="(a)">
            <text>Before January 1, 2020:</text>
            <paragraph num="(i)">
              <text>More than 10 percent or 100,000, whichever is less, of the electric utility’s Maryland customers experience a sustained interruption of electric service and restoration of electric service to any of these customers takes more than 24 hours; or</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The federal, State, or local government declares an official state of emergency in the utility’s service territory and the emergency involves interruption of electric service; or</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>Beginning January 1, 2020:</text>
            <paragraph num="(i)">
              <text>More than 10 percent or 100,000, whichever is less, of the electric utility’s Maryland customers experience a sustained interruption of electric service; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Restoration of electric service to any of these customers takes more than 24 hours.</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(33)">
          <text>“Major outage event interruption data” means all electric customer interruption occurrence and duration information collected by the utility during a major outage event.</text>
        </paragraph>
        <paragraph num="(34)">
          <text>“Mature tree” means a tree, whether or not previously pruned by the utility, that is well-established with a defined crown and that is at least 20 feet tall or 6 inches in diameter at breast height. Mature tree does not include a hazard tree.</text>
        </paragraph>
        <paragraph num="(35)">
          <text>“Meter” means unless otherwise qualified, a device of the utility used in measuring watts, watt-hours, vars, var-hours, volt-amperes, or volt-ampere-hours.</text>
        </paragraph>
        <paragraph num="(36)">
          <text>“Micro combined heat and power” has the meaning stated in Public Utilities Article, §7-306, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(37)">
          <text>“Momentary average interruption frequency index (MAIFIE)” means the ratio of the total number of customer momentary interruption events divided by the total number of customers served.</text>
        </paragraph>
        <paragraph num="(38)">
          <text>Momentary Interruption.</text>
          <paragraph num="(a)">
            <text>“Momentary interruption” means the loss of electric service of a duration limited to the time required to restore electric service by:</text>
            <paragraph num="(i)">
              <text>Automatic or supervisory-controlled switching operations; or</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Manual switching at locations where an operator is immediately available.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>“Momentary interruption” does not include a loss of electric service which takes more than 5 minutes to restore.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(39)">
          <text>“Net energy metering” has the meaning stated in Public Utilities Article, §7-306, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(40)">
          <text>“Net Excess Generation” has the meaning stated in Public Utilities Article, §7-306, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(41)">
          <text>“Normal conditions” means conditions other than a major outage event.</text>
        </paragraph>
        <paragraph num="(42)">
          <text>“Number of customer interruptions” means the number of customers without electric service during a sustained interruption.</text>
        </paragraph>
        <paragraph num="(43)">
          <text>“Off right-of-way tree” means a tree or part of a tree where the utility does not typically perform routine tree trimming maintenance and may not have the rights to perform tree trimming to improve electric service reliability.</text>
        </paragraph>
        <paragraph num="(44)">
          <text>“On right-of-way tree” means a tree or part of a tree where the utility typically performs routine tree trimming maintenance and may or may not have the rights to perform tree trimming to improve electric service reliability.</text>
        </paragraph>
        <paragraph num="(45)">
          <text>“Operating district” means a distinct geographic area for which a cooperatively owned electric utility provides customer services from a decentralized office.</text>
        </paragraph>
        <paragraph num="(46)">
          <text>Outside Assistance.</text>
          <paragraph num="(a)">
            <text>“Outside assistance” means resources not routinely used by a utility for service restoration.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Outside assistance” does not include resources transferred among utility operating areas.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(47)">
          <text>“PJM” has the meaning stated in COMAR 20.52.01.02B.</text>
        </paragraph>
        <paragraph num="(48)">
          <text>“Premises” means a tract of land or real estate, including buildings and other appurtenances on it.</text>
        </paragraph>
        <paragraph num="(49)">
          <text>“Primary distribution system” means the alternating current distribution lines supplying the primaries of distribution transformers.</text>
        </paragraph>
        <paragraph num="(50)">
          <text>“Protective devices” means substation breakers and reclosers, line reclosers, line sectionalizing equipment, and line fuses.</text>
        </paragraph>
        <paragraph num="(51)">
          <text>“Resilience plan” means a plan or plans to prepare for and recover from pandemics, physical attacks, cyber attacks, electric supply shortages, weather events, significant infrastructure failures, and other credible disturbances with the potential to lead to large and widespread electric outages or loss of critical facilities essential for public health and safety.</text>
        </paragraph>
        <paragraph num="(52)">
          <text>“Secondary distribution system” means the alternating current system which connects the secondaries of distribution transformers to the customers' services.</text>
        </paragraph>
        <paragraph num="(53)">
          <text>“Sustained interruption” means the loss of electric service that is not classified as a momentary interruption.</text>
        </paragraph>
        <paragraph num="(54)">
          <text>“System average interruption duration index (SAIDI)” has the meaning stated in Public Utilities Article, §7-213(a)(2), Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(55)">
          <text>“System average interruption frequency index (SAIFI)” has the meaning stated in Public Utilities Article, §7-213(a)(3), Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(56)">
          <text>“Test current” means the current marked on the nameplate of a watt-hour meter by the manufacturer (identified as “TA” on meters manufactured since 1960). This is the current in amperes which is used as the base for adjusting and determining the accuracy of a watt-hour meter at heavy and light loads.</text>
        </paragraph>
        <paragraph num="(57)">
          <text>“Time-varying rate” means a base or commodity rate structure that includes more than one rate, each of which is applicable to a different time period during the billing cycle and excludes hourly priced rates for which the rate is derived from hourly energy costs from the PJM market.</text>
        </paragraph>
        <paragraph num="(58)">
          <text>“Total number of customers served” means the number of customers provided with electric service by the distribution facility on the last day of the time period for which a reliability index is being calculated.</text>
        </paragraph>
        <paragraph num="(59)">
          <text>“Utility” means an electric company as defined in Public Utilities Article, §1-101, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(60)">
          <text>” Utility crew” means personnel and equipment routinely used by a utility for service restoration.</text>
        </paragraph>
        <paragraph num="(61)">
          <text>“Voltage survey plan” means an electric company plan approved by the Commission governing the electric company’s contact voltage detection and testing equipment and voltage detection and testing procedures to be used when conducting contact voltage surveys.</text>
        </paragraph>
        <paragraph num="(62)">
          <text>“Vulnerable individual” means a customer who is certified to the utility as having a serious illness or the need for life support pursuant to COMAR 20.31.03.01.</text>
        </paragraph>
        <paragraph num="(63)">
          <text>“Zonal ETR” means the estimated time for restoration when at least 90 percent of all affected customers in the sub-area will have been restored to service.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Environmental Surcharge to be Billed and Remitted by Electric Companies.">
      <paragraph num="A.">
        <text>If an electric company itemizes the environmental surcharge on a customer's bill, the electric company shall bill the environmental surcharge to each customer as required by Public Utilities Article, §7-203, Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An electric company shall remit to the State Comptroller the amount equal to the environmental surcharge billed under §A of this regulation.</text>
      </paragraph>
      <paragraph num="C.">
        <text>When calculating the amount billed to a customer for the environmental surcharge in a billing period, an electric company shall follow the following rounding practices:</text>
        <paragraph num="(1)">
          <text>If the amount calculated using the environmental surcharge rate and total kilowatt hour usage for the billing period results in an amount ending in $0.005 or greater, the amount shall be rounded up to the next whole cent; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If the amount calculated using the environmental surcharge rate and total kilowatt hour usage for the billing period results in an amount ending in less than $0.005, the amount shall be rounded down to the next whole cent.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Waiver.">
      <text>The Commission may waive a regulation in this subtitle for good cause shown.</text>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, 5-303, and 7-213, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03 amended effective September 16, 2024 (51:18 Md. R. 810)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03B amended effective April 15, 2002 (29:7 Md. R. 622); July 2, 2007 (34:13 Md. R. 1152); September 21, 2009 (36:19 Md. R. 1438); November 28, 2011 (38:24 Md. R. 1503); February 20, 2012 (39:3 Md. R. 260); May 28, 2012 (39:10 Md. R. 661); December 2, 2019 (46:24 Md. R. 1104); August 21, 2023 (50:16 Md. R. 728);</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04 adopted effective July 2, 2007 (34:13 Md. R. 1152)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 adopted effective February 20, 2012 (39:3 Md. R. 260)</annotation>
    </annotations>
  </chapter>
  <chapter num="02" heading="Engineering">
    <regulation prefix="Regulation" num=".01" heading="Good Engineering Practice.">
      <text>The electric plant of the utility shall be constructed, installed, maintained, and operated in accordance with accepted good engineering practice in the electric industry to assure, as far as reasonably possible, continuity of service, uniformity in the quality of service furnished, and the safety of persons and property.</text>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Acceptable Standards.">
      <text>Unless otherwise specified by the Commission, the utility shall use the applicable provisions in the latest revised version of the incorporated by reference publications listed below as standards of accepted good engineering practice in this subtitle:</text>
      <paragraph num="A.">
        <text>National Electrical Safety Code, ANSI C2 — 2017;</text>
      </paragraph>
      <paragraph num="B.">
        <text>National Electrical Code, ANSI/NFPA 70 — 2020;</text>
      </paragraph>
      <paragraph num="C.">
        <text>American National Standard for Electric Meters — Code for Electricity Metering, ANSI C12.1 — 2014;</text>
      </paragraph>
      <paragraph num="D.">
        <text>American Standard Requirements, Terminology and Test Code for Instrument Transformers, ANSI/IEEE C57.13 — 2016;</text>
      </paragraph>
      <paragraph num="E.">
        <text>Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces, IEEE 1547-2018;</text>
      </paragraph>
      <paragraph num="F.">
        <text>Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces, IEEE 1547-2018 Amendment 1 (IEEE Std. 1547a-2020);</text>
      </paragraph>
      <paragraph num="G.">
        <text>Errata to Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces, IEEE 1547-2018;</text>
      </paragraph>
      <paragraph num="H.">
        <text>IEEE 1547.1-2020, Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces;</text>
      </paragraph>
      <paragraph num="I.">
        <text>UL Standard for Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy</text>
      </paragraph>
      <paragraph num="J.">
        <text>NEMA Standards Publication TP 1 — 2002;</text>
      </paragraph>
      <paragraph num="K.">
        <text>Guide for Electric Power Distribution Reliability Indices, IEEE Standard 1366 — 2003, 4.5 Major event day classifications;</text>
      </paragraph>
      <paragraph num="L.">
        <text>Institute of Electrical and Electronic Engineers Standard 1695 — 2016 — IEEE Guide to Understanding, Diagnosing, and Mitigating Stray and Contact Voltage;</text>
      </paragraph>
      <paragraph num="M.">
        <text>Interconnection Requirements for Onboard, Grid Support Inverter Systems, SAE J3072, Revision 3, June 10, 2024;</text>
      </paragraph>
      <paragraph num="N.">
        <text>Electric Vehicle Supply Equipment, UL 2594, Edition 3, December 15, 2022; and</text>
      </paragraph>
      <paragraph num="O.">
        <text>Electric Vehicle Power Export Equipment (EVPE), UL 9741, September 29, 2023.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Adequacy of Supply.">
      <text>The generating capacity of the utility's plant, supplemented by the electric power regularly available from other sources, shall be sufficiently large to meet all normal demands for service and provide a reasonable reserve for emergencies.</text>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Electric Plant Operation and Maintenance.">
      <text>Each utility shall adopt written operation and maintenance procedures for its electric plant in order to determine the necessity for replacement and repair. The frequency of the various procedures shall be based on the utility's experience and accepted good practice. Each utility shall keep sufficient records to give evidence of compliance with its operation and maintenance procedures.</text>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Specific Electric Plant Engineering Requirements.">
      <paragraph num="A.">
        <text>When the National Electrical Safety Code and the National Electric Code, which are incorporated by reference in Regulation .02 of this chapter, call for different standards or requirements for installations that are under the exclusive control of the utility and located in legally established easements or rights-of-way, or located pursuant to agreements recognized by the Commission such as a utility tariff, the utility shall use the standard or requirement of the National Electrical Safety Code.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Utilities shall maintain the vertical clearances of overhead electric supply lines that cross water surfaces suitable for sailboating in accordance with the values specified by Rule 232 of the National Electrical Safety Code.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Life-Cycle Cost Analysis to Guide the Purchase of Liquid-Immersed Distribution Transformers.">
      <paragraph num="A.">
        <text>Scope. This regulation does not apply to an electric cooperative that supplies electricity to fewer than 60,000 electric meters in the State.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Purchase of Liquid-Immersed Distribution Transformers.</text>
        <paragraph num="(1)">
          <text>Beginning January 1, 2009, a utility shall use the life-cycle cost methodology contained in NEMA Standards Publication TP 1-2002, which is incorporated by reference under COMAR 20.50.02.02, when selecting any liquid-immersed distribution transformer for purchase.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Evaluation of Distribution Transformer Models.</text>
          <paragraph num="(a)">
            <text>Within each capacity class or type of liquid-immersed distribution transformer, a reasonable number of commercially available models shall be evaluated, and, except as provided §B(2)(b) of this regulation, a utility shall select for purchase the model in each capacity class or type with the lowest total owning costs as determined by the life-cycle cost methodology.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If a utility is soliciting bids to supply multiple capacity classes or types of liquid-immersed distribution transformers under a single contract, models offered by a supplier in more than one capacity class or type may be combined for purposes of life-cycle cost evaluation.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A utility shall select for purchase the aggregation of models offered by a supplier in the combined classes or types with the lowest total owning cost as determined by the life-cycle cost methodology in §B(2)(b) of this regulation.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Under this section, a utility shall use:</text>
            <paragraph num="(i)">
              <text>The values for load losses and no-load losses as determined by the “Uniform Test Method for Measuring the Energy Consumption of Distribution Transformers”, Appendix A to Subpart K of 10 CFR Part 431, as amended, which is incorporated by reference; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The estimated value of energy and capacity from the most current year available at the time of any bid solicitation.</text>
            </paragraph>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>This regulation does not require a utility to purchase any liquid-immersed distribution transformer that fails to meet federal energy efficiency standards specified in 10 CFR Part 431, as amended, which is incorporated by reference.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Each utility shall keep sufficient records to give evidence of compliance with this regulation.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, 5-303, and 7-213, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02 amended effective January 23, 1981 (8:2 Md. R. 117); March 27, 2006 (33:6 Md. R. 580); June 9, 2008 (35:8 Md. R. 808); September 21, 2009 (36:19 Md. R. 1438); May 28, 2012 (39:10 Md. R. 661); October 8, 2018 (45:20 Md. R. 920); March 20, 2023 (50:5 Md. R. 183); August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02K, L amended effective July 7, 2025 (52:13 Md. R. 657)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02M—O adopted effective July 7, 2025 (52:13 Md. R. 657)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04 amended effective April 15, 2002 (29:7 Md. R. 622); May 28, 2012 (39:10 Md. R. 661)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 adopted effective March 27, 2006 (33:6 Md. R. 580)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 amended effective June 9, 2008 (35:8 Md. R. 808)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06 adopted effective September 21, 2009 (36:19 Md. R. 1438)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06D adopted effective December 2, 2019 (46:24 Md. R. 1104)</annotation>
    </annotations>
  </chapter>
  <chapter num="03" heading="Records and Reports">
    <regulation prefix="Regulation" num=".01" heading="Availability of Records.">
      <text>All records required by these regulations or necessary for the administration thereof shall be available for examination by the Commission or its authorized representatives.</text>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Retention of Records.">
      <text>All records required by these regulations shall be preserved for the period of time specified in 18 CFR 125, as amended, which is incorporated by reference, unless otherwise specified by the Commission.</text>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Tariff.">
      <text>Each utility shall file with the Commission a copy of its tariff which shall include:</text>
      <paragraph num="A.">
        <text>Rates. Each schedule of rates for service together with the applicable riders.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Rules. The utility's rules, or terms and conditions, describing the utility's policies and practices in rendering service. These rules shall include:</text>
        <paragraph num="(1)">
          <text>Extension Plan. The utility's plan for the installation of extensions of main and service lines where these facilities are in excess of those included in the regular rates for service and for which the customer shall be required to pay all or part of the cost. The customer's payments under this plan should be related to the investment that the utility prudently can make in consideration of the probable revenue.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Voltages. A list of available voltages.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Material Furnished by Utility. A list of the items which the utility furnishes, owns, and maintains on the customer's premises, such as meters, meter sockets, service entrances, etc.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Billing Period. A statement indicating the minimum and maximum number of days for which the utility will bill a customer at its regular monthly rates for service.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Payment Period. A statement indicating the minimum number of days allowed for payment of the gross amount of the customer's bill before service will be terminated for non-payment.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Wastage of Electricity. A general statement of the utility's policy in making adjustments for wastage of electricity when an accidental ground exists without the knowledge of the customer.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Information to Be Filed with the Commission.">
      <paragraph num="A.">
        <text>Special Contracts. Each utility shall file with the Commission a copy of each contract for service not covered by the utility's filed tariff.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Installation Rules. Each utility shall file with the Commission a copy of the utility's rules, if any, designed by the utility for the use of engineers, architects, electrical contractors, etc., covering meter and service installations.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Bill Forms. Each utility shall file with the Commission a sample of each type of customer bill form, which shall include the information normally shown on a customer's bill for service.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Map of System. Each utility shall file with the Commission a map showing the utility's operating area. This map shall be revised annually unless the revision is unnecessary, in which event the utility shall notify the Commission that the map on file is current. If practicable, the map should show:</text>
        <paragraph num="(1)">
          <text>Generating stations;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Transmission lines with voltages;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Primary distribution lines;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>State boundary crossings; and</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Territorial boundary.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Persons to Contact. Each utility shall notify Commission staff, within 30 days of a change, of the name, title, address, telephone number, and email address of the person who should be contacted in connection with:</text>
        <paragraph num="(1)">
          <text>General electric distribution management duties;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Customer relations (complaints);</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Electric distribution operations;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Electric distribution planning;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Meter tests and repairs;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Emergencies during non-office hours;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>Cybersecurity; and</text>
        </paragraph>
        <paragraph num="(8)">
          <text>Regulatory contact for general inquiries.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Fatal Accident Notice. In the event of a fatal accident, prompt notice shall be given to the Commission by telephone or email.</text>
      </paragraph>
      <paragraph num="G.">
        <text>Accident Notice. Each utility shall file with the Commission an “Accident Notice” report, on forms provided by the Commission, within 30 days after the end of any month during which an accident occurred.</text>
      </paragraph>
      <paragraph num="H.">
        <text>Line Support Identification. Each.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-121, 4-202, 5-101, 5-302, and 6-203—6-210; State Government Article, §7-207(a); Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02 amended effective January 1, 1972 (Order No. 59734); March 12, 2007 (34:5 Md. R. 561)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04 amended effective September 21, 2009 (36:19 Md. R. 1438); December 2, 2019 (46:24 Md. R. 1104); August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04H amended effective September 18, 1989 (16:18 Md. R. 2024)</annotation>
    </annotations>
  </chapter>
  <chapter num="04" heading="Customer Relations">
    <regulation prefix="Regulation" num=".01" heading="Information for Customers.">
      <paragraph num="A.">
        <text>System Maps or Records. Each utility shall maintain up-to-date maps, plans, or records of its entire transmission and distribution system, with such other information as may be necessary to enable the utility to advise prospective customers, and others entitled to the information, as to the facilities available for serving a locality.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Selecting Rate Schedule. Each utility shall assist the customer or prospective customer in selecting the most economical rate schedule.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Notifying Customers. Each utility shall notify customers affected by a change in rates or schedule classification.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Tariff Notice.</text>
        <paragraph num="(1)">
          <text>A utility shall post a notice in a conspicuous place in each office of the utility where applications for service are received, informing the public that a copy of its tariff, as filed with the Commission, is available for inspection.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A utility shall post its tariff and pending tariff changes on its website.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>After Commission acceptance of a tariff change, a utility shall update the tariff posted on its website not later than 3 business days after the date of acceptance.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Meter Reading Instruction. Upon request, each utility shall inform its customers as to the method of reading meters.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Other Information. Each utility shall furnish such additional information as the customer may reasonably request.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".01-1" heading="Application for Service.">
      <paragraph num="A.">
        <text>A utility may accept either written or verbal applications for service. Each verbal application for service shall be promptly confirmed in writing by the utility. A utility may require an applicant to sign and return a copy of the written confirmation. The application shall include the:</text>
        <paragraph num="(1)">
          <text>Name, address, home and work telephone numbers, and employer of the customer of record;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Address of the premises for which electric service is requested;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Mailing address and telephone number of the customer of record if he is not an occupant of the premises for which service is requested; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Customer of record's former electric service address and the date customer moved, if applicable.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>A utility may require an applicant to sign and return a copy of the written confirmation before providing service.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Upon request of the applicant, an electric utility shall accept more than one individual customer name on applications for service. All persons named on an account shall be customers of record.</text>
      </paragraph>
      <paragraph num="D.">
        <text>When the name of the person applying for service is different from the name of the applicant, when more than one name is to be on an account, or when there is a reasonable basis for questioning the authority of a person requesting service in the name of the applicant, the utility may request that the applicant or applicants appear at the utility's designated office, present satisfactory identification, and execute a written application for service.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Customer Identification. A utility may require a customer to provide a written, signed statement attesting to an order, decree, or agreement formalizing a name change, but may not request a copy of the actual order, divorce decree, or separation agreement.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".01-2" heading="Denial of Application for Residential Service.">
      <paragraph num="A.">
        <text>Payment of Outstanding Bills.</text>
        <paragraph num="(1)">
          <text>Except as prohibited by State or federal law, a utility may refuse to provide service for a former customer unless the customer has paid, or has made satisfactory arrangements to pay, any outstanding bill, or undisputed portion of a disputed bill, for prior residential service.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A utility may not refuse service to a customer for nonpayment of an outstanding bill that is over 7 years old, unless the:</text>
          <paragraph num="(a)">
            <text>Customer signed an agreement to pay the outstanding bill before the expiration of this period; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Outstanding bill is for service obtained by the customer in any manner described in COMAR 20.31.02.03D or COMAR 20.31.02.04A(1)—(4).</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Refusal to Connect Service. A utility may refuse to connect service if an attempt to secure service is made in any manner described below. If application is made:</text>
        <paragraph num="(1)">
          <text>In a fictitious name;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>In the name of an individual who is not an occupant of the premises, without disclosure of the individual's actual address;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>In the name of a third party without disclosing that fact or without bona fide authority from the third party;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Without disclosure of a material fact or by misrepresentation of a material fact;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>For connection of service to a residence where there are co-occupants, if a service account for that dwelling unit was previously maintained in a current co-occupant's name during a period of co-occupancy with the applicant and the co-occupant has failed to pay or make satisfactory arrangements to pay an outstanding bill or undisputed portion of a disputed bill for service at the dwelling unit, the collection of which is not barred under applicable State or federal law;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>For connection of service to a dwelling unit where there are co-occupants, if the service account of a prior dwelling unit of the applicant was listed in a current co-occupant's name and the co-occupant has failed to pay or to make satisfactory arrangement to pay an outstanding bill or undisputed portion of a disputed bill for service at the prior dwelling unit, the collection of which is not barred under applicable State or federal law; or</text>
        </paragraph>
        <paragraph num="(7)">
          <text>By an individual for the purpose of assisting another occupant of a dwelling unit to avoid payment of that occupant's prior outstanding bill.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>For purposes of §B, “co-occupants” means two or more adults who occupy the same dwelling unit as their primary domicile, or legal residence within the State.</text>
      </paragraph>
      <paragraph num="D.">
        <text>For purposes of this regulation, a utility may provide service conditionally for not more than 30 days after the date of application. If, during this time, a utility discovers that an application has been made in one of the manners enumerated in this regulation, it may disconnect service in accordance with §§E and F.</text>
      </paragraph>
      <paragraph num="E.">
        <text>If a utility denies or disconnects service pursuant to this regulation, the utility shall notify the individual in writing of the reason for the denial or disconnection including the facts or circumstances upon which the utility bases its determination that service should be denied or disconnected.</text>
      </paragraph>
      <paragraph num="F.">
        <text>An individual who disputes the proposed denial or disconnection shall do so in accordance with the provisions of COMAR 20.32.01.</text>
      </paragraph>
      <paragraph num="G.">
        <text>The Commission’s Consumer Affairs Division may direct a utility to connect service, if deemed safe, in a customer’s name during the pendency of an investigation if a utility denies an application for service due to an unpaid arrearage for unauthorized use or tampering with equipment furnished and owned by the utility but does not provide the amount necessary to reconnect service within 3 business days of a filed complaint, provided that the applicant makes a payment to the utility:</text>
        <paragraph num="(1)">
          <text>In an amount that represents 2/12 of the estimated charges for service for the ensuing 12 months; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Of any outstanding prior bill or in accordance with an alternate payment plan as described in COMAR 20.31.01.08 and agreed to by the utility.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Customer Deposits.">
      <text>Each utility may require from a customer a deposit to be applied against any unpaid balance due the utility for service at the time service is terminated, in accordance with the provisions of Subtitle 30 of this title.</text>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Bill Forms.">
      <paragraph num="A.">
        <text>The bill forms shall show:</text>
        <paragraph num="(1)">
          <text>The readings of all meters used for billing purposes at the end of the period for which the bill is rendered;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The meter reading date;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The number and kind of units metered;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The applicable rate schedule, including any seasonal or time differential in base rates for the billing period in which the differential is applicable, or identification of the applicable rate schedule;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Any State or local surcharges;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>The applicable late payment charge, if any, separately stated or labelled a late payment charge, or a statement that the total amount due includes:</text>
          <paragraph num="(a)">
            <text>A late payment charge,</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An explanation of the calculation, and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The date of applicability of the late payment charge;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(7)">
          <text>The total due, including any prior unpaid amount but excluding the current late payment charge;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>The date by which the customer shall pay the bill in order to avoid a late payment charge;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>A distinct marking to identify an estimated bill;</text>
        </paragraph>
        <paragraph num="(10)">
          <text>Information concerning the customer's electricity usage during the same billing period in the prior year;</text>
        </paragraph>
        <paragraph num="(11)">
          <text>The utility's appropriate business address and telephone number for billing inquiries; and</text>
        </paragraph>
        <paragraph num="(12)">
          <text>Any conversions from meter reading units to billing units, or any calculations to determine billing units from recording or other devices, and any other factors used in determining the bill.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Rate Schedule. If the actual rates are not shown on the bill form as required in §A(4), the bill shall carry a statement to the effect that the applicable rate schedule, including the actual seasonal, or time differential, the fuel rate and the customer charge will be furnished on request.</text>
      </paragraph>
      <paragraph num="C.">
        <text>The Commission may, for good cause, grant a waiver or exemption from provisions in this regulation. A utility may request a waiver of exemption by filing an application with the Commission which sets forth the facts and reasons for the waiver or exemption.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Billing Records.">
      <paragraph num="A.">
        <text>Retention of Records. The utility shall retain customer billing records for the length of time necessary to permit the utility to comply with Regulation .05, of this chapter, but not less than 3 years.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Records For Demand Charge Customers. Records for customers whose billing includes a separate charge for a measured demand shall show:</text>
        <paragraph num="(1)">
          <text>KWH meter reading;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>KWH consumption;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>KW meter reading;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>KW measured demand;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>KW billing demand;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Net amount of the bill.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Adjustment of Bills.">
      <paragraph num="A.">
        <text>Fast Meters. Whenever a meter is tested and found to have over-registered more than 2 percent, the utility shall recalculate the bills for service of the last customer of record receiving service through the meter and shall make a refund if the amount of the adjustment exceeds $1. The refund shall be for the period that the customer received service through the meter, but for not more than the periods established below:</text>
        <paragraph num="(1)">
          <text>Known Date of Error. If the date on which the error first developed or occurred can be established, the bills for service shall be recalculated from that time.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Unknown Date of Error. If the time at which the error first developed or occurred cannot be established, it shall be assumed that the over-registration existed for a period of 3 years or a period equal to one-half of the time since the meter was last tested, whichever is less.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Slow Meters. Whenever a meter is found to be more than 2 percent slow, the utility may bill the customer one-half of the unbilled error for a period of 12 months, unless the meter has been tested within that 12-month period, in which event the utility may bill the customer one-half the unbilled error for the period since the meter was last tested. If the amount of under-registration is less than $5, the utility may not adjust the bill.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Accuracy Calculation. Billing adjustments due to fast or slow meters shall be calculated on the basis that the meter should be 100 percent accurate. For watthour meters, the average accuracy shall be the arithmetic average of the percentage registration at light load and at heavy load, giving the heavy load registration a weight of 4.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Overcharge—Undercharge Adjustment. When a customer has been overcharged or undercharged for services because of incorrect application of the rate schedule, incorrect calculation of charges, or other similar reasons, the amount of overcharge or undercharge adjustment shall be determined separately during the period of time the discrepancy occurred, in accordance with the following:</text>
        <paragraph num="(1)">
          <text>Overcharge Adjustment. The total overcharge for the period the discrepancy occurred shall be refunded or credited to the customer, except for an overcharge resulting from an incorrect reading of the meter when the amount shall automatically be corrected in a subsequent billing based on the correct meter reading.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Undercharge Adjustment.</text>
          <paragraph num="(a)">
            <text>Unless authorized by the Commission, retroactive billing may not be for undercharging which occurred more than 12 months before the discovery of the error. A utility may seek the Commission's authorization for retroactive billing for undercharges which occurred more than 12 months but not more than 3 years before the discovery of the error if the customer knew, or reasonably should have known, that the bills were in error. The utility's request to the Commission shall be in writing and shall explain the factual basis for the request to the customer with a notice of the customer's right to write to the Commission, within 20 days, if the customer is in opposition to the request.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If the total undercharge is more than 35 percent of the customer's average monthly bill during the preceding 3 months, the customer shall be allowed to enter into an installment plan to pay the total retroactive billing, without interest. In such a plan the monthly payments against the undercharge may not exceed 35 percent of the customer's average monthly bill during the preceding 3 months. However, if the installment plan will not recover within a 12-month period the total undercharge, the monthly payment may be equal to the total undercharge divided by 12 or a number greater than 12.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Unless otherwise authorized by the Commission, the utility may deny service for nonpayment only for that portion of the undercharge applicable to the 4 months immediately before the discovery of the error.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>If requested by a customer, a utility shall provide means by which any undercharge may be paid in installments over a reasonable period of time, but not less than the same period in which any undercharges were incurred.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Theft of Service.</text>
        <paragraph num="(1)">
          <text>If a meter is found not to register, in whole or in part, due to tampering or interference with the company’s material, equipment, or facilities, the utility may issue an estimated bill.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The company shall retain all information relied on to calculate the estimated bill for not less than 3 years or until the conclusion of a Commission investigation, whichever is longer.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06—.08" heading="Repealed." />
    <regulation prefix="Regulation" num=".09" heading="Customer Wiring.">
      <text>If local authorities require an inspection of a customer's wiring, the utility may not provide a customer with new or upgraded electric service until the inspecting authority certifies that the wiring conforms to the applicable code.</text>
    </regulation>
    <regulation prefix="Regulation" num=".10" heading="Investigation of Complaints.">
      <text>The utility shall investigate promptly and thoroughly any complaint concerning its charges, practices, facilities, or service.</text>
    </regulation>
    <regulation prefix="Regulation" num=".11" heading="Records of Complaints.">
      <text>The utility shall keep such records of customer complaints as will enable it to review and analyze its procedures and actions as an aid in rendering improved service.</text>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utility Companies Article, §§2-113, 2-121, 4-202, 5-101, 7-203, and 7-305, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01D amended effective September 21, 2009 (36:19 Md. R. 1438)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01-1 adopted effective November 18, 1985 (12:23 Md. R. 2224); amended effective July 28, 1986 (13:15 Md. R. 1736)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01-2 adopted effective April 21, 1986 (13:8 Md. R. 904); amended effective July 28, 1986 (13:15 Md. R. 1736)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01-2A amended effective May 10, 1993 (20:9 Md. R. 780)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01-2G adopted effective August 29, 2016 (43:17 Md. R. 957)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02 superseded effective May 28, 1970 (Order No. 58089, affecting residential customers) and October 20, 1978 (Order No. 63400, affecting all nonresidential customers)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02 amended effective January 23, 1981 (8:2 Md. R. 117)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03 amended effective November 18, 1985 (12:23 Md. R. 2224)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 amended effective November 18, 1985 (12:23 Md. R. 2224); April 21, 1986 (13:8 Md. R. 904)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05A, B amended effective October 1, 1967 (Order No. 56893)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05F adopted effective August 29, 2016 (43:17 Md. R. 957)</annotation>
      <annotation type="History" subtype="Administrative History">Regulations .06—.08 repealed effective October 14, 1991 (18:20 Md. R. 2200)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .09 amended effective June 2, 1997 (24:11 Md. R. 794)</annotation>
    </annotations>
  </chapter>
  <chapter num="05" heading="Meter Requirements">
    <regulation prefix="Regulation" num=".01" heading="Metering of Electricity.">
      <paragraph num="A.">
        <text>Customer Use. All electricity sold by a utility shall be on the basis of meter measurement, except for installations where the usage is constant and the consumption may readily be computed, or as provided for in its filed rates.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Utility Use. Wherever practicable, consumption of electricity within the utility itself, or by administrative units associated with it, shall be metered, except for installations where the usage is constant and the consumption may readily be computed.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Metering Installation.">
      <paragraph num="A.">
        <text>Condition. A meter may not be installed if it is mechanically or electrically defective, has incorrect constants, or has not been tested in accordance with the requirements of COMAR 20.50.02.02.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Capacity. The capacity of the metering installation and the index mechanism should be consistent with the electrical requirements of the customer.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Meter Multiplier.">
      <text>If it is necessary to apply a multiplier to a meter reading, the multiplier shall be marked on the face of the meter register.</text>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Demand Meter Registration.">
      <text>Demand meter installations for billing purposes should be designed, where practicable, so that the highest annual demand reading used for billing should appear in the upper half of the meter's range.</text>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Meter Reading Interval.">
      <text>Meters shall be read at approximate monthly intervals, unless otherwise authorized by the Commission.</text>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Meter Reading Records.">
      <text>The meter reading records from which bills are prepared shall show:</text>
      <paragraph num="A.">
        <text>Customer's name, address, and rate schedule;</text>
      </paragraph>
      <paragraph num="B.">
        <text>Identifying number or description of the meter;</text>
      </paragraph>
      <paragraph num="C.">
        <text>Meter readings;</text>
      </paragraph>
      <paragraph num="D.">
        <text>Date of meter reading;</text>
      </paragraph>
      <paragraph num="E.">
        <text>If the reading has been estimated;</text>
      </paragraph>
      <paragraph num="F.">
        <text>Any applicable multiplier or constant.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".07" heading="Inventory Records.">
      <text>Each utility shall maintain records of each meter and associated metering device which will identify each item as to its design, capacity, and application. The identifying information may include, as applicable: manufacturer, number, type, voltage, amperes, phase, number of wires, number of stators, disk constant (Kh), demand interval, and ratio.</text>
    </regulation>
    <regulation prefix="Regulation" num=".08" heading="History Records.">
      <text>Each utility shall maintain records for each meter and associated metering device which shall show the dates of installation and removal from service, together with the location.</text>
    </regulation>
    <regulation prefix="Regulation" num=".09" heading="Test Records.">
      <text>Each utility shall maintain test records for each meter which shall include the following:</text>
      <paragraph num="A.">
        <text>The date and reason for the test;</text>
      </paragraph>
      <paragraph num="B.">
        <text>The reading of the meter before making the test;</text>
      </paragraph>
      <paragraph num="C.">
        <text>The accuracy “as found” at light and heavy loads; and</text>
      </paragraph>
      <paragraph num="D.">
        <text>The accuracy “as left” at light and heavy loads.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utility Companies Article, §§2-121, 5-101, 7-301, and 7-302,  Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02A amended effective June 2, 1997 (24:11 Md. R. 795)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06 amended effective June 2, 1997 (24:11 Md. R. 795)</annotation>
    </annotations>
  </chapter>
  <chapter num="06" heading="Inspections and Tests">
    <regulation prefix="Regulation" num=".01" heading="Meter Shop.">
      <paragraph num="A.">
        <text>Meter Shop.</text>
        <paragraph num="(1)">
          <text>A utility shall maintain its own meter shop or use an outside meter shop, including one operated by a meter manufacturer, for testing, inspecting, or repairing a meter.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A meter shop used by a utility for testing, inspecting, or repairing meters shall be approved by the Commission and be open for inspection upon request by an authorized representative of the Commission during normal business hours.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Available Voltage. Each meter shop shall have a 3-phase voltage supply, one phase of which shall be variable from 0 volts to not less than 270 volts.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Test Table. Each meter shop shall have a test table, test bench, or other facility which will serve as a mounting for the meter test equipment and for the meter or meters under test.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Standard Watt-Hour Meters.">
      <paragraph num="A.">
        <text>Requirements. Each utility shall have the following standard watt-hour meters for the purposes indicated:</text>
        <paragraph num="(1)">
          <text>Secondary Standard. Each utility shall have at least one portable secondary standard watt-hour meter to be used to check the accuracy of the working standard watt-hour meters.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Working Standard. Each utility shall have at least one portable working standard watt-hour meter to be used to check the accuracy of watt-hour meters.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Accuracy. Each portable secondary and working standard watt-hour meter shall have a correction of not more than 0.5 percent at commonly used loads. If the correction percentage varies between successive tests by more than 0.25, a complete check shall be made to determine the cause of the variation. If the cause of variation cannot be corrected, the use of the instrument should be discontinued.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Calibration. The accuracy of the standard watt-hour meters shall be checked as indicated below:</text>
        <paragraph num="(1)">
          <text>Secondary Standards. Secondary standards shall be checked at intervals not exceeding 12 months at the National Institute of Standards and Technology (NIST) or at a laboratory acceptable to the Commission.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Working Standards. Working standards shall be checked at intervals not to exceed 12 months by comparison with a secondary standard in the utility's meter shop or other meter shop approved by the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Certificates. Each standard shall be accompanied at all times by a certificate or calibration card, duly signed and dated, on which are recorded the corrections required to compensate for errors found at the customary test points at the time of the last previous test.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Care In Handling. Extreme care shall be exercised in the use and handling of standards to assure that their accuracy is not disturbed.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Test Procedures and Accuracies.">
      <paragraph num="A.">
        <text>Procedure. The following procedures shall apply to the testing and adjusting of meters and associated devices:</text>
        <paragraph num="(1)">
          <text>General. The test of any unit of metering equipment shall consist of a comparison of its accuracy with the accuracy of a standard.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Adjusted to Zero. All meters and associated devices, when tested, shall be adjusted as closely as practicable to the condition of zero error.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Use of Tolerances. All tolerances are to be interpreted as maximum permissible variations from the condition of zero error. In making adjustments, no advantage of the prescribed tolerance limits shall be taken.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Creep. Meters may not creep, that is, there shall be no continuous rotation of the moving element of a meter at a speed in excess of one revolution in 5 minutes when the meter load wires have been removed and voltage is applied to the potential elements of the meter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Watt-Hour Meters. Watt-hour meters shall be tested at the loads and adjusted to the tolerances prescribed below:</text>
        <paragraph num="(1)">
          <text>Shop Tests.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Field Tests.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Block Interval Demand Meters. Block interval demand meters shall be tested and adjusted as prescribed below:</text>
        <paragraph num="(1)">
          <text>Test of Indicating Type. Demand meters shall be tested at a load point not less than 50 percent of full scale. However, they may be tested at a lower scale point if conditions warrant. Tests shall be continuous for at least one demand interval, or subinterval in the case of programmable demand register-equipped meters, and shall be started simultaneously with the demand interval of the demand meter.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Test of Pulse-Operated Type. Demand meters which are actuated by pulses shall be tested by transmitting enough pulses to cause the meter to register at a load point not less than 50 percent of full scale. If a pulse actuated demand meter is equipped with a device which records the number of pulses received by the meter, and if there is frequent and accurate comparison of the record with the number of kilowatt hours registered on the associated watt-hour meter, then it is not necessary to make a periodic field test of the demand meter.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Check of Pulse Devices. Pulse devices associated with demand meters shall be checked for proper operation.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Accuracy. The demand meter shall have an accuracy of within 1 percent of full scale.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Time Interval Accuracy. The total time interval, including reset time, shall be accurate within 0.5 percent, except that when a timing element also serves to keep a record of the time of day at which the demand occurs, it shall be adjusted if it is found to be in error by more than 2 minutes per day.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Adjusted to Zero. Demand meters shall be adjusted to indicate zero under no-load conditions, and shall be checked to ascertain that the meter resets to zero.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Lagged-Demand Meters. Lagged-demand meters shall be tested and adjusted as prescribed below:</text>
        <paragraph num="(1)">
          <text>Test Points. Lagged-demand meters shall be tested initially at 50 and 90 percent of full scale. Subsequent tests shall be at not less than 50 percent of full scale.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Accuracy. The lagged-demand meter shall have an accuracy within 2 percent of full scale.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Time Interval Accuracy. The interval rating of lagged-demand meters shall be checked before installation, and the time required for the demand meter to reach 90 percent of final indication, with a constant load suddenly applied, may not vary from the rated demand interval by more than 2 percent.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Adjusted to Zero. Lagged-demand meters shall be adjusted to indicate zero under no-load conditions.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Instrument Transformers. The following procedures and requirements shall apply to instrument transformers used for billing purposes:</text>
        <paragraph num="(1)">
          <text>Standard for Testing. Unless otherwise specified by the Commission, all current and potential transformers shall be tested in accordance with the procedures prescribed in American Standard Requirements, Terminology and Test Code for Instrument Transformers, ANSI C57.13.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Test Facilities. Any utility unable to perform the above test due to a lack of proper equipment may have its instrument transformers tested by another utility or approved meter shop whose testing equipment conforms to the requirements of the Commission.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Test. In lieu of utility testing of instrument transformers, the Commission will accept the certificate of test as furnished by the manufacturer.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Accuracy. Current or potential transformers may not be installed if their accuracy does not fall within the 0.6 accuracy class as defined in ANSI C57.13.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Meters For Measurement of Purchased Electricity. Utilities purchasing electricity from non-utilities or from utilities outside the State shall see that the instruments and meters which are necessary to furnish complete and accurate information as to the energy purchased are installed and tested in accordance with the requirements of the Commission.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Preinstallation Inspections and Tests.">
      <paragraph num="A.">
        <text>Authorization by Commission. A meter may be installed for use for revenue-billing purposes if it meets the following conditions:</text>
        <paragraph num="(1)">
          <text>Approved Type. Its type and design meet the requirements of COMAR 20.50.02.02.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Accuracy. The registration of the meter is within the tolerances specified in Regulation .03 of this chapter. A representative of the Commission will check the condition of meters in the meter shop of the utility from time to time by testing random samples of meters ready for installation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Test Required. Each meter and associated metering device shall be inspected and tested in the meter shop of the utility, or sample tested by the utility if 100 percent tested by the manufacturer, before being placed in service, except for instrument transformers tested in accordance with Regulation .03E(3) of this chapter.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Reinstallation. When a meter is removed from service, it shall be adjusted if necessary in order to conform to the accuracy tolerances specified in Regulation .03 of this chapter before being placed in service again. However, it may be retired without test or returned to service without being tested if it is covered by an in-service sample or periodic test plan.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Post-Installation Inspections.">
      <text>Post-installation inspections on new or upgraded service installations which incorporate instrument transformers to determine proper operation and wiring connections shall be made within 60 days after installation by a qualified person who shall be someone other than the original installer.</text>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Request Tests.">
      <paragraph num="A.">
        <text>Request For Test.</text>
        <paragraph num="(1)">
          <text>Upon request by a customer and at no charge, the utility shall test the accuracy of the meter serving the customer.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A utility may not perform a customer-requested meter test more than once during an 18-month period.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>A customer-requested test may be performed at:</text>
          <paragraph num="(a)">
            <text>The metering location;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The utility's meter shop; or</text>
          </paragraph>
          <paragraph num="(c)">
            <text>An approved meter shop.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Customer May Observe. The customer, or his representative, may be present when the meter is tested.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Report to Customer. A report of the results of the test shall be made to the customer within a reasonable time after the completion of the test, and a record of the report, together with a complete record of the test, shall be kept on file at the office of the utility for at least 3 years.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".07" heading="Referee Tests.">
      <paragraph num="A.">
        <text>Application for Test. Upon written application to the Commission by a customer or a utility, a test will be made of the customer's meter as soon as practicable by a representative of the Commission.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Deposit for Test. The application shall be accompanied by a deposit as indicated below:</text>
        <paragraph num="(1)">
          <text>Watt-hour meter --------------------------------------------- $10;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Combination watt-hour and demand meter -------------- $20.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Notice to Utility. On receipt of the request from a customer, the Commission will notify the utility and the utility may not knowingly remove or adjust the meter until instructed by the Commission. The utility shall furnish to the Commission's representative such reasonable assistance as may be required to make the test.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Customer May Observe. The customer, or his representative, may be present when the meter is tested.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Report to Customer. A written report of the results of the test will be sent to the customer and to the utility.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Disposition of Deposit. If the meter is found to over-register more than 2 percent, calculated in accordance with COMAR 20.50.04.05C, the deposit shall be refunded by the Commission and the utility billed the amount of the deposit. If the meter is found to be not more than 2 percent fast, the deposit will be retained and disposed of according to law.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".08" heading="As Found Tests.">
      <text>Each meter shall be tested before the meter is adjusted or repaired.</text>
    </regulation>
    <regulation prefix="Regulation" num=".09" heading="In-Service Performance Tests.">
      <paragraph num="A.">
        <text>Test Program. In-service performance tests shall be made in accordance with the requirements of COMAR 20.50.02.02.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Location of Tests. In-service performance tests may be made on the customer's premises, in the utility's meter shop, or in an approved meter shop.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Tests for Other Purposes. Tests, such as request or referee tests, which are made for purposes other than to determine the in-service performance of a group of meters, may not be counted as in-service performance tests, except for those groups of meters being tested under the Periodic Test Schedule.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Periodic Test Schedule. Periodic tests shall be scheduled in accordance with the requirements of COMAR 20.50.02.02.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".10" heading="Instrument Transformer Tests.">
      <paragraph num="A.">
        <text>Preinstallation Test. All instrument transformers used for billing purposes shall conform to the requirements of Regulation .03E of this chapter before being placed in service.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Current Transformers. Current transformers should be tested with a suitable variable burden device to determine if the windings of the secondary circuit have developed an open circuit, short circuit, or unwanted grounds.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Potential Transformers. Potential transformers should be tested by measuring the secondary voltage to reveal defects in the transformer or secondary circuit which appreciably affect accuracies.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Performance Test. If there is any evidence that an instrument transformer is inaccurate or has been damaged to the extent that its performance has been impaired, it shall be tested to determine whether it should be replaced.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".11" heading="Generating Station Meter Tests.">
      <text>Generator output watt meters and watt-hour meters in the utility's generating station shall be tested according to a suitable schedule by comparison with the utility's standards but may not exceed the appropriate test intervals as required under COMAR 20.50.02.02.</text>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-121, 5-101, 7-301, and 7-302, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulations .04A and .07F amended effective October 1, 1967 (Order No. 56893)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04 amended effective January 23, 1981 (8:2 Md. R. 117)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .07B amended effective September 2, 1991 (18:17 Md. R. 1921)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 2, 1997 (24:11 Md. R. 795)</annotation>
    </annotations>
  </chapter>
  <chapter num="07" heading="Quality of Service">
    <regulation prefix="Regulation" num=".01" heading="Standard Frequency.">
      <text>The standard frequency for alternating current distribution systems shall be either 60 cycles per second or 25 cycles per second.</text>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Voltage Limits.">
      <paragraph num="A.">
        <text>Secondary Voltages. The voltage at the utility's service terminals, as installed for each customer, shall be maintained within the Limits specified in the table below. If a utility adopts any standard voltage not included in the table, it shall advise the Commission in order that the Commission may establish appropriate voltage limits. When 3-phase service is provided, the utility shall exercise reasonable care to assure that the phase voltages are balanced.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Primary Voltages. The following limits shall apply where the utility supplies service at primary voltage:</text>
        <paragraph num="(1)">
          <text>Industrial Customers. For service rendered principally for industrial or power purposes, the voltage may not exceed 7-1/2 percent above or 7-1/2 percent below the standard nominal voltages as filed in the utility's rules.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Sales For Resale. For service rendered to public utilities and others for resale, the nominal voltage shall be as mutually agreed upon by the parties concerned. The allowable voltage may not exceed 7-1/2 percent above or 7-1/2 percent below the agreed upon nominal voltage without the express approval of the Commission.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Special Contract Exceptions. The limitations in §§B(1) and B(2), of this regulation, do not apply to special contracts in which the customer specifically agrees to accept service with unregulated voltage.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Exceptions to Voltage Requirements. It will not be considered a violation when voltages outside of the prescribed limits are caused by any of the following:</text>
        <paragraph num="(1)">
          <text>Action of the elements;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Service interruptions;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Temporary separation of parts of the system from the main system;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Infrequent fluctuations not exceeding 5 minutes' duration; or</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Other causes beyond the control of the utility.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Voltmeters.">
      <paragraph num="A.">
        <text>Requirements. Each utility shall have the following voltmeters for the purposes indicated:</text>
        <paragraph num="(1)">
          <text>Secondary Standard. Each utility shall have at least one secondary standard indicating voltmeter to be used in checking the accuracy of working standard voltmeters.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Working Standards. Each utility shall have at least two working standard indicating voltmeters to be used in checking the voltage on the utility's electric system and in checking the accuracy of recording voltmeters.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Recording Voltmeters. Each utility shall have at least two portable recording voltmeters to be used to record the voltage on the utility's electric system.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Accuracy. The voltmeters shall be of sufficient quality to meet the accuracy standards prescribed below:</text>
        <paragraph num="(1)">
          <text>Secondary Standard. The secondary standard indicating voltmeter shall have a stated accuracy within 0.25 percent of full scale. This instrument shall be maintained within its stated accuracy.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Working Standards. The working standard indicating voltmeters shall have a stated accuracy within 0.75 percent of full scale.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Recording Voltmeters. The portable recording voltmeters shall have a stated accuracy within 1.5 percent of full scale.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Calibration. The accuracy of the voltmeters shall be checked as indicated below:</text>
        <paragraph num="(1)">
          <text>Secondary Standard. Secondary standards shall be checked at intervals not exceeding 3 years at the National Bureau of Standards, or at a laboratory acceptable to the Commission.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Working Standards. Working standards shall be checked at intervals not exceeding 3 years by comparison with a secondary standard in the utility's meter shop.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Certificates. Each standard shall be accompanied at all times by a certificate or calibration card, duly signed and dated, on which are recorded the corrections required to compensate for errors found at the customary test points at the time of the last calibration test.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Care In Handling. Extreme care shall be exercised in the handling of standards and other instruments to assure that their accuracy is not disturbed.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Voltage Surveys and Records.">
      <paragraph num="A.">
        <text>Voltage Surveys. Each utility shall make voltage measurements, using recording voltmeters, in order to determine if voltages are in compliance with the requirements contained in Regulation .02.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Point of Measurement. Voltage measurements shall be made at the utility's service terminals. For single phase service, the measurement shall be made between the grounded conductor and the ungrounded conductors. For 3 phase service, the measurement shall be made between the phase wires.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Voltage Records. All voltmeter records obtained under §A, above, shall be retained by the utility for at least 2 years and shall be available for inspection by the Commission's representatives. Notations on each chart shall indicate the following:</text>
        <paragraph num="(1)">
          <text>Location where the voltage was taken;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Time and date of the test;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Results of the comparison of the recording voltmeter with an indicating voltmeter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Record of Corrective Action. If action is taken to correct the voltage conditions, the chart which records the voltage subsequent to the change shall be attached to the first chart so that the conditions before and after the change may be reviewed.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Interruption of Service.">
      <paragraph num="A.">
        <text>Endeavor to Avoid Interruptions. Each utility shall make reasonable efforts to avoid interruptions of service, but when interruptions occur, service shall be re-established within the shortest time practicable, consistent with safety.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Report to Commission.</text>
        <paragraph num="(1)">
          <text>Each utility shall promptly report to the Commission's Engineering Division and Consumer Affairs Division:</text>
          <paragraph num="(a)">
            <text>The onset of a major outage event;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A sustained interruption, to firm-service customers, initiated by the utility in response to unacceptable system voltages; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A sustained interruption, to firm-service customers, initiated by the utility in response to thermal overloads of electric plant.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>The utility's report required by §B(1) of this regulation shall include a general description of the areas experiencing a sustained interruption and the expected system restoration times, if available.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The utility making the report required by §B(1) of this regulation shall also provide periodic updates to the Consumer Affairs Division.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Planned Interruptions. Planned interruptions shall be made at a time that will not cause unreasonable inconvenience to customers and shall be preceded, if feasible, by adequate notice to those who will be affected.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Record of Interruptions. Each utility shall keep records of interruptions of service on its primary distribution system and shall make an analysis of the records for the purpose of determining steps to be taken to prevent recurrence of the interruptions. The records should include the following information concerning the interruptions:</text>
        <paragraph num="(1)">
          <text>Cause;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Date and time; and</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Duration.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Momentary Interruption Record. A utility shall maintain information which it collects on momentary interruptions for 5 years.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Unattended Substations. The record for each unattended substation shall show interruptions which required attention to restore service, with the estimated time of interruption.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-121, 5-101, and 5-303, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03C amended effective June 6, 2005 (32:11 Md. R. 983)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 amended effective April 15, 2002 (29:7 Md. R. 622)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05B amended effective May 28, 2012 (39:10 Md. R. 661)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06 adopted effective April 15, 2002 (29:7 Md. R. 622)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06 repealed effective May 28, 2012 (39:10 Md. R. 661)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .07 adopted effective April 15, 2002 (29:7 Md. R. 622)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .07 repealed effective May 28, 2012 (39:10 Md. R. 661)</annotation>
    </annotations>
  </chapter>
  <chapter num="08" heading="Safety">
    <regulation prefix="Regulation" num=".01" heading="Protective Measures.">
      <paragraph num="A.">
        <text>Exercise Reasonable Care. Each utility shall exercise reasonable care to reduce the hazards to which its employees, its customers, and the general public may be subjected.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Investigation by Commission. The utility shall give reasonable assistance to the Commission in the investigation of the cause of accidents and in the determination of suitable means of preventing accidents.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Record of Accidents. Each utility shall maintain a summary of all reportable accidents arising from its operations.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Safety Program.">
      <paragraph num="A.">
        <text>Adopt Safety Program. Each utility shall adopt and execute a safety program, fitted to the size and type of its operations.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Use Suitable Tools and Equipment. Each utility should require its employees to use suitable tools and equipment in order that they may perform their work in a safe manner.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Promote Safe Work Methods. Each utility should instruct its employees in safe methods of performing their work.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Instruct In Artificial Respiration. Each utility should instruct its employees who, in the course of their work, are subject to the hazard of electrical shock or drowning, in accepted methods of artificial respiration.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Grounding of Secondary Distribution System.">
      <paragraph num="A.">
        <text>Standard Codes. Each utility shall use the applicable provisions in the National Electrical Safety Code and the National Electrical Code, which have been incorporated by reference in COMAR 20.50.02.02, for the grounding of secondary circuits and equipment.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Testing Grounds. Artificial grounds not connected to a multigrounded system shall be tested for ground resistance at the time of installation.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Records of Tests. Records shall be kept of all ground resistance tests made in accordance with §B, above.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Inspection of Grounds. The utility shall establish a program of inspection to insure that artificial grounds are in good mechanical and electrical condition.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">State Government Article, §7-207; Public Utilities Article, §§2-113, 2-121, 5-101, 5-303, and 5-304; Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 22, 1942 (Order No. 38330)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective May 18, 1960 (Order No. 54348)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective June 1, 1965 (Order No. 55819)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03A amended effective March 12, 2007 (34:5 Md. R. 562)</annotation>
    </annotations>
  </chapter>
  <chapter num="09" heading="Small Generator Facility Interconnection Standards">
    <regulation prefix="Regulation" num=".01" heading="Scope.">
      <paragraph num="A.">
        <text>This chapter applies to a small generator facility seeking to interconnect and operate in parallel with the electric distribution system. All small generator facilities shall interconnect under requirements in this chapter or under the physical interconnection requirements of the PJM Interconnection, LLC under the authority of FERC.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A small generator facility seeking to interconnect and operate in parallel with the electric distribution system under this chapter shall meet one of the following criteria:</text>
        <paragraph num="(1)">
          <text>The small generator facility is a qualifying facility pursuant to the Public Utility Regulatory Policies Act that intends to make sales at a rate approved by the Maryland Commission;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The small generator facility is not a qualifying facility pursuant to the Public Utility Regulatory Policies Act and does not intend to make sales of wholesale electric energy through the PJM Interconnection, LLC;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The small generator facility intends to make sales of wholesale electric energy through the PJM Interconnection, LLC at an electric distribution interconnection facility where there has been no prior FERC jurisdictional service;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The small generator facility intends to make sales of wholesale electric energy through the PJM Interconnection, LLC only at an electric distribution interconnection facility through participation in a distributed energy resource aggregation; or</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The small generator facility will be interconnected to an electric distribution circuit and its energy will not be transmitted across state lines for a wholesale customer other than the electric distribution owner.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Market processes under FERC jurisdiction that are administered by the PJM Interconnection, LLC may not impede the interconnection timeline requirements in this chapter unless the utility has good cause to believe that equipment upgrades exceeding minor equipment modifications and related modifications to the interconnection agreement will be needed to facilitate these market processes. In these cases, the utility shall notify the interconnection customer in writing of their rationale to delay approval of the interconnection request until the conclusion of the PJM Interconnection, LLC's market process study.</text>
      </paragraph>
      <paragraph num="D.">
        <text>In situations where an interconnected small generator facility project intends to change their energy sales strategy from market processes under FERC jurisdiction to retail processes under this chapter, the small generator facility shall submit an interconnection request.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Definitions.">
      <paragraph num="A.">
        <text>In this chapter, the following terms have the meanings indicated.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Terms Defined.</text>
        <paragraph num="(1)">
          <text>“AC EVSE” means supply equipment that passes alternating current to the EV with conversion between AC and DC accomplished onboard the EV.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>“Adverse system impact” means a negative effect, due to technical or operational limits on conductors or equipment being exceeded, that may compromise the safety or reliability of the electric distribution system.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>“Affected system” means a utility electric system that is affected by the interconnection of a small generator facility to another utility’s electric distribution system.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>“Aggregate generation” means the aggregated net system capacities of all small generator facilities across multiple points of common coupling.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>“Applicant” means a person who has submitted an interconnection request to interconnect a small generator facility to a utility's electric distribution system.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>“Area network” means a type of electric distribution system served by multiple transformers interconnected in an electrical network circuit, often used in large, densely populated metropolitan areas.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>“Bidirectional electric vehicle” has the meaning stated in Public Utilities Article, §7-1001(c), Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>“Certificate of completion” means a certificate provided by a utility to an applicant containing information about the interconnection equipment used, its installation, and local inspections.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>“Closed circuit” means an electric distribution system circuit with no available hosting capacity.</text>
        </paragraph>
        <paragraph num="(10)">
          <text>“Commissioning test” means one of several tests applied to a small generator facility by the applicant after construction is completed to verify that the small generator facility does not create adverse system impacts, including the test specified in Section 5.4 of IEEE Standard 1547.</text>
        </paragraph>
        <paragraph num="(11)">
          <text>“DC EVSE” means supply equipment that passes direct current to or from the EV, with the EVSE accomplishing conversion between AC and DC.</text>
        </paragraph>
        <paragraph num="(12)">
          <text>“Default utility required inverter settings profile” means a utility set of default smart inverter settings optimized for use across a utility’s service territory.</text>
        </paragraph>
        <paragraph num="(13)">
          <text>“Distributed energy resource” means any geographically dispersed energy resource located on an electric distribution system that produces electricity or offsets electrical demand including small generator facilities, energy storage devices, energy efficiency devices, and demand response devices.</text>
        </paragraph>
        <paragraph num="(14)">
          <text>“Distribution upgrade” means a required addition or modification to the utility electric distribution system, excluding the interconnection facilities, necessary to accommodate the interconnection of a small generator facility.</text>
        </paragraph>
        <paragraph num="(15)">
          <text>“Draw-out type circuit breaker” means a molded case switching device that:</text>
          <paragraph num="(a)">
            <text>Can be inserted into or removed from its enclosure during no-load conditions; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Is capable of making, carrying, and breaking currents under normal and abnormal circuit conditions.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(16)">
          <text>Electric Distribution System.</text>
          <paragraph num="(a)">
            <text>“Electric distribution system” means the facilities and equipment used to transmit electricity generally at less than 69 kV to ultimate usage points such as homes and industries from interchanges with higher voltage transmission networks that transport bulk power over longer distances.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Electric distribution system” has the same meaning as the term Area EPS as defined in Section 3.1.6.1 of IEEE Standard 1547.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(17)">
          <text>“Electric vehicle” or “EV” means a vehicle that employs electrical energy as a primary or secondary mode of propulsion and is capable of charging the onboard battery from an external supply of electricity.</text>
        </paragraph>
        <paragraph num="(18)">
          <text>“Electric vehicle supply equipment” or “EVSE” means a device or system designed and used specifically to transfer electrical energy between an electric vehicle and the electric grid.</text>
        </paragraph>
        <paragraph num="(19)">
          <text>“Energy Storage Device” means a piece of equipment that captures energy produced at one time, stores that energy for a period of time, and delivers that energy as electricity at a future time.</text>
        </paragraph>
        <paragraph num="(20)">
          <text>“Fault current” means the electrical current that flows through a circuit during an electrical fault condition, such as when one or more electrical conductors contact ground or each other.</text>
        </paragraph>
        <paragraph num="(21)">
          <text>“Grid support services” means compensated or uncompensated services unrelated to wholesale markets provided by a small generator facility that support the safety, stability, reliability, or economics of the electric grid.</text>
        </paragraph>
        <paragraph num="(22)">
          <text>“Hosting capacity” means the amount of aggregate generation that can be accommodated on an electric distribution system or area, or a system component, without requiring infrastructure upgrades.</text>
        </paragraph>
        <paragraph num="(23)">
          <text>“Hosting capacity reporting system” means the information available on a utility website providing reports, tabular data, or maps of hosting capacity available on the electric distribution system.</text>
        </paragraph>
        <paragraph num="(24)">
          <text>“Hosting capacity upgrade plan” means a utility plan to promote clean energy interconnection for a particular area or a proposal to open multiple restricted and closed circuits or areas on an electric system in the aggregate through proactive distribution system investments that includes a cost allocation and recovery proposal, under conditions that are approved by the Commission.</text>
        </paragraph>
        <paragraph num="(25)">
          <text>“IEEE Standard 1547” means the standard incorporated by reference in COMAR 20.50.02.02.</text>
        </paragraph>
        <paragraph num="(26)">
          <text>“IEEE Standard 1547.1” means the standard incorporated by reference in COMAR 20.50.02.02.</text>
        </paragraph>
        <paragraph num="(27)">
          <text>“Inadvertent export” means the unscheduled export of power from a small generator facility, beyond a specified magnitude and for a limited duration, generally due to fluctuations in load-following behavior.</text>
        </paragraph>
        <paragraph num="(28)">
          <text>“Interconnection agreement” means an agreement that contains details regarding the proposed interconnection equipment and its operation to ensure the reliability and safety of the grid, including schedules, rights, obligations, and terms and conditions that become effective on the date the agreement is executed by the utility and the interconnection customer.</text>
        </paragraph>
        <paragraph num="(29)">
          <text>“Interconnection customer” means an entity that proposes to interconnect or has interconnected a small generator facility to an electric distribution system.</text>
        </paragraph>
        <paragraph num="(30)">
          <text>Interconnection Equipment.</text>
          <paragraph num="(a)">
            <text>“Interconnection equipment” means a group of components or an integrated system connecting an electric generator with a local electric power system, or an electric distribution system.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Interconnection equipment” means all interface equipment including switchgear, protective devices, inverters, or other interface devices.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>“Interconnection equipment” includes equipment installed as part of an integrated equipment package that includes a generator or other electric source.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(31)">
          <text>Interconnection Facilities.</text>
          <paragraph num="(a)">
            <text>“Interconnection facilities” means facilities and equipment required by the utility to accommodate the interconnection of a small generator facility.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Interconnection facilities” includes all facilities and equipment between the small generator facility and the point of interconnection, and modifications, additions, or upgrades that are necessary to physically and electrically interconnect the small generator facility to the electric distribution system.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>“Interconnection facilities” includes any distribution upgrade.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(32)">
          <text>“Interconnection facility cost sharing” means the allocation of distribution interconnection facility upgrade costs among multiple small generator facility projects that utilize the hosting capacity created by an interconnection facility upgrade.</text>
        </paragraph>
        <paragraph num="(33)">
          <text>“Interconnection request” means an applicant's request for the interconnection of a small generator facility, or to increase the capacity or operating characteristics of a small generator facility that is already interconnected with the utility's electric distribution system.</text>
        </paragraph>
        <paragraph num="(34)">
          <text>“Interconnection study” means an interconnection feasibility study, interconnection system impact study, or interconnection facilities study as described in Regulation .12 of this chapter.</text>
        </paragraph>
        <paragraph num="(35)">
          <text>“Limited export agreement” means an agreement for energy supplied to the grid by an interconnection customer that may be managed to specified ramp rates and generation levels for operating conditions, as specified in the interconnection agreement or in a separate limited export agreement.</text>
        </paragraph>
        <paragraph num="(36)">
          <text>“Line section” means that portion of a utility electric distribution system connected to an interconnection customer, bounded by automatic sectionalizing devices, or the end of the distribution line.</text>
        </paragraph>
        <paragraph num="(37)">
          <text>Local Electric Power System.</text>
          <paragraph num="(a)">
            <text>“Local electric power system” means those facilities that deliver electric power to a load that are contained entirely within a single premises or group of premises.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Local electric power system” has the same meaning as the term local electric power system as defined in Section 3.1.6.2 of IEEE Standard 1547.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(38)">
          <text>“Meter collar adapter” means an electronic device that is installed between a residential electric meter and the meter socket, for the purpose of facilitating the deployment of customer-owned or customer-leased technology.</text>
        </paragraph>
        <paragraph num="(39)">
          <text>“Minor equipment modification” means a change to the proposed small generator facility that does not have a significant impact on safety or reliability of the electric distribution system.</text>
        </paragraph>
        <paragraph num="(40)">
          <text>“Minor system modification” means a change to the distribution system:</text>
          <paragraph num="(a)">
            <text>Located between the service tap on the distribution circuit and the meter serving the applicant; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>That the utility estimates will entail less than 4 hours of work and less than $1,500 in materials.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(41)">
          <text>“Nameplate capacity” means the maximum rated output of a generator at a point of common coupling of all electric power production equipment or energy storage devices under specific conditions designated by the manufacturer that is usually listed on a nameplate physically attached to the equipment.</text>
        </paragraph>
        <paragraph num="(42)">
          <text>“Nationally recognized testing laboratory (NRTL)” means a qualified private organization recognized by the Occupational Safety and Health Administration to perform independent safety testing and product certification.</text>
        </paragraph>
        <paragraph num="(43)">
          <text>“Net system capacity” means the total export capacity at a point of common coupling of a small generator facility as measured by the nameplate capacities of all power production units and energy storage devices minus their consumption of electrical power, if applicable, as limited through the use of a control system, power relays, or other similar device settings or adjustments.</text>
        </paragraph>
        <paragraph num="(44)">
          <text>“Parallel operation” means the sustained state of operation over 100 milliseconds which occurs when a small generator facility is connected electrically to the electric distribution system, and thus has the ability for electricity to flow from the small generator facility to the electric distribution system.</text>
        </paragraph>
        <paragraph num="(45)">
          <text>“Permission to operate notice” means the written permission provided by a utility in the form of an email or letter authorizing an interconnection customer to interconnect and operate its small generator interconnection facility.</text>
        </paragraph>
        <paragraph num="(46)">
          <text>“Point of common coupling” means the point of interconnection where the small generator facility is electrically connected to the electric distribution system.</text>
        </paragraph>
        <paragraph num="(47)">
          <text>“Point of interconnection” has the same meaning as the term “point of common coupling”.</text>
        </paragraph>
        <paragraph num="(48)">
          <text>“Primary line” means a distribution line rated at greater than 600 volts.</text>
        </paragraph>
        <paragraph num="(49)">
          <text>“Primary voltage hosting capacity upgrade cost” means the equipment upgrade costs of all interconnection equipment, interconnection facilities, protective devices and associated communications systems, and other upgrades that directly increase hosting capacity for multiple primary voltage and secondary voltage interconnection customers while excluding equipment upgrade costs that solely benefit a single interconnection customer, to the extent practicable and material.</text>
        </paragraph>
        <paragraph num="(50)">
          <text>“Primary voltage interconnection customer” means an interconnection customer with a point of interconnection at greater than 600 nominal volts.</text>
        </paragraph>
        <paragraph num="(51)">
          <text>Proposed Use.</text>
          <paragraph num="(a)">
            <text>“Proposed use” means the operational control modes of a small generator facility upon which the applicant’s technical review is based and under which the small generator facility is bound to operate upon the execution of the interconnection agreement.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Proposed use” for a small generator facility includes a combination of electric generators and energy storage devices operating in specified operational control modes during specified time periods.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(52)">
          <text>“Queue position” means the order of a completed interconnection request, relative to all other pending completed interconnection requests, that is established based upon the date and time of receipt of the completed interconnection request by the utility.</text>
        </paragraph>
        <paragraph num="(53)">
          <text>“Radial distribution circuit” means a circuit configuration in which independent feeders branch out radially from a common source of supply.</text>
        </paragraph>
        <paragraph num="(54)">
          <text>“Reserve hosting capacity” means the amount of hosting capacity reserved for small generator facilities on an electric distribution system circuit.</text>
        </paragraph>
        <paragraph num="(55)">
          <text>“Restricted circuit” means an electric system distribution circuit with reserve hosting capacity.</text>
        </paragraph>
        <paragraph num="(56)">
          <text>“Rightsizing” means to increase the size, scope, and cost of an electric utility hosting capacity upgrade project, following a distributed energy resource interconnection request, to account for both the immediate interconnection customer’s needs and future hosting capacity needs that are identified by the electric utility through a distributed energy resource forecast.</text>
        </paragraph>
        <paragraph num="(57)">
          <text>“Scoping meeting” means a meeting between the applicant and utility conducted for the purpose of discussing alternative interconnection options, exchanging information, including any electric distribution system data and earlier study evaluations that would be reasonably expected to impact interconnection options, analyzing information, and determining the potential feasible points of interconnection.</text>
        </paragraph>
        <paragraph num="(58)">
          <text>“Secondary line” means a service line subsequent to the primary line that is rated for 600 volts or less, also referred to as the customer's service line.</text>
        </paragraph>
        <paragraph num="(59)">
          <text>“Secondary voltage hosting capacity upgrade cost” means the costs of all primary voltage and secondary voltage interconnection equipment upgrades that directly increase secondary voltage hosting capacity available to multiple secondary voltage interconnection customers while excluding all primary voltage and secondary voltage interconnection equipment upgrade costs that solely benefit a single interconnection customer, to the extent practicable and material.</text>
        </paragraph>
        <paragraph num="(60)">
          <text>“Secondary voltage interconnection customer” means an interconnection customer with a point of interconnection at less than or equal to 600 nominal volts.</text>
        </paragraph>
        <paragraph num="(61)">
          <text>“Shared transformer" means a transformer that supplies secondary source voltage to more than one customer.</text>
        </paragraph>
        <paragraph num="(62)">
          <text>“Site-specific utility required inverter settings profile” means a set of smart inverter settings optimized for use at a specific site on a utility’s electric system.</text>
        </paragraph>
        <paragraph num="(63)">
          <text>Small Generator Facility.</text>
          <paragraph num="(a)">
            <text>“Small generator facility” means the equipment used to generate or store electricity that operates in parallel with the electric distribution system.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Small generator facility” includes an electric generator, a prime mover, energy storage device, and the interconnection equipment required to safely interconnect with the electric distribution system or local electric power system.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(64)">
          <text>“Smart Inverter” means any inverter hardware system certified to be compliant with IEEE 1547-2018 or subsequent revisions to these standards.</text>
        </paragraph>
        <paragraph num="(65)">
          <text>Spot Network.</text>
          <paragraph num="(a)">
            <text>“Spot network” means a type of electric distribution system that uses two or more inter-tied transformers to supply an electrical network circuit.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Spot network” is generally used to supply power to a single customer or a small group of customers.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>“Spot network” has the same meaning as the term is defined in 4.1.4 of IEEE Standard 1547.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(66)">
          <text>“Statewide utility required inverter settings profile” or “grid code” means a set of smart inverter settings optimized for use Statewide that can be used by utilities and manufacturers in establishing defaults.</text>
        </paragraph>
        <paragraph num="(67)">
          <text>“Technical interconnection requirement” or “TIR” means a public-facing document available on an electric company's website that specifies interconnection technical review criteria and distributed energy resource functional settings.</text>
        </paragraph>
        <paragraph num="(68)">
          <text>“Utility monitoring and control plan” means a plan to monitor and control, in the aggregate, a set of small generator facilities in multiple locations that includes a cost recovery method, under conditions that are approved by the Commission.</text>
        </paragraph>
        <paragraph num="(69)">
          <text>“Utility required inverter settings profile” means smart inverter settings for a small generator facility that are established by a utility.</text>
        </paragraph>
        <paragraph num="(70)">
          <text>“V1G or managed charging” means a range of approaches from utility programs and rate design to incentivize ratepayers for varying the time or rate at which an electric vehicle is charged.</text>
        </paragraph>
        <paragraph num="(71)">
          <text>“V1G Ready EVSE” is an EVSE that is capable of controlled charging rate operation but is either not certified for or is certified for but not programmed or configured for bidirectional operation.</text>
        </paragraph>
        <paragraph num="(72)">
          <text>“V2G or vehicle-to-grid” means the ability for an EVSE connected to a bidirectional electric vehicle to operate in parallel to the grid and both receive and feed power to the point of interconnection between the EVSE and the grid.</text>
        </paragraph>
        <paragraph num="(73)">
          <text>“V2G Ready EVSE” is an AC EVSE or DC EVSE, is certified for and programmed or configured for bidirectional operation as part of a V2G system in parallel with the electric grid.</text>
        </paragraph>
        <paragraph num="(74)">
          <text>“V2G System” is a combination of hardware and software in or around the EVSE and EV for the purposes of communication with and programmed flow of energy into and out of the vehicle battery in support of electrical loads or systems offboard the EV, including the electric grid.</text>
        </paragraph>
        <paragraph num="(75)">
          <text>“Witness test” means, for lab-certified or field-approved equipment, verification either by an on-site observation or review of documents by the utility that the interconnection installation evaluation required by Section 5.3 of IEEE Standard 1547 and the commissioning test required by Section 5.4 of IEEE Standard 1547 have been adequately performed.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Acceptable Standards.">
      <text>The technical standard to be used in evaluating all interconnection requests under Level 1, Level 2, Level 3, and Level 4 reviews, unless otherwise provided for in this chapter, is IEEE Standard 1547.</text>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Interconnection Requests.">
      <paragraph num="A.">
        <text>Applicants seeking to interconnect a small generator facility shall submit an interconnection request to the utility that owns the electric distribution system to which interconnection is sought.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An interconnection request shall be in the form and format specified by the utility that owns the electric distribution system to which interconnection is sought and shall include the following information and any additional information that may be reasonably requested by the utility:</text>
        <paragraph num="(1)">
          <text>Contact information for the interconnection customer;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Existing utility account information;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Location information for the small generator facility;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Contact information for the interconnection customer’s equipment and electrical contractors;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Information on the manner in which the interconnection customer intends to use the small generator facility;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Requested review level for interconnection request;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>Technical information regarding the generator and prime mover;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>Technical information regarding the interconnection components and system or systems;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>Location and other information regarding disconnect switch for small generator facility;</text>
        </paragraph>
        <paragraph num="(10)">
          <text>Details regarding any plans to export power to the electric distribution system; and</text>
        </paragraph>
        <paragraph num="(11)">
          <text>Any other item specified by the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Each utility shall make reasonable efforts to align the content of its interconnection request form with those forms provided by other utilities in Maryland.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Each utility shall establish a process that allows an applicant and an applicant’s authorized designee to:</text>
        <paragraph num="(1)">
          <text>Sign and submit an interconnection request electronically on the utility’s website;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Track the status of the interconnection request electronically; and</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Conduct electronically any other process that can reasonably occur in that manner.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Interconnection Request Processing Fees.">
      <paragraph num="A.">
        <text>A utility may only charge a small generator interconnection request fee for a Level 2, Level 3, or Level 4 interconnection request.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A utility may not charge interconnection request fees for interconnection requests determined to be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of this chapter.</text>
      </paragraph>
      <paragraph num="C.">
        <text>The utility shall specify the interconnection [processing] request fees charged under this regulation in its tariff.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="General Requirements.">
      <paragraph num="A.">
        <text>For small generator facilities at a site for which the applicant seeks a single point of interconnection, the interconnection request shall be evaluated for total exports on the basis of the net system capacity.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An interconnection request is required for the interconnection of a new small generator facility, or to increase the total exports, change the energy sales strategy pursuant to Regulation .01C of this chapter, or change the proposed use of an existing small generator facility. Any time a new interconnection request is processed for an existing small generator facility, the utility will apply any standards in effect at the time of the interconnection request and, if approved, a new interconnection agreement will be required. The interconnection request shall be evaluated on the basis of the total net system capacity of the small generator facility.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Utility Provided Information.</text>
        <paragraph num="(1)">
          <text>A utility shall designate a contact person, and provide contact information on its website and for the Commission's website for submission of all interconnection requests, and from whom information on the interconnection request process and the utility's electric distribution system can be obtained.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The information provided by the utility on its website shall include studies and other materials useful to an understanding of the feasibility of interconnecting a small generator facility on the utility electric distribution system, except to the extent providing the materials would violate security requirements or confidentiality agreements, or be contrary to law.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>For projects with a nameplate capacity over 20kW, the utility shall:</text>
          <paragraph num="(a)">
            <text>Provide the applicant an opportunity to request a pre-application report, which may require payment of a fee listed in the utility’s tariff;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Publicly post the fee amount on the utility’s website; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Provide the pre-application report within 20 business days, once the fee is paid.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>The pre-application report shall rely largely on pre-existing utility data and shall, at a minimum, include the following items:</text>
          <paragraph num="(a)">
            <text>Initial proposed point of interconnection of the small generator facility, including address or GIS coordinates;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Closest electrical facilities to the initial proposed point of interconnection of the small generator facility, including voltage level, feeder identification, substation, and including distance to that substation;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Amount of generation hosting capacity available on the closest feeder, if this information is in possession of or easily obtainable by the utility; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Any other items specified by the Commission.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>In appropriate circumstances, the utility may require an applicant to execute an appropriate confidentiality agreement prior to release or access to confidential or restricted information.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>If an interconnection request is determined to be complete, any material modification, other than a minor equipment modification, that is not agreed to in writing by the utility, shall require submission of a new interconnection request.</text>
      </paragraph>
      <paragraph num="E.">
        <text>If an applicant is not currently a customer of the utility at the location for the proposed small generator facility, upon request from the utility, the applicant shall provide proof of site control evidenced by a property tax bill, deed, lease agreement, contract, or other acceptable document.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Connection of Multiple Small Generator Facilities by Single Interconnection.</text>
        <paragraph num="(1)">
          <text>To minimize the cost of interconnecting multiple small generator facilities, the utility or the applicant may propose a single point of interconnection for multiple small generator facilities located at a single site.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If an applicant rejects a utility proposal for a single point of interconnection, the applicant shall pay any additional cost of providing separate points of interconnection for each small generator facility.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>If a utility unreasonably rejects a customer proposal for a single point of interconnection without providing a written technical explanation, the utility shall pay any additional cost of providing separate points of interconnection for each small generator facility.</text>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Electrical Isolation of a Small Generator Facility.</text>
        <paragraph num="(1)">
          <text>A small generator facility shall be capable of being isolated from the utility electric distribution system.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>For a small generator facility interconnecting to a primary or secondary line, the isolation shall be by means of a lockable, visible-break isolation device accessible by the utility.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The isolation device shall be installed, owned, and maintained by the interconnection customer for the small generator facility, and located electrically between the small generator facility and the point of interconnection.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>A draw-out type circuit breaker with a provision for padlocking at the draw-out position satisfies the requirement for an isolation device.</text>
        </paragraph>
      </paragraph>
      <paragraph num="H.">
        <text>Use of Lockbox for Access to Isolation Device.</text>
        <paragraph num="(1)">
          <text>An interconnection customer may elect to provide the utility access to an isolation device that is contained in a building or area that may be unoccupied and locked or not otherwise readily accessible to the utility, by installing a lockbox provided by the utility that shall allow ready access to the isolation device.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The lockbox shall be in a location that is readily accessible by the utility, and the interconnection customer shall permit the utility to affix a placard in a location of its choosing that provides clear instructions to utility operating personnel on access to the isolation device.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>In the event the interconnection customer fails to comply with the terms of this section and the utility needs to gain access to the isolation device, the utility may not be held liable for any damages resulting from any necessary utility action to isolate the small generator facility.</text>
        </paragraph>
      </paragraph>
      <paragraph num="I.">
        <text>Metering.</text>
        <paragraph num="(1)">
          <text>Any metering necessitated by a small generator facility interconnection shall be installed, operated, and maintained in accordance with the applicable utility tariff.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Any small generator facility metering requirements shall be clearly identified as part of the interconnection agreement executed by the interconnection customer and the utility.</text>
        </paragraph>
      </paragraph>
      <paragraph num="J.">
        <text>Utility Monitoring and Control of Small Generator Facility.</text>
        <paragraph num="(1)">
          <text>Utility monitoring or control of a small generator facility shall be permitted subject to the conditions in §J of this regulation.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Any utility monitoring or control requirements shall be:</text>
          <paragraph num="(a)">
            <text>Consistent with the utility published requirements, as available on the utility’s website; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Clearly identified in an interconnection agreement executed by the interconnection customer and the utility.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>For a small generator facility under a nameplate capacity of 2 MW, utility monitoring or control is not permitted unless:</text>
          <paragraph num="(a)">
            <text>The Commission approves a utility monitoring and control plan addressing such facilities in the aggregate; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The interconnection customer consents to utility monitoring or control.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>Equipment certified under the latest published editions of IEEE 1547, IEEE 1547.1, and UL 1741 shall be permitted to be used for monitoring or control upon mutual agreement of the utility and the interconnection customer.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>A utility monitoring and control plan submitted to the Commission pursuant to §J(3)(a) of this regulation shall include:</text>
          <paragraph num="(a)">
            <text>Technical requirements;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Cost;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Benefits;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Comparison to IEEE 1547-2018 compliant monitoring and control alternatives, if applicable;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Customer permissions plan; and</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Project management plan.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="K.">
        <text>Good Small Generator Facility Cybersecurity Practice. A small generator facility’s cybersecurity shall be:</text>
        <paragraph num="(1)">
          <text>Designed;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Installed;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Maintained; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Operated to the extent reasonable and practical, in accordance with accepted industry standards and meet utility cybersecurity requirements</text>
        </paragraph>
      </paragraph>
      <paragraph num="L.">
        <text>Witness Test of Small Generator Facility.</text>
        <paragraph num="(1)">
          <text>The utility shall have the option of performing a witness test after construction of the small generator facility is completed.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The applicant shall provide the utility at least 5 business days notice of the planned commissioning test for the small generator facility.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>If the utility elects to perform a witness test, the utility shall contact the applicant to schedule the witness test at a mutually agreeable time within 10 business days of the scheduled commissioning test.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>If the utility does not perform the witness test within 10 business days of the commissioning test, the witness test is considered waived unless the utility and applicant agree to extend the time for conducting the witness test.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>If the results of the witness test are not acceptable to the utility, the applicant shall address and resolve any deficiencies within 30 calendar days, which may be extended upon the request of the applicant prior to the expiration of the 30-calendar-day period. A request for extension may not be unreasonably denied by the utility.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>If the applicant fails to address and resolve the deficiencies to the satisfaction of the utility, the interconnection request shall be considered withdrawn.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>If a witness test is not performed by the utility or an entity approved by the utility, the applicant shall satisfy the interconnection test specifications and requirements specified in Section 8 of IEEE Standard 1547.1-2020.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>For interconnection equipment that has not been certified or approved under Regulation .07 of this chapter, the witness test may also include the verification by the utility specified in Section 8 of IEEE Standard 1547.1-2020.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>All tests verified by the utility shall be performed in accordance with the test procedures specified in Section 8 of IEEE Standard 1547.1-2020.</text>
        </paragraph>
        <paragraph num="(10)">
          <text>The applicant shall, if requested by the utility, provide a copy of all documentation in its possession regarding testing conducted under  Section 8 of IEEE Standard 1547.1-2020.</text>
        </paragraph>
        <paragraph num="(11)">
          <text>The applicant shall demonstrate that it meets the smart inverter requirements of §O of this regulation, if applicable.</text>
        </paragraph>
      </paragraph>
      <paragraph num="M.">
        <text>Interconnection Studies and Applicant Information.</text>
        <paragraph num="(1)">
          <text>If requested by the applicant, the utility shall provide the applicant copies of any interconnection studies performed in analyzing an interconnection request.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An applicant may provide any other prospective applicant copies of interconnection studies to aid in streamlining a future utility review.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Queue position for all small generator facilities shall be prioritized based on the date the interconnection request is submitted.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Each utility shall publicly and electronically provide an interconnection queue, updated monthly, that includes the following information about each interconnection request for any small generator facility with a nameplate capacity greater than 500 kW:</text>
          <paragraph num="(a)">
            <text>Size (MW or kW);</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Proposed circuit number and substation;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>County and zip code;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Interconnection request received date;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Queue position on the system’s proposed circuit number and substation;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Review status;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Interconnection request approved date; and</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Any other information requested by the Commission.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>A small generator facility shall remain on the list for at least 3 years after the interconnection request was approved by the utility, unless subsequently cancelled or removed from the interconnection queue pursuant to §N of this regulation.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>A utility may provide any additional information to a prospective applicant if the utility determines that doing so would streamline the utility’s review of an interconnection request.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>A utility has no obligation to provide any prospective applicant any information regarding prior interconnection requests, including a prior applicant's name, copies of prior interconnection studies performed by the utility, or any other information regarding a prior applicant or request.</text>
        </paragraph>
      </paragraph>
      <paragraph num="N.">
        <text>Validity of Conditional Approval.</text>
        <paragraph num="(1)">
          <text>A project participating as a community solar energy generating system under COMAR 20.62 is not subject to this section.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The notice of conditional approval shall clearly identify the applicable deadline and the consequences of failing to either deliver the certification of completion or request an extension by the deadline.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Once the utility delivers notice of conditional approval to the applicant, the applicant shall deliver the certification of completion within the following time frames:</text>
          <paragraph num="(a)">
            <text>For an application for a small generator facility with a nameplate capacity smaller than or equal to 100 kW, the applicant:</text>
            <paragraph num="(i)">
              <text>Shall deliver the certification of completion within 6 months;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Shall receive a 6-month extension of the specified deadline, upon request; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>May receive one or more additional extensions of at least 6 months upon good cause shown after an initial 6-month extension; and</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>For an application for a small generator facility with a nameplate capacity larger than 100 kW, the applicant:</text>
            <paragraph num="(i)">
              <text>Shall deliver the certification of completion within 12 months;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Shall receive a 6-month extension of the specified deadline, upon request; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>May receive one or more additional extensions of at least 6 months upon good cause shown after an initial 6-month extension.</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>A project participating in the Community Solar pilot program under COMAR 20.62 is not subject to this section.</text>
        </paragraph>
      </paragraph>
      <paragraph num="O.">
        <text>Smart Inverters.</text>
        <paragraph num="(1)">
          <text>After January 1, 2024, any small generator facility requiring an inverter that submits an interconnection request shall use a smart inverter with either a default or a site-specific utility required inverter settings profile, as determined by a utility.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Any small generator facility may replace an existing inverter with a similar spare inverter that was purchased prior to January 1, 2024, for use at the small generator facility. This requirement does not apply to inverter replacements conducted under manufacturer warranty.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Prior to January 1, 2024, all utilities will establish default utility required inverter settings profiles for smart inverters pursuant to §O(5) of this regulation. A utility with a total number of less than 150,000 customers served in Maryland may use a Statewide utility required inverter settings profile as their default utility required inverter settings profile.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>To the extent reasonable, pursuant to any modifications required by §O(5) of this regulation, all utility required inverter setting profiles shall be consistent with applicable smart inverter recommendations from PJM Interconnection, LLC that are applicable.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>A default utility required inverter settings profile shall be established by a utility to optimize the safe and reliable operation of the electric distribution system, and shall serve the following objectives:</text>
          <paragraph num="(a)">
            <text>The primary objective is to incur no involuntary real power inverter curtailments incurred during normal operating conditions and minimal real power involuntary curtailments during abnormal operating conditions.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The secondary objective is to enhance electric distribution system hosting capacity and to optimize the provision of grid support services.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(6)">
          <text>A site-specific utility required inverter settings profile may be established by a utility as necessary to optimally meet the objectives established in §O(5) of this regulation.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>All default and site-specific utility required inverter settings profiles shall be documented in interconnection agreements.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>A default utility required inverter settings profile shall be published on the utility’s website.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>A utility with a total number of 150,000 or more customers served in Maryland shall:</text>
          <paragraph num="(a)">
            <text>File an initial default utility required inverter settings profile with the Commission for approval by October 1, 2023 to be effective by January 1, 2024.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>File any changes to its established default utility required inverter settings profile with the Commission for approval.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(10)">
          <text>Commission Staff shall file any changes to the established statewide utility required inverter settings profile with the Commission for approval.</text>
        </paragraph>
        <paragraph num="(11)">
          <text>A utility required inverter settings profile or statewide utility required inverter settings profile shall be deemed approved within 90 days upon filing, unless directed otherwise by the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="P.">
        <text>Flexible Interconnection Options.</text>
        <paragraph num="(1)">
          <text>Utilities shall approve interconnection requests while considering flexible interconnection options under a limited export agreement or, for inadvertent export, net system capacity and a proposed use subject to the requirements of this section.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Inadvertent Export for Energy Storage Devices.</text>
          <paragraph num="(a)">
            <text>Small generator facilities using Level 3 interconnection requests are non-exporting systems and are not allowed to utilize inadvertent exports.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A utility may not approve an inadvertent export option if the interconnection customer lacks the appropriate standardized controls to ensure that the small generator facility operates as agreed upon in interconnection agreements.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Small generator facilities may inadvertently export power of a magnitude and duration as evaluated and allowed by the utility and as specified in their interconnection agreement. Thirty seconds shall be used as a default inadvertent export duration unless the utility determines that this level duration violates utility evaluation criteria.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>There are no limits on the number of times inadvertent exports occur in any given customer billing cycle.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Small generator facilities may not have total inadvertent exports greater than the generating facility nameplate capacity multiplied by 1 hour per customer in each billing cycle.</text>
          </paragraph>
          <paragraph num="(f)">
            <text>In the event that a small generator facility exceeds approved inadvertent export magnitude or duration limits, the small generator facility shall immediately cease to export power to the grid until acceptable output control has been reestablished.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Net System Capacity and Proposed Use.</text>
          <paragraph num="(a)">
            <text>An interconnection customer may request that its interconnection request be based on the proposed use of the small generator facility and the impact of its proposed use on net system capacity.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A utility may not approve a proposed use if the interconnection customer lacks the appropriate standardized controls to ensure that the small generator facility operates as agreed upon in interconnection agreements.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>In the event that a small generator facility exceeds the approved net system capacity for the proposed use, the small generator facility shall immediately cease to export power to the grid until acceptable output control has been reestablished.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>Limited Export Agreements.</text>
          <paragraph num="(a)">
            <text>By January 1, 2025, a utility shall publish on its interconnection website a description of their limited export agreement policies and provide a process for interconnection customers to request these agreements to avoid the need for a hosting capacity upgrade project to accommodate an interconnection request, including the following:</text>
            <paragraph num="(i)">
              <text>Limited export agreements shall be made available upon request only to Level 2 and Level 4 interconnection customers;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Limited export agreement terms shall be mutually agreed upon between a utility and an interconnection customer for operating conditions as specified in the interconnection agreement or in a separate limited export interconnection customer agreement; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>The method of implementation and control of the limited export agreement terms shall be mutually agreed upon between a utility and the interconnection customer and specified in the interconnection agreement or in a separate limited export interconnection customer agreement.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>A utility may not approve a limited export agreement if the interconnection customer lacks the appropriate standardized controls to ensure that the small generator facility operates as agreed upon in interconnection agreements.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>In the event that a small generator facility does not curtail and exceeds the approved limited export parameters stated in the interconnection agreement or a separate limited export interconnection customer agreement, the small generator facility shall immediately cease to export real power to the grid until acceptable output control has been reestablished.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>If required by the utility, the small generator facility shall be subject to a verification reporting plan to monitor the small generator facility’s compliance with any flexible interconnection option limits involving net system capacity, inadvertent export, proposed use, and limited export agreement requirements as documented in the interconnection agreement. A verification reporting plan may include periodic reports, online monitoring, or other verification methods, or it may be waived as agreed upon by the utility and interconnection customer.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Utilities may include a recurring administrative fee in utility tariffs as a term in flexible interconnection option agreements to reimburse the utility for estimated additional costs to administer these agreements and the stated limiting conditions.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>Failure of a small generator facility to demonstrate compliance with the facility’s verification reporting plan may result in the suspension of utility approvals in this section until the small generator facility agrees and implements an acceptable corrective action plan with the utility within 30 calendar days of notification by the utility.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>A small generator facility shall cease to export power if it fails to provide an acceptable corrective action plan to the utility, pursuant to §P(7) of this regulation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="Q.">
        <text>Hosting Capacity.</text>
        <paragraph num="(1)">
          <text>Utilities shall establish hosting capacity policies subject to the following requirements:</text>
          <paragraph num="(a)">
            <text>A utility shall designate a circuit a closed circuit if there is no remaining hosting capacity.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A utility shall designate a circuit a restricted circuit if only reserve hosting capacity is available.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A utility shall determine the amount of reserve hosting capacity on a restricted circuit based on a circuit-specific assessment of distributed energy resource forecasts or other factors, including customer density, type of area served, and customer demographics of the circuit.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>A utility may determine the aggregate generation of a small generator facility permitted to use an electric distribution circuit’s reserve hosting capacity and publish this information on their website.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>A utility shall report their closed circuits, restricted circuits, and reserve hosting capacity in their hosting capacity reporting system.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>A utility may submit for the Commission’s review and approval a hosting capacity upgrade plan or multiple plans to address or otherwise increase the utility’s existing distribution aggregate circuit hosting capacity limits across the system, or in a specific area of an electric utility’s system, that are forecasted to be congested in the future if the utility’s forecast of distributed energy resource growth exceeds existing hosting capacity. These plans may be considered by the Commission if primary voltage hosting capacity upgrade fees, pursuant to §R of this regulation, exceed a threshold of the utility’s average cost per kilowatt for their aggregate customer funded hosting capacity upgrade projects completed in the previous year, unless good cause exists for a utility to request a waiver of this requirement.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Hosting capacity upgrade plans that are submitted by a utility shall include:</text>
          <paragraph num="(a)">
            <text>A description of the electric system areas to be included in the hosting capacity upgrade plan at the feeder and substation level;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A description of the assumptions used for establishing and prioritizing the area covered by the hosting capacity upgrade plan and associated forecasts and timeline for hosting capacity utilization;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A description of the assumptions used for modeling and establishing the cost of the hosting capacity upgrade plan;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>If the plan proposes that ratepayers bear any costs that would not be paid by future interconnection customers, a justification for the percentage cost allocation proposed between interconnection customers and ratepayers, including descriptions of:</text>
            <paragraph num="(i)">
              <text>How the proposed cost allocation was developed and what alternatives were considered, explaining and quantifying the benefits ratepayers are expected to receive from the upgrade; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>How the utility engaged with stakeholders, particularly the ratepayer advocate’s office, the Maryland Office of People’s Counsel, in the development of the utility’s cost allocation proposal;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(e)">
            <text>A description of the proposed cost allocation method in terms of dollars per kilowatt for a primary voltage hosting capacity fee for an interconnection customer;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>A description of the proposed cost allocation to ratepayers and the risks to ratepayers of unallocated hosting capacity upgrade costs if the hosting capacity upgrade does not become fully utilized; and</text>
          </paragraph>
          <paragraph num="(g)">
            <text>A proposal for utility cost recovery that describes how hosting capacity upgrade costs shall be offset by future utility revenues from interconnection customers.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>A utility shall have a procedure for calculating hosting capacity accounting for either gross peak or gross minimum loading based on good engineering practice.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The utility shall perform a representative sample of hosting capacity calculation validation checks at least annually, or more frequently in areas experiencing significant growth or distributed energy resource penetration. The hosting capacity calculation validation check frequency shall account for the utility's experience, good engineering practices, and judgment.</text>
        </paragraph>
      </paragraph>
      <paragraph num="R.">
        <text>Maryland Cost Allocation Method.</text>
        <paragraph num="(1)">
          <text>Within 1 year of the effective date of this regulation, electric utilities shall submit an electric utility service tariff for Commission approval for a primary voltage hosting capacity cost sharing and allocation methodology for interconnection customers, as follows:</text>
          <paragraph num="(a)">
            <text>The default hosting capacity cost sharing and allocation methodology for primary voltage interconnection customers shall be based on locational pricing to incentivize interconnection in areas with higher available hosting capacity and disincentivize interconnection in areas with lower available hosting capacity.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A utility may petition the Commission to implement a hosting capacity cost sharing and allocation methodology for primary voltage interconnection customers that is not locationally based for “good cause” in their tariff filing.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>An interconnection request shall be eligible for hosting capacity cost sharing and allocation under this section unless they are exempted for the following reasons:</text>
            <paragraph num="(i)">
              <text>The interconnection request is subject to the PJM Interconnection, LLC Tariff;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The interconnection request is in an area with its cost allocation governed by a hosting capacity upgrade plan approved by the Commission;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>The interconnection is on a dedicated primary voltage feeder that may not benefit any other interconnection customer;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>The interconnection is on a dedicated secondary voltage facility that may not benefit any other interconnection customer;</text>
            </paragraph>
            <paragraph num="(v)">
              <text>The interconnection request is on an AC distribution grid or spot network; or</text>
            </paragraph>
            <paragraph num="(vi)">
              <text>Other good cause as documented by the utility and reported, pursuant to Regulation .14 of this chapter.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(d)">
            <text>If an interconnection request is exempted, pursuant to §R(1)(c) of this regulation, the interconnection customer shall pay all interconnection costs as determined by the utility, unless the interconnection request is subject to the PJM Tariff or the interconnection request is in an area with its cost allocation governed by a hosting capacity upgrade plan approved by the Commission.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>If sufficient hosting capacity is not available at a point of interconnection for a primary voltage interconnection customer, an electric utility may propose a hosting capacity upgrade project to the interconnection customer or customers, as follows:</text>
            <paragraph num="(i)">
              <text>The utility shall charge the primary voltage interconnection customer a hosting capacity fee for its share of the primary voltage hosting capacity upgrade cost proportional to the interconnection customer’s utilization of hosting capacity.</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>If more than one interconnection request exists in the interconnection queue that shall benefit from the electric utility proposed hosting capacity upgrade project, these interconnection customers shall be clustered together for the purpose of calculating hosting capacity fees.</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Hosting capacity fees for clustered interconnection customers shall be calculated proportional to each interconnection customer’s utilization of the hosting capacity created by the hosting capacity upgrade project.</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>All hosting capacity upgrade costs in excess of hosting capacity fees collected shall be accumulated in a separate unallocated primary voltage hosting capacity upgrade cost account for future allocation to primary voltage interconnection customers.</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Unallocated hosting capacity upgrade costs for primary voltage interconnection customers shall be shared and allocated to other primary voltage interconnection customers using a primary voltage hosting capacity cost sharing and allocation methodology in an electric utility service tariff approved by the Commission.</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Within 1 year of the effective date of this regulation, electric utilities shall submit an electric utility service tariff for Commission approval for a secondary voltage cost sharing and fee for both residential and commercial interconnection customers, as follows:</text>
          <paragraph num="(a)">
            <text>If sufficient hosting capacity is not available at a point of interconnection for a secondary voltage interconnection customer, an electric utility may construct a hosting capacity upgrade project for the interconnection customer or customers.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>All secondary voltage hosting capacity upgrade costs shall be accumulated in separate unallocated accounts for both residential and commercial secondary voltage interconnection customers for future allocation in hosting capacity fees.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Unallocated hosting capacity upgrade costs for both residential and commercial secondary voltage interconnection customers shall be shared and allocated to other secondary voltage interconnection customers using a hosting capacity cost sharing and allocation fee in an electric utility service tariff approved by the Commission.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Hosting capacity fees for primary voltage interconnection customers shall be reset using a cost sharing and allocation methodology approved by the Commission in an electric utility service tariff filing whenever a change in methodology is proposed, unless the fee is zero or the fee change is less than $1 per kilowatt.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Hosting capacity fees for secondary voltage interconnection customers shall be reset annually using a cost sharing and allocation methodology approved by the Commission unless the fee is zero or the fee change is less than $1 per kilowatt from the current fee in the electric utility’s service tariff.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>A utility may submit for Commission approval an administrative charge in its service tariff to recover its administrative costs for managing the cost sharing and allocation methodology for primary and secondary voltage interconnection customers.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>A utility shall describe all hosting capacity upgrade project rightsizing projects describing their forecasts, inputs, and assumptions in their next rate case to assist stakeholders in a prudency review.</text>
        </paragraph>
      </paragraph>
      <paragraph num="S.">
        <text>Vehicle to Grid Interconnection.</text>
        <paragraph num="(1)">
          <text>A V2G System shall meet the following requirements:</text>
          <paragraph num="(a)">
            <text>The interconnection customer for a V2G system shall submit an interconnection request pursuant to Regulation .04 of this chapter.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A V2G system interconnection shall be valid only at a single point of interconnection specified in the interconnection agreement. Additional locations shall require additional interconnection reviews and associated interconnection agreements.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>An electric company shall consider a V2G system to be an energy storage device pursuant to Regulation .02B of this chapter for the purpose of evaluating the electrical performance requirements applicable to an interconnection request.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Characteristics of energy storage systems that do not and cannot apply to the use of EVs as connected energy storage units shall not be required of V2G systems operated as energy storage.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>A V2G system shall not be authorized in bidirectional mode while in parallel operation with the local electric power system unless an interconnection agreement is in place between the interconnection customer and the relevant electric utility and the interconnection customer has received a permission to operate from the electric company.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>An electric company may delay interconnection of a V2G system to provide adequate time to ensure electric distribution system safety and reliability in advance of vehicle-to-grid interconnections pursuant to applicable requirements in Regulation .09 of this chapter for Level 1 Review, Regulation .10 of this chapter for a Level 2 Review, Regulation .11 of this chapter for a Level 3 Review, and Regulation .12 of this chapter for a Level 4 Review.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>To ensure safety, reliability and V2G functionality for DC EVSE V2G Systems, the interconnection agreement shall require adherence to UL 1741 incorporated by reference in COMAR 20.50.02.02(I).</text>
        </paragraph>
        <paragraph num="(4)">
          <text>To ensure safety, reliability and V2G functionality for AC EVSE V2G Systems there are two acceptable certification pathways for which only one certification pathway shall be required in an interconnection agreement:</text>
          <paragraph num="(a)">
            <text>Certification pathway 1 is as follows:</text>
            <paragraph num="(i)">
              <text>UL 1741 incorporated by reference in COMAR 20.50.02.02(I) and UL 2594 incorporated by reference in COMAR 20.50.02.02(N) for a V2G Ready EVSE; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>SAE J3072 incorporated by reference in COMAR 20.50.02.02(O) for a bidirectional electric vehicle.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>Certification pathway 2 is as follows:</text>
            <paragraph num="(i)">
              <text>UL 9741 incorporated by reference in COMAR 20.50.02.02(M) for V2G Ready EVSE; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>UL 1741 SB under the QIKP Grid Interconnection Performance Certification for a bidirectional electric vehicle and V2G Ready EVSE.</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>If applicable, certifications pursuant to Regulation .06S(4) of this chapter are not available or safety, reliability, and V2G functionality cannot be ensured:</text>
          <paragraph num="(a)">
            <text>The utility may require reasonable alternative methods such as protective relaying equipment, a power control system, or other alternative methods in an interconnection agreement; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If safety, reliability and V2G functionality cannot be ensured through certifications or reasonable alternative methods, an electric company shall deny the interconnection request.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(6)">
          <text>A V1G System shall meet the following requirements.</text>
          <paragraph num="(a)">
            <text>An interconnection request, interconnection agreement, and an electric company permission to operate is not required for a V1G Ready EVSE provided that the V1G Ready EVSE is configured to only allow V1G operation in compliance with relevant standards.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A V2G System that operates as a V1G Ready EVSE shall be accepted by an electric company using a method for notification form submittal as determined by the electric company. The notification form used by the electric company shall only require information required to attest to V1G operation and not duplicate an interconnection request.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A V1G Ready EVSE shall not be changed to a V2G Ready EVSE without first receiving an interconnection request and permission to operate from the utility.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Only the EVSE manufacturer or a manufacturer approved third party entity may reprogram or reconfigure an EVSE to bidirectional operation.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".07" heading="Certified and Approved Equipment.">
      <paragraph num="A.">
        <text>After January 1, 2024, any small generator facility inverter for which an interconnection request is submitted shall be deemed certified and approved if it meets the requirements of IEEE Standard 1547-2018 and UL Standard 1741-SB, except for inverters purchased pursuant to Regulation .06N(2) of this chapter.</text>
      </paragraph>
      <paragraph num="B.">
        <text>After January 1, 2024, any small generator facility shall be deemed approved if the interconnection equipment including interface components such as switchgear, multifunction relays, or other interface devices are compatible with the interconnection equipment, pursuant to witness test requirements pursuant to Regulation .06L of this chapter.</text>
      </paragraph>
      <paragraph num="C.">
        <text>An electric utility shall approve a meter collar adapter model for installation in its Maryland service area for specific compatible meter configurations and customer applications, provided that the meter collar adapter model meets the following criteria:</text>
        <paragraph num="(1)">
          <text>The meter collar adapter model is approved or listed by a nationally recognized testing laboratory;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The meter collar adapter model is approved for use in utility service areas, unless sufficient rational for disapproval is provided by an electric utility;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>All meter collar model installations, access, testing, inspections, servicing, and removals shall only be performed by a qualified person as agreed between the utility and the meter collar manufacturer;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The meter collar adapter model design does not impede access to the sealed meter socket compartment, or to the meter itself by a qualified person;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The meter collar adapter model is compatible with the National Electric Code; and</text>
        </paragraph>
        <paragraph num="(6)">
          <text>The meter collar adapter model is compatible to the specific meter configurations and customer applications to ensure that the meter collar adapter is capable of being safely and reliably inserted into a meter socket to maintain a secure connection with both the meter socket and the utility meter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>An electric utility shall approve or disapprove a meter collar adapter model for installation in its service area no later than 90 days after a meter collar manufacturer submits a request for approval of the meter collar adapter, and a utility’s procedures shall be updated within 90 days of utility approval.</text>
      </paragraph>
      <paragraph num="E.">
        <text>An electric utility shall provide an explanation to the requesting meter collar manufacturer explaining the reasons any meter collar adapter model application was denied.</text>
      </paragraph>
      <paragraph num="F.">
        <text>A requesting meter collar adapter manufacturer may appeal the utility decision to the Commission using the dispute resolution process in Regulation .13 of this chapter.</text>
      </paragraph>
      <paragraph num="G.">
        <text>An electric utility shall provide public notice of all decisions approving a meter collar adapter model by posting the information on the utility’s website.</text>
      </paragraph>
      <paragraph num="H.">
        <text>An electric utility shall authorize the installation and operation of a utility-approved meter collar adapter for a customer installation, provided the meter collar adapter meets the following criteria:</text>
        <paragraph num="(1)">
          <text>The meter collar adapter is qualified to be connected to the supply side of the service disconnect, pursuant to the applicable provisions of the National Electric Code;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The meter collar adapter is rated for the meter socket into which it is intended to be installed;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The meter collar adapter does not exceed the weight bearing limits of a meter socket;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Multiple meter collar adapters are not stacked in a meter socket; and</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The meter collar adapter does not disable this excessive heating detection capability of AMI meters.</text>
        </paragraph>
      </paragraph>
      <paragraph num="I.">
        <text>A utility shall uninstall an approved meter collar adapter in the aggregate if any deficiencies are found after installation that result in safety or operational concerns, if these concerns cannot be remediated by a customer for a specific installation or by a meter collar adapter manufacturer, in the aggregate.</text>
      </paragraph>
      <paragraph num="J.">
        <text>The determination of violations in this regulation and the assessment of related civil penalties and corrective action plans shall be delegated to the Engineering Division.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".08" heading="Determination of Interconnection Jurisdiction and Level of Utility Review of Interconnection Request.">
      <paragraph num="A.">
        <text>A utility shall determine within 10 business days the interconnection jurisdiction pursuant to Regulation .01 of this chapter and the level of utility review required for an interconnection request based on nameplate capacity.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A utility shall use a Level 1 procedure to evaluate an interconnection request to connect an inverter-based small generator facility when the small generator facility, or multiple small generator facilities interconnecting at a point of common coupling, has a nameplate capacity of 20kW or less.</text>
      </paragraph>
      <paragraph num="C.">
        <text>A utility shall use a Level 2 procedure to evaluate an interconnection request when:</text>
        <paragraph num="(1)">
          <text>The following criteria are met:</text>
          <paragraph num="(a)">
            <text>The small generation facility, or multiple small generator facilities interconnecting at a point of common coupling, has a nameplate capacity of 2 MW or less;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The interconnection equipment is lab-certified or field-approved; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The proposed interconnection is to a radial distribution circuit, or a spot network limited to serving one customer; or</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Alternatively, the small generator facility was reviewed under Level 1 review procedures but not approved, and the applicant has submitted a new interconnection request for consideration.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>A utility shall use a Level 3 procedure to evaluate an interconnection request to area networks and radial distribution circuits when electric power is not exported to the electric distribution system based on the following criteria:</text>
        <paragraph num="(1)">
          <text>For interconnection requests to the load side of an area network:</text>
          <paragraph num="(a)">
            <text>The nameplate capacity of the small generator facility, or multiple small generator facilities interconnecting at a point of common coupling, is less than or equal to 50 kW;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The proposed small generator facility utilizes a lab-certified inverter-based equipment package;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The small generator facility utilizes reverse power relays, other protection functions, or both, that prevent the export of power into the area network;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The aggregate generation on the area network does not exceed the smaller of 5 percent of an area network's maximum load or 50 kW; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Construction of facilities by the electric distribution company is not required to accommodate the small generator facility; or</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>For interconnection requests to a radial distribution circuit:</text>
          <paragraph num="(a)">
            <text>The small generator facility has a nameplate capacity of 10 MW or less;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The aggregate generation on the circuit, including the proposed small generator facility, is 10 MW or less;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The small generator facility will use reverse power relays or other protection functions that prevent power flow onto the electric distribution system;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The small generator facility is not served by a shared transformer; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Construction of facilities by the utility on its own electric distribution system is not required to accommodate the small generator facility.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>A utility shall use the Level 4 procedures for evaluating interconnection requests if:</text>
        <paragraph num="(1)">
          <text>The interconnection request cannot be approved under a Level 1, Level 2, or Level 3 review, and the applicant has submitted an interconnection request for consideration under a Level 4 study review; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The interconnection request does not meet the criteria for qualifying for a review under Level 1, Level 2, or Level 3 review procedures.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".09" heading="Level 1 Review.">
      <paragraph num="A.">
        <text>The utility shall evaluate a Level 1 small generator facility for the potential for adverse system impacts using net system capacity, pursuant to Regulation .06A and B of this chapter, unless nameplate capacity is specifically required using the following:</text>
        <paragraph num="(1)">
          <text>For interconnection of a proposed small generator facility:</text>
          <paragraph num="(a)">
            <text>To a radial distribution circuit, the aggregate generation on the circuit, including the proposed small generator facility, may not exceed 15 percent of the line section annual peak load as most recently measured at the substation or calculated for the line section; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>To a spot network:</text>
            <paragraph num="(i)">
              <text>On the load side of spot network protectors, the proposed small generator facility shall utilize an inverter-based equipment package;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The interconnection equipment proposed for the small generator facility is lab-certified; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>The aggregate generation of all interconnected small generator facilities may not exceed 5 percent of the spot network's maximum load if the spot network serves more than one customer;</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>When a proposed small generator facility is to be interconnected on a single-phase shared secondary line, the aggregate generation on the shared secondary line, including the proposed small generator facility, may not exceed 20 kW;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>When a proposed small generator facility is single-phase and is to be interconnected on a center tap neutral of a 240 volt service, its addition may not create an imbalance between the two sides of the 240 volt service of more than 20 percent of the nameplate rating of the service transformer;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>As an alternative non-mandatory method to evaluate the adverse system impacts of a proposed Level 1 small generator facility on the distribution system, as described in §A(1)—(3) of this regulation, or as a mandatory next step prior to rejecting an interconnection request, pursuant to §E of this regulation, for Level 1 Review Failure, a utility may use a power-flow based analysis system with modeling of IEEE 1547-2018 inverter capabilities as follows, if its use may change the analysis result as determined by the utility:</text>
          <paragraph num="(a)">
            <text>For primary voltage systems, within 6 months of the effective date of this regulation; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>For secondary voltage systems, within 2 years of the effective date of this regulation;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>Modification or construction of additional interconnection facilities by the utility on its distribution system, except for metering or a minor system modification, is not required to accommodate the small generator facility; and</text>
        </paragraph>
        <paragraph num="(6)">
          <text>If the proposed interconnection requires a minor system modification, the utility shall notify the applicant of that requirement when it provides the Level 1 evaluation result, as follows:</text>
          <paragraph num="(a)">
            <text>The applicant shall inform the utility within 10 business days if the applicant elects to continue the application;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If the applicant makes such an election, the utility shall provide an interconnection agreement, along with a non-binding good faith cost estimate and construction schedule for those upgrades, to the applicant within 30 calendar days after the utility receives such an election; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The applicant shall have 30 calendar days, or other mutually agreeable time frame after receipt of the interconnection agreement, to sign and return such agreement.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>The utility in conducting a Level 1 interconnection review shall:</text>
        <paragraph num="(1)">
          <text>Within 5 business days after receipt of the interconnection request, inform the applicant that the interconnection request is:</text>
          <paragraph num="(a)">
            <text>Complete; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Incomplete and what materials are missing; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Within 15 business days after the utility notifies the applicant that the application is complete under §B(1) of this regulation, verify that the small generator facility can be interconnected safely and reliably under §A of this regulation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Unless the utility determines and demonstrates that a small generator facility cannot be interconnected safely or reliably to its electric distribution system, the utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
        <paragraph num="(1)">
          <text>The small generator facility has been approved by local or municipal electric code officials with jurisdiction over the interconnection;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A certificate of completion has been returned to the utility;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The witness test has been successfully completed or waived by the utility; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The applicant has signed an interconnection agreement.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>If an applicant does not sign the interconnection agreement within 30 calendar days after receipt from the utility, the interconnection request is considered withdrawn unless the applicant requests to have the deadline extended. A request for extension may not be unreasonably denied by the utility.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Level 1 Review Failure.</text>
        <paragraph num="(1)">
          <text>If the small generator facility is not approved under a Level 1 review, the utility shall provide the applicant a letter explaining its reasons for denying the interconnection request.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If a small generator facility fails a Level 1 review, the utility may approve the interconnection request if the small generator facility can be interconnected safely and reliably to the utility’s electric distribution system.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>When a small generator facility is not approved under a Level 1 review, the applicant may submit a new interconnection request for consideration under Level 2, Level 3, or Level 4 procedures.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".10" heading="Level 2 Review.">
      <paragraph num="A.">
        <text>The utility shall evaluate a Level 2 small generator facility for the potential for adverse system impacts using net system capacity, pursuant to Regulation .06A and B of this chapter, unless nameplate capacity is specifically required using the following:</text>
        <paragraph num="(1)">
          <text>For interconnection of a proposed small generator facility:</text>
          <paragraph num="(a)">
            <text>To a radial distribution circuit, the aggregate generation on the circuit, including the proposed small generator facility, may not exceed 15 percent of the line section annual peak load most recently measured at the substation or calculated for the line section; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>To a spot network:</text>
            <paragraph num="(i)">
              <text>When the interconnection of a proposed small generator facility is to the load side of spot network protectors, the proposed small generator facility shall utilize an inverter-based equipment package;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The applicant's interconnection equipment proposed for the small generator facility shall be lab-certified or field-approved; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>A small generator facility, when aggregated with other generation, the aggregate generation on the spot network, may not exceed 5 percent of a spot network's maximum load if the spot network serves more than one customer;</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>For fault current limitations:</text>
          <paragraph num="(a)">
            <text>The nameplate capacity of the proposed small generator facility, in aggregation with other generation and energy storage devices on the distribution circuit, may not contribute more than 10 percent to the electric distribution circuit's maximum fault current at the point on the primary line nearest the point of interconnection;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The nameplate capacity of the proposed small generator facility, in aggregation with other generation and energy storage devices on the distribution circuit, may not cause any distribution protective devices and equipment including substation breakers, fuse cutouts, and line reclosers, or other customer equipment on the electric distribution system to be exposed to fault currents exceeding 90 percent of the short circuit interrupting capability; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The interconnection request may not request interconnection on a circuit that already exceeds 90 percent of the short circuit interrupting capability;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>The proposed small generator facility's point of interconnection may not be on a transmission line;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>When a small generator facility is to be connected to 3-phase, 3-wire primary utility distribution lines, a 3-phase or single-phase generator shall be connected phase-to-phase;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>When a small generator facility is to be connected to 3-phase, 4-wire primary utility distribution lines, a 3-phase or single-phase generator will be connected line-to-neutral and will be effectively grounded;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>When the proposed small generator facility is to be interconnected on single-phase shared secondary line, the aggregate generation on the shared secondary line, including the proposed small generator facility, may not exceed 20 kW;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>When a proposed small generator facility is single-phase and is to be interconnected on a center tap neutral of a 240 volt service, its addition may not create an imbalance between the two sides of the 240 volt service of more than 20 percent of the nameplate rating of the service transformer;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>A small generator facility, in aggregate with other generation and energy storage devices interconnected to the distribution side of a substation transformer feeding the circuit where the small generator facility proposes to interconnect, the aggregate generation may not exceed 10 MW in an area where there are known or posted transient stability limitations to generating units located in the general electrical vicinity;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>As an alternative non-mandatory method to evaluate the adverse system impacts of a proposed Level 2 small generator facility on the distribution system, as described in §A(1)—(8) of this regulation, or as a mandatory next step prior to rejecting an interconnection request, pursuant to §F of this regulation, for Level 2 Review Failure, a utility may use a power-flow based analysis system with modeling of IEEE 1547-2018 inverter capabilities as follows, if its use may change the analysis result as determined by the utility:</text>
          <paragraph num="(a)">
            <text>For primary voltage systems, within 6 months of the effective date of this regulation; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>For secondary voltage systems, within 2 years of the effective date of this regulation;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(10)">
          <text>Except as permitted by an additional review in §G of this regulation, no modification or construction of additional facilities by a utility of its distribution system, with the exception of metering or a minor system modification, shall be required to accommodate the small generator facility; and</text>
        </paragraph>
        <paragraph num="(11)">
          <text>If the proposed interconnection facility requires a site-specific utility required inverter settings profile review or a minor system modification without further study review needed, the utility shall notify the applicant of that requirement when it provides the Level 2 evaluation result, as follows:</text>
          <paragraph num="(a)">
            <text>The applicant must inform the utility within 10 business days if the applicant elects to continue the application;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If the applicant makes such an election, the utility shall provide an interconnection agreement, along with a non-binding good faith cost estimate and construction schedule for any minor system modifications to the applicant within 30 calendar days after the utility receives such an election; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The applicant shall have 30 calendar days, or other mutually agreeable time frame after receipt of the interconnection agreement, to sign and return such agreement.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>A utility shall, within 5 business days after receipt of the interconnection request, inform the applicant that the interconnection request is:</text>
        <paragraph num="(1)">
          <text>Complete; or</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Incomplete and what materials are missing;</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Queue Position.</text>
        <paragraph num="(1)">
          <text>When an interconnection request is complete, the utility shall assign a queue position.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The queue position of the interconnection request shall be used to determine the potential adverse system impact of the small generator facility based on the relevant screening criteria.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The utility shall notify the applicant of any other higher queue position applicants on the same line section or spot network for which interconnection is sought.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Queue position may not be forfeited or otherwise impacted by the submission of a dispute under the provisions of Regulation .13 of this chapter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>When a utility determines additional information is required to complete an evaluation:</text>
        <paragraph num="(1)">
          <text>The utility shall request the information;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The time necessary to complete the evaluation may be extended, but only to the extent of the delay required for receipt of the additional information; and</text>
        </paragraph>
        <paragraph num="(3)">
          <text>When additional information is required, the utility may not revert to the start of the review process or alter the applicant's queue position.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Within 20 business days after the utility notifies the applicant it has received a completed interconnection request, the utility shall:</text>
        <paragraph num="(1)">
          <text>Evaluate the interconnection request using the Level 2 screening criteria;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Review the applicant's analysis, if provided by applicant, using the same criteria;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Provide the applicant with the utility's evaluation, including a comparison of the results of its own analyses with those of applicant, if applicable; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>When a utility does not have a record of receipt of the interconnection request and the applicant can demonstrate that the original interconnection request was delivered, expedite its review to complete the evaluation of the interconnection request within 20 business days.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Failure to Meet Level 2 Criteria.</text>
        <paragraph num="(1)">
          <text>Additional review may be appropriate when a small generator facility has failed to meet one or more of the Level 2 criteria of §A of this regulation.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A utility shall:</text>
          <paragraph num="(a)">
            <text>Within 30 calendar days, offer to perform additional review to determine whether minor system modifications or a site-specific utility required inverter settings profile would enable the interconnection to be made consistent with safety, reliability, and power quality criteria;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Provide the applicant with a nonbinding, good faith estimate of the costs of the additional review and minor system modifications; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Advise the applicant if a limited export customer agreement could be used to facilitate reliable and safe interconnection to the electric distribution system.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>The utility shall undertake the additional review only if the applicant agrees within 10 business days to pay for the cost of the review, which may be extended at the request of the applicant. A request for extension may not be unreasonably denied by the utility.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>If the review identifies the need for modifications to the distribution system, the utility shall make the necessary modifications only if the interconnection customer agrees to pay for the cost of the modifications.</text>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Interconnection Agreement.</text>
        <paragraph num="(1)">
          <text>When a utility determines that the interconnection request passes the Level 2 screening criteria, or fails one or more of the Level 2 screening criteria but determines that the small generator facility can be interconnected safely and reliably, the utility shall provide the applicant an interconnection agreement within 5 business days after the determination.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The applicant shall have either 30 calendar days, or another mutually agreeable time frame after receipt of the interconnection agreement, to sign and return the interconnection agreement.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>If the applicant does not sign the interconnection agreement within 30 calendar days, the request shall be considered withdrawn unless the applicant and utility mutually agree to extend the time period for executing the interconnection agreement prior to the expiration of the 30-calendar-day calendar period. A request for extension may not be unreasonably denied by the utility.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>After the interconnection agreement is signed by the applicant and utility, interconnection of the small generator facility shall proceed according to any milestones agreed to by the applicant and utility in the interconnection agreement.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
          <paragraph num="(a)">
            <text>All milestones agreed to in the interconnection agreement are satisfied;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The small generator facility is approved by electric code officials with jurisdiction over the interconnection;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The applicant provides a certificate of completion to the utility;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Upon request of the utility, the applicant provides one or more photographs of the small generator facility site location, components, metering equipment, and other related facilities and equipment; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>There is a successful completion of the witness test, if conducted by the utility.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="H.">
        <text>Level 2 Review Failure.</text>
        <paragraph num="(1)">
          <text>If the small generator facility is not approved under a Level 2 review, the utility shall provide the applicant written notification explaining its reasons for denying the interconnection request.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The applicant may submit a new interconnection request for consideration under a Level 3 or Level 4 interconnection review; however, the queue position assigned to the Level 2 interconnection request shall be retained provided the request is made within 15 business days of notification that the current Level 2 interconnection request is denied.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".11" heading="Level 3 Review.">
      <paragraph num="A.">
        <text>The utility shall use the Level 3 review procedure for an interconnection request that meets the Level 3 criteria in Regulation .08 of this chapter.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Queue Position.</text>
        <paragraph num="(1)">
          <text>Once the interconnection request is considered complete by the utility, the utility shall assign a queue position based upon the date and time the interconnection request is determined to be complete.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The queue position of each interconnection request shall be used to determine the potential adverse system impact of the small generator facility based on the relevant screening criteria.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The utility shall notify the applicant of any other higher queue position applicants on the same radial line or area network that the applicant is seeking to interconnect to.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Queue position may not be forfeited or otherwise impacted by any pending dispute submitted under the provisions of Regulation .13 of this chapter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Interconnection requests meeting the requirements set forth in Regulation .08 of this chapter for nonexporting small generator facilities interconnecting to an area network shall be presumed by the utility to be appropriate for interconnection. The utility shall process the interconnection request to area networks using the following procedures:</text>
        <paragraph num="(1)">
          <text>The utility shall evaluate the interconnection request under Level 2 interconnection review procedures as set forth in Regulation .10 of this chapter, except that the utility shall have 25 business days to conduct an area network impact study to determine any potential adverse system impact of interconnecting to the utility's area network;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If the area network impact study identifies potential adverse system impacts, the utility may determine at its sole discretion that it is inappropriate for the small generator facility to interconnect to the area network, in which case the interconnection request shall be denied; however, the applicant may elect to submit a new interconnection request for consideration under Level 4 procedures, in which case the queue position assigned to the Level 3 interconnection request will be retained provided the request is made within 15 business days of notification that the current application is denied;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The utility shall conduct the area network impact study at its own expense; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>In the event the utility denies the interconnection request, the utility shall provide the applicant with a copy of its area network impact study and written justification for denying the interconnection request.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>When an interconnection request meets the requirements of Regulation .08 of this chapter for nonexporting small generator facilities interconnecting to a radial distribution circuit, the utility shall:</text>
        <paragraph num="(1)">
          <text>Evaluate the interconnection request using the Level 2 review in Regulation .10 of this chapter; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Approve the interconnection request if all of the applicable Level 2 screens are satisfied, except that the peak line section value indicated in Regulation .10A(1)(a) shall be 25 percent instead of 15 percent.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Interconnection Agreement.</text>
        <paragraph num="(1)">
          <text>If a small generator facility satisfies the criteria in §C or D of this regulation, the utility shall approve the interconnection request and provide an interconnection agreement for the applicant to sign.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The applicant shall have 30 calendar days, or other mutually agreeable time frame after receipt of the interconnection agreement, to sign and return the interconnection agreement.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>If the applicant does not sign the interconnection agreement within 30 calendar days, the interconnection request shall be considered withdrawn unless the applicant and utility mutually agree to extend the time period for executing the interconnection agreement prior to the expiration of the 30-calendar-day period. A request for extension may not be unreasonably denied by the utility.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>After the interconnection agreement is signed by the applicant and utility, interconnection of the small generator facility shall proceed according to any milestones agreed to by the applicant and utility in the interconnection agreement.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
          <paragraph num="(a)">
            <text>All milestones agreed to in the interconnection agreement are satisfied;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The small generator facility is approved by electric code officials with jurisdiction over the interconnection;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The applicant provides a certificate of completion to the utility;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Upon request of the utility, the applicant provides one or more photographs of the small generator facility site location, components, metering equipment, and other related facilities and equipment; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>There is a successful completion of the witness test, if conducted by the utility.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Level 3 Review Failure.</text>
        <paragraph num="(1)">
          <text>If the small generator facility is not approved under a Level 3 review, the utility shall provide the applicant written notification explaining its reasons for denying the interconnection request.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If the small generator facility is not approved under a Level 3 review, the applicant may submit a new interconnection request for consideration under the Level 4 procedures; however, the queue position assigned to the Level 3 interconnection request shall be retained provided the request is submitted within 15 business days of the notice that the current Level 3 request was not approved.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".12" heading="Level 4 Study Review.">
      <paragraph num="A.">
        <text>A utility shall use the Level 4 study review procedure for an interconnection request that meets the Level 4 criteria in Regulation .08 of this chapter.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Interconnection Request.</text>
        <paragraph num="(1)">
          <text>Within 5 business days from receipt of an interconnection request, the utility shall notify the applicant whether the request is</text>
          <paragraph num="(a)">
            <text>Complete; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Incomplete.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>If the interconnection request is not complete:</text>
          <paragraph num="(a)">
            <text>The utility shall provide the applicant a written list detailing information that shall be provided to complete the interconnection request;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The applicant shall have 10 business days, which may be extended at the request of the applicant and not unreasonably denied by the utility, to provide appropriate data in order to complete the interconnection request, or the interconnection request shall be considered withdrawn; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The interconnection request shall be considered complete:</text>
            <paragraph num="(i)">
              <text>If the required information has been provided by the applicant; or</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The utility and applicant have agreed that the applicant may provide additional information at a later time.</text>
            </paragraph>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Queue Position.</text>
        <paragraph num="(1)">
          <text>When an interconnection request is complete, the utility shall assign a queue position.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The utility shall use the queue position of an interconnection request to determine the cost responsibility necessary for the facilities to accommodate the interconnection.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The utility shall notify the applicant of other higher-queued applicants on the same line section of the new interconnection request.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Any required interconnection studies may not begin until the utility has completed its review of all other interconnection requests that have a higher queue position.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Queue position is not forfeited or otherwise impacted by any pending dispute submitted under the provisions of Regulation .13 of this chapter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Scoping Meeting.</text>
        <paragraph num="(1)">
          <text>By mutual agreement of the utility and applicant, the scoping meeting may be waived and the interconnection feasibility study, interconnection impact study, or interconnection facilities studies provided for in a Level 4 review and discussed in this section may be waived or combined.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If agreed to by the utility and applicant, a scoping meeting shall be held within 10 business days, or other mutually agreed to time, after the utility has notified the applicant that the interconnection request is considered complete, or the applicant has requested that its interconnection request proceed after failing the requirements of a Level 2 review or Level 3 review.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The purpose of the meeting is to review the interconnection request, existing studies relevant to the interconnection request, and the results of the Level 1, Level 2, or Level 3 screening criteria.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>If the utility and applicant agree at a scoping meeting that an interconnection feasibility study shall be performed, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
          <paragraph num="(a)">
            <text>An interconnection feasibility study agreement;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An outline of the scope of the study; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>If the applicant and utility agree at a scoping meeting that an interconnection feasibility study is not required, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
          <paragraph num="(a)">
            <text>An interconnection system impact study agreement;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An outline of the scope of the study; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(6)">
          <text>If the utility and applicant agree at the scoping meeting that an interconnection feasibility study and system impact study are not required, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
          <paragraph num="(a)">
            <text>An interconnection facilities study agreement;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An outline of the scope of the study; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Interconnection Feasibility, Interconnection System Impact, and Interconnection Facilities Studies.</text>
        <paragraph num="(1)">
          <text>Interconnection Feasibility Study.</text>
          <paragraph num="(a)">
            <text>An interconnection feasibility study shall include any necessary analyses for the purpose of identifying a potential adverse system impact to the utility's electric distribution system that would result from the interconnection from among the following:</text>
            <paragraph num="(i)">
              <text>Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Initial identification of any thermal overload or voltage limit violations resulting from the interconnection;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Initial review of grounding requirements and system protection; and</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Description and nonbinding estimated cost of facilities required to interconnect the small generator facility to the utility's electric distribution system in a safe and reliable manner.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>If an applicant requests that the interconnection feasibility study evaluate multiple potential points of interconnection, additional evaluations may be required. Additional evaluations shall be conducted at the expense of the applicant.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>An interconnection system impact study is not required if the interconnection feasibility study concludes there is no adverse system impact, or if the study identifies an adverse system impact and the utility is able to identify a remedy without the need for an interconnection system impact study.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The utility and applicant shall use an interconnection feasibility study agreement form.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The utility shall avoid duplicating previously conducted interconnection studies to the extent possible.</text>
          </paragraph>
          <paragraph num="(f)">
            <text>The utility may require a study deposit of the lesser of 100 percent of estimated nonbinding good faith study costs or $1,000.</text>
          </paragraph>
          <paragraph num="(g)">
            <text>The interconnection feasibility study shall be completed and the results shall be transmitted to the interconnection customer within 30 calendar days after the interconnection feasibility study agreement is signed by the parties.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Interconnection System Impact Study.</text>
          <paragraph num="(a)">
            <text>A distribution interconnection system impact study shall be performed when a potential distribution system adverse system impact is identified in the interconnection feasibility study.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Scope of Interconnection System Impact Study.</text>
            <paragraph num="(i)">
              <text>An interconnection system impact study shall evaluate the impact of the proposed interconnection on both the safety and reliability of the utility's electric distribution system.</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The interconnection system impact study shall identify and detail the system impacts that result when a small generator facility is interconnected without project or system modifications, focusing on the adverse system impacts identified in the interconnection feasibility study, or potential impacts including those identified in the scoping meeting.</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>The interconnection system impact study shall consider all small generator facilities that, on the date the interconnection system impact study is commenced, are directly interconnected with the utility's electric distribution system, have a pending higher queue position to interconnect to the system, or have signed an interconnection agreement.</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>As part of its impact study, the utility shall agree to evaluate and consider any separate studies prepared by the applicant that evaluate alternatives for interconnecting the small generator facility, including the applicant's assessment of potential impacts of the small generator facility on the electric distribution system.</text>
            </paragraph>
            <paragraph num="(v)">
              <text>The utility shall provide the applicant with the utility's final impact study evaluation, including a comparison of the results of its own analyses with those provided by the applicant.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(c)">
            <text>Within 5 business days of transmittal of the interconnection feasibility study report, the utility shall send the applicant:</text>
            <paragraph num="(i)">
              <text>An interconnection system impact study agreement using a form;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>An outline of the scope of the interconnection system impact study; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>A good faith estimate of the cost to perform the study.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(d)">
            <text>The interconnection system impact study shall include any necessary elements from among the following:</text>
            <paragraph num="(i)">
              <text>A load flow study;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Identification of affected systems;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>An analysis of equipment interrupting ratings;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>A protection coordination study;</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Voltage drop and flicker studies;</text>
            </paragraph>
            <paragraph num="(vi)">
              <text>Protection and set point coordination studies;</text>
            </paragraph>
            <paragraph num="(vii)">
              <text>Grounding reviews; and</text>
            </paragraph>
            <paragraph num="(viii)">
              <text>Impact on system operation.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(e)">
            <text>An interconnection system impact study shall consider any necessary criteria from among the following:</text>
            <paragraph num="(i)">
              <text>A short circuit analysis;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>A stability analysis;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Alternatives for mitigating adverse system impacts on affected systems;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Voltage drop and flicker studies;</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Protection and set point coordination studies; and</text>
            </paragraph>
            <paragraph num="(vi)">
              <text>Grounding reviews.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(f)">
            <text>The final interconnection system impact study shall provide the following:</text>
            <paragraph num="(i)">
              <text>The underlying assumptions of the study;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The results of the analyses;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>A list of any potential impediments to providing the requested interconnection service;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>Required distribution upgrades; and</text>
            </paragraph>
            <paragraph num="(v)">
              <text>A nonbinding good faith estimate of cost and time to construct any required distribution upgrades.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(g)">
            <text>The utility may require a study deposit of the lesser of 50 percent of estimated nonbinding good faith study costs or $3,000.</text>
          </paragraph>
          <paragraph num="(h)">
            <text>The interconnection system impact study, if required, shall be completed and the results transmitted to the interconnection customer within 45 calendar days after the interconnection system impact study agreement is signed by the parties.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Interconnection Facilities Study.</text>
          <paragraph num="(a)">
            <text>Within 5 business days of completion of the interconnection system impact study, the utility shall provide to the applicant:</text>
            <paragraph num="(i)">
              <text>A report of the interconnection system impact study;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>An interconnection facilities study agreement;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>An outline of the scope of the interconnection facilities study; and</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>A nonbinding good faith estimate of the cost to perform the facilities study.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>The interconnection facilities study shall identify:</text>
            <paragraph num="(i)">
              <text>The electrical switching configuration of the equipment, including transformer, switchgear, meters, and other station equipment;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The nature and estimated cost of the utility's interconnection facilities and distribution upgrades necessary to accomplish the interconnection, including engineering, procurement, construction, and overhead; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>An estimate of the time required to complete the construction and installation of the facilities.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(c)">
            <text>Third-Party Design or Construction of Interconnection Facilities.</text>
            <paragraph num="(i)">
              <text>The applicant and utility may agree to permit an applicant to separately arrange for a third party to design and construct the required interconnection facilities.</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>The utility may review and approve the design of the facilities under the interconnection facilities study agreement.</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>If the applicant and utility agree to separately arrange for design and construction, the utility, consistent with security and confidentiality requirements, shall make all relevant information and required specifications available to the applicant to permit the applicant to obtain an independent design and cost estimate for the interconnection facilities.</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>The interconnection facilities shall be built in accordance with the specifications in the interconnection facilities study.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(d)">
            <text>Upon completion of the interconnection facilities study, and with the agreement of the applicant to pay for the interconnection facilities and distribution upgrades identified in the interconnection facilities study, the utility shall provide the applicant with an interconnection agreement within 5 business days.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The utility may require a study deposit of the lesser of 50 percent of estimated nonbinding good faith study costs or $10,000.</text>
          </paragraph>
          <paragraph num="(f)">
            <text>In cases where no interconnection upgrades are required, the interconnection facilities study shall be completed and the results shall be transmitted to the interconnection customer within 30 calendar days after the agreement is signed by the parties.</text>
          </paragraph>
          <paragraph num="(g)">
            <text>In cases where interconnection upgrades are required, the interconnection facilities study shall be completed and the results shall be transmitted to the interconnection customer within 45 calendar days after the agreement is signed by the parties.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Interconnection Agreement.</text>
        <paragraph num="(1)">
          <text>When a utility determines, as a result of the interconnection studies conducted under a Level 4 review, that it is appropriate to interconnect the small generator facility, the utility shall provide the applicant with an interconnection agreement.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The applicant shall have either 30 calendar days, or another mutually agreeable time frame after receipt of the interconnection agreement, to sign and return the interconnection agreement.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>If the applicant does not sign the interconnection agreement within 30 calendar days, the request shall be considered withdrawn unless the applicant and utility mutually agree to extend the time period for executing the interconnection agreement prior to the expiration of the 30-calendar-day period. A request for extension may not be unreasonably denied by the utility.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>After the interconnection agreement is signed by the applicant and utility, interconnection of the small generator facility shall proceed according to any milestones agreed to by the applicant and utility in the interconnection agreement.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
          <paragraph num="(a)">
            <text>All milestones agreed to in the interconnection agreement are satisfied;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The small generator facility is approved by electric code officials with jurisdiction over the interconnection;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The applicant provides a certificate of completion to the utility;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Upon request of the utility, the applicant provides one or more photographs of the small generator facility site location, components, metering equipment, and other related facilities and equipment; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>There is a successful completion of the witness test, if conducted by the utility.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Level 4 Review Failure. If the interconnection request is denied, the utility shall provide the applicant a letter explaining the reasons for denying the interconnection request.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".13" heading="Dispute Resolution.">
      <paragraph num="A.">
        <text>The applicant and utility shall attempt to resolve all disputes regarding interconnection as provided in this regulation promptly, equitably, and in a good faith manner.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Dispute Resolution Before the Commission.</text>
        <paragraph num="(1)">
          <text>If a dispute arises, the applicant or utility may seek immediate resolution through the procedures of COMAR 20.32.01.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Dispute resolution shall be conducted in an informal, expeditious manner to reach resolution with minimal costs and delay.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>If a dispute arises involving technical matters regarding the interconnection process, dispute resolution shall be delegated to the Commission’s Engineering Division.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Pursuit of dispute resolution may not affect an applicant with regard to consideration of an interconnection request or an applicant's queue position.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Any deadline imposed by the regulations in this chapter, which is directly affected by any issue in dispute, shall be suspended until resolution of the dispute.</text>
      </paragraph>
      <paragraph num="E.">
        <text>If a satisfactory resolution is not achieved between the applicant and utility, the applicant or utility may request a hearing, pursuant to Public Utilities Article, §3-102, Annotated Code of Maryland.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".14" heading="Record Retention and Reporting Requirements.">
      <paragraph num="A.">
        <text>A utility shall retain records of the following for a minimum of 7 years:</text>
        <paragraph num="(1)">
          <text>The total number nameplate capacity and total fees charged for the interconnection requests received, approved, and denied under Level 1, Level 2, Level 3, and Level 4 reviews;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The number of evaluations of interconnections requests approved and denied using any alternate process under Level 1, Level 2, Level 3, and Level 4 reviews;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The fuel type, if appropriate, total number, and nameplate capacity of small generator facilities approved in each of the following categories:</text>
          <paragraph num="(a)">
            <text>Net metering;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Emergency standby capable of operating in parallel;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Behind the meter load offset;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Combined heat and power;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Energy storage devices; and</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Other;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>The number of interconnection requests that were not processed within the deadlines established for Level 1, Level 2, Level 3, and Level 4 reviews in this chapter;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The number of scoping meetings held, the number of feasibility studies, impact studies, and facility studies performed, and the fees charged for these studies;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>The justifications for the actions taken to deny interconnection requests;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>The number of interconnection requests that were not processed within the deadlines established for Level 1, Level 2, Level 3, and Level 4 reviews in this chapter due to a PJM Interconnection, LLC market process study; and</text>
        </paragraph>
        <paragraph num="(8)">
          <text>Any special operating requirements required in interconnection agreements, which are permitted only for generating facilities with a nameplate capacity greater than 2 MW, that are not part of the utility's standard operating procedures applicable to small generator facilities.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>A utility shall retain records of interconnection studies it performs to determine the feasibility, system impacts, and facilities required by the interconnection of any small generator facility for a minimum of 7 years.</text>
      </paragraph>
      <paragraph num="C.">
        <text>A utility shall file not later than April 1 of each year a report entitled “Annual Small Generator Interconnection Report” to the Commission containing the following information for the preceding calendar year:</text>
        <paragraph num="(1)">
          <text>The total number of interconnection requests received, approved, and denied under Level 1, Level 2, Level 3, and Level 4 reviews;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The fuel type, or energy storage type, total number, and total nameplate capacity of small generator facilities approved in each of the following categories:</text>
          <paragraph num="(a)">
            <text>Net metering;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Emergency standby capable of operating in parallel;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Behind the meter load offset;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Combined heat and power;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Energy storage devices;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>V2G Systems – DC EVSE;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>V2G Systems – AC EVSE; and</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Other;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>The number of interconnection requests that were not processed within the deadlines established for Level 1, Level 2, Level 3, and Level 4 reviews and permission to operate notices in this chapter;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The total number of interconnection requests denied and the reason for each denial;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Each interconnection request for a proposed small generator facility that received a cost estimate or incurred an actual cost of at least $10,000 for interconnection facilities or distribution upgrades and was completed during the reporting year, which shall include:</text>
          <paragraph num="(a)">
            <text>A list of the nameplate capacity of the proposed small generator facility;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Cost variance;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Variance percentage; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>If required, a summary explanation on why the actual cost of facilities or upgrades was at least 10 percent greater than the cost estimate provided;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(6)">
          <text>The number of scoping meetings held, the number of feasibility studies, impact studies, facility studies, and combined studies performed and the total fees charged for these studies;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>For each interconnection request for a proposed small generator facility that failed to meet Level 2 criteria according to Regulation .10F of this chapter, a list of the queue number, reason for failure to meet Level 2 criteria, if the applicant requested additional review, whether the additional review was completed within 30 calendar days, or if the applicant decided to request interconnection under Level 4 criteria;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>The current utility status and future plans and schedule for implementation of hosting capacity reporting systems or improvements to existing hosting capacity reporting systems;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>Beginning April 1, 2021, a utility shall also report annually for the previous year:</text>
          <paragraph num="(a)">
            <text>The total number of restricted circuits and the total number of closed circuits;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The number of interconnection requests totaled for Level 1, Level 2, Level 3, and Level 4 that were denied due to restricted circuits and the total number that were denied due to closed circuits;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The number of interconnection requests for inadvertent export totaled for Level 1, Level 2, Level 3, and Level 4 that were approved, denied, or suspended due to non-compliance;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The number of interconnection requests for flexible interconnection options totaled for Level 1, Level 2, Level 3, and Level 4 that were approved, denied, or suspended due to non-compliance;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The number of cancelled small generator facility projects that result in interconnection costs to subsequent small generator facility projects in the same interconnection queue; and</text>
          </paragraph>
          <paragraph num="(f)">
            <text>The number of small generator facility projects that delay payment for a distribution system upgrade until the time a first higher small generator facility project in an interconnection queue is ready to interconnect;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(10)">
          <text>Beginning April 1, 2024, if Volt-Watt control is implemented in a utility’s default utility required inverter settings profile, a utility shall also report for the electric distribution system annually for the previous year:</text>
          <paragraph num="(a)">
            <text>Number of total interconnection customer complaints about smart inverter related curtailments;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Number of smart inverter related curtailment interconnection customer complaints resolved by utility;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Number of smart inverter related curtailment interconnection customer complaints resolved by customer; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Number of smart inverter related interconnection customer curtailment complaints unresolved; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(11)">
          <text>Beginning April 1, 2025, an electric utility shall report exemptions to Regulation .06R of this chapter annually for the previous year, including:</text>
          <paragraph num="(a)">
            <text>The number of interconnection requests subject to the PJM Interconnection, LLC Tariff;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The number of interconnection requests in an area governed by a hosting capacity upgrade plan approved by the Commission;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The number of interconnection requests on a dedicated primary voltage feeder that may not benefit any other interconnection customer;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The number of interconnection requests on a dedicated secondary voltage facility that may not benefit any other interconnection customer;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The number of interconnection requests on an AC distribution grid or spot network;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>The number of interconnection requests exempted for other good cause; and</text>
          </paragraph>
          <paragraph num="(g)">
            <text>The reason for good cause for each interconnection request exempted from Regulation .06R of this chapter.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>The utility shall file a notice with the Commission describing any interconnection equipment the utility has considered field-approved for its distribution system within 90 days after granting approval for the interconnection of a small generator facility using the field-approved interconnection equipment.</text>
      </paragraph>
      <paragraph num="E.">
        <text>For any small generator facility receiving an interconnection impact study, the utility shall list and explain any study for which the cost of the actual upgrade exceeded the impact study’s estimate by at least 25 percent.</text>
      </paragraph>
      <paragraph num="F.">
        <text>For any small generator facility receiving an interconnection facilities study, the utility shall list and explain any study for which the cost of the actual upgrade exceeded the impact study’s estimate by at least 10 percent.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, 5-303, 7-306, and 7-306.2, and 7-1004, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: June 9, 2008 (35:8 Md. R. 808)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01B amended effective March 20, 2023 (50:5 Md. R. 183)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02B amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04E repealed effective April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436); March 20, 2023 (50:5 Md. R. 183)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .07B amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .08 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .09 amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .09A, E amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .10 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .10A, G amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .11 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .11E amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .12 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .12E, F amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .13C amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .14 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .14C amended effective March 20, 2023 (50:5 Md. R. 183)</annotation>
      <annotation type="History" subtype="Administrative History">Chapter revised effective December 12, 2024 (Md. R. 51:24 1082)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02B amended effective July 7, 2025 (52:13 Md. R. 657)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06N amended effective July 7, 2025 (52:13 Md. R. 657)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .06S adopted effective July 7, 2025 (52:13 Md. R. 657)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .14C amended effective July 7, 2025 (52:13 Md. R. 657)</annotation>
    </annotations>
  </chapter>
  <chapter num="10" heading="Net Metering">
    <regulation prefix="Regulation" num=".01" heading="General.">
      <paragraph num="A.">
        <text>Net Energy Metering. An electric company shall provide net metering of electric service to eligible customer-generators using a meter capable of net energy metering until the rated generating capacity of all eligible customer-generators in the State reaches 1,500 megawatts.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Maximum Size of Electric Generating System — Net Metering. An electric company may not provide net energy metering to an eligible customer-generator operating an electric generating system that has a rated capacity of more than 2 megawatts.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Micro Combined Heat and Power Electric Generating System. An electric company may not provide net energy metering to an eligible customer-generator operating a micro combined heat and power electric generating system that has a rated capacity of more than 30 kilowatts.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Qualifying for Net Energy Metering.</text>
        <paragraph num="(1)">
          <text>In order to initially qualify for net energy metering:</text>
          <paragraph num="(a)">
            <text>An eligible customer-generator shall comply with the provisions of COMAR 20.50.09; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The eligible customer-generator’s proposed electric generating system may not exceed 200 percent of the eligible customer-generator’s baseline annual usage.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Upgraded Electric Generating Systems.</text>
          <paragraph num="(a)">
            <text>When an eligible customer-generator receiving net energy metering proposes an upgrade to an existing electric generating system, an electric company shall re-evaluate the baseline annual usage to determine whether the electric generating system continues to meet the requirements of §D(1)(b) of this regulation.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If the eligible customer-generator’s upgraded electric generating system does not meet the requirements of §D(1)(b) of this regulation, an electric company may discontinue net energy metering.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Metering.">
      <text>An electric company shall ensure that a meter installed for net energy metering is capable of measuring the flow of electricity in two directions.</text>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Tariffs and Contracts.">
      <paragraph num="A.">
        <text>An electric company shall offer net energy metering service to an eligible customer-generator under a Commission-approved standard contract or tariff.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An electric company’s tariff or contract for net metering shall contain an energy rate, a rate structure, and any monthly charge identical to the monthly contract or tariff charge paid by a customer of the rate class in which the eligible customer-generator would be a member if they were not receiving net energy metering service.</text>
      </paragraph>
      <paragraph num="C.">
        <text>An electric company may not include in an eligible customer-generator’s bill rates, charges or fees that raise the eligible customer-generator’s minimum monthly charge above that of customers of the same rate class to which the eligible customer-generator would otherwise be assigned.</text>
      </paragraph>
      <paragraph num="D.">
        <text>An electric company may not charge to an eligible customer-generator new or additional demand charges, standby charges, customer charges, or minimum monthly charges.</text>
      </paragraph>
      <paragraph num="E.">
        <text>An electric company may not require an eligible customer-generator whose electric generating system meets the requirements of this chapter to:</text>
        <paragraph num="(1)">
          <text>Install additional controls;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Perform or pay for additional tests; or</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Purchase additional liability insurance.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Calculation of Net Energy.">
      <paragraph num="A.">
        <text>Net Energy Calculation. An electric company shall calculate net energy in accordance with this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Metering Net Energy — The electric company shall meter net energy produced or consumed on a regular basis in accordance with standard metering practice under this subtitle.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Time-Varying Rates.</text>
        <paragraph num="(1)">
          <text>For eligible customer-generators whose applicable tariff includes time-varying rates, an electric company may calculate net energy separately for each applicable rate period during a billing cycle.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An electric company may apply §§D, E, and F of this regulation separately for each rate period for an eligible customer-generator whose applicable tariff bills using time-varying rates. If net generation is calculated separately for each applicable rate period during a billing cycle, an electric company shall apply §§E and F of this regulation separately for each rate period for an eligible customer-generator whose applicable tariff bills using time-varying rates.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Energy Usage Exceeds Generation — Billing. If the electricity used by an eligible customer-generator exceeds the electricity generated by the eligible customer-generator in a billing month, an electric company shall bill the eligible customer-generator for usage under the terms of Regulation .03 of this chapter.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Generation Exceeds Usage — Billing. If the electricity generated by an eligible customer-generator exceeds the customer’s usage, an electric company shall only bill the eligible customer-generator a customer charge.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Conversion of Excess Generation — Billing. An electric company shall convert any excess electric generation described in §E of this regulation into generation credits upon billing, consistent with the provisions of Regulation .05 of this chapter.</text>
      </paragraph>
      <paragraph num="G.">
        <text>Commercial Customers.</text>
        <paragraph num="(1)">
          <text>An electric company shall use the net hourly energy consumed or produced to assign the energy requirement for commercial eligible customer-generators with interval metering equipment.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>PJM shall use the net energy metered each hour, positive or negative, for the settlement process, even in cases when the total usage by the customer in a month exceeds the electricity generated by a commercial eligible customer-generator with interval metering equipment.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Net Excess Generation.">
      <paragraph num="A.">
        <text>Generation Conversion — Dollar Amount. An electric utility shall convert an eligible customer-generator’s net excess generation to a dollar amount according to this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Conversion Calculation.</text>
        <paragraph num="(1)">
          <text>Except as provided in §C of this regulation, an electric company shall convert net excess generation from kilowatt-hours to dollars by multiplying the net excess generation by the generation or commodity portion of the rate that the eligible customer-generator would have been charged by the electric company averaged over the previous 12-month period ending with the billing cycle that is complete immediately prior to the end of April.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>For customers served by an electricity supplier, the utility shall convert net excess generation in the same manner as described in §B(1) of this regulation except that the dollar value of the net excess generation shall be equal to the generation or commodity rate that the customer would have been charged by the electricity supplier multiplied by the number of kilowatt-hours of net excess generation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Cooperative Electric Company — Conversion Calculation.</text>
        <paragraph num="(1)">
          <text>When net energy metering is provided by a cooperative electric company that serves a population of less than 250,000 in its distribution territory, the eligible customer-generator may choose to be paid for the dollar value of net excess generation remaining at the end of each month instead of at the end of the accrual period specified in §F of this regulation.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If an eligible customer-generator chooses to be paid for the dollar value of net excess generation remaining at the end of each month:</text>
          <paragraph num="(a)">
            <text>The customer-generator may accrue net excess generation on a monthly basis;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The dollar value of the net excess generation shall be equal to the generation or commodity portion of the rate that the eligible customer-generator would have been charged by the electric company for the previous month multiplied by the number of kilowatt-hours of excess generation; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>On or before 30 days after the end of each month, the electric cooperative shall pay the eligible customer-generator for the dollar value of net excess generation remaining at the end of the previous month.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Net Excess Generation — Carry Forward. An electric company shall carry forward accrued net excess generation on a customer’s bill until the net excess generation has been used by the customer or the electric company has paid the customer for the credit under §F of this regulation.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Time-Varying Rates—Carry Forward.</text>
        <paragraph num="(1)">
          <text>For customers on a time-varying rate, an electric company may calculate net excess generation separately for each applicable rate period during a billing cycle.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An electric company may carry forward net excess generation separately for each rate period until the net excess generation has been used by the customer or the electric company has paid the customer for the credit under §F of this regulation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Payment for Generator Credits.</text>
        <paragraph num="(1)">
          <text>On or before 30 days after the billing cycle that is complete immediately prior to the end of April of each year, the electric company shall pay each eligible customer-generator for the dollar value of any accrued net excess generation remaining at the end of previous 12-month period ending with the billing cycle that is complete immediately prior to the end of April.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>On the closure of a net energy metering account of an eligible customer-generator, an electric company shall pay an eligible customer-generator the dollar value of the net excess generation on their account within 15 days.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Safety Standards and Controls for Net Energy Metering.">
      <text>An electric generating system used by an eligible customer-generator for net energy metering shall meet all applicable safety and performance standards incorporated by reference in COMAR 20.50.02.02.</text>
    </regulation>
    <regulation prefix="Regulation" num=".07" heading="Meter Aggregation.">
      <paragraph num="A.">
        <text>When requested in writing by a qualified eligible customer-generator under §B of this regulation, an electric utility shall provide meter aggregation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Customers Qualifying for Aggregation. The following electric utility eligible customer-generators are qualified to request meter aggregation under §A of this regulation:</text>
        <paragraph num="(1)">
          <text>An eligible customer-generator using electrical service for agriculture;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An eligible customer-generator who is a not-for-profit organization or a not-for-profit business; or</text>
        </paragraph>
        <paragraph num="(3)">
          <text>An eligible customer-generator who is a municipal or county government or its affiliated organizations.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>An electric company shall require that an eligible customer-generator requesting meter aggregation under this regulation provide written allocation instructions detailing how to distribute its excess generation credits to each account prior to the commencement of any meter aggregation.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".08" heading="Meter Aggregation Method.">
      <paragraph num="A.">
        <text>This regulation applies to an eligible customer-generator qualifying for meter aggregation under Regulation .07 of this chapter.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Virtual Meter Aggregation.</text>
        <paragraph num="(1)">
          <text>If an aggregation qualified eligible customer-generator’s electrical services are not located close enough to physically interconnect metered service, the electric company shall sum the usage and excess generation of all applicable accounts on a kilowatt-hour basis over each billing period prior to calculating the customer’s excess generation for that billing period.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The electric company shall allocate generated electricity to each account per the instructions of the eligible customer-generator.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Physical Meter Aggregation.</text>
        <paragraph num="(1)">
          <text>For an aggregation qualified eligible customer-generator whose electrical services are located close enough to physically interconnect and meter at a single point, the electric company shall allow the customer to make physical electrical connections and re-establish metering at a single location.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Physically aggregated services must meet all applicable requirements of COMAR 20.50.01 and 20.50.02.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The electric company shall allocate the net-energy used each billing period and the excess generation credit calculated each billing period to each account per the instructions of the customer.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, 5-303, and 7-306, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date:</annotation>
      <annotation type="History" subtype="Administrative History">Regulations .01—.04 and Regulations .06—.08 adopted effective September 5, 2011 (38:18 Md. R. 1078)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04 amended effective September 16, 2024 (51:18 Md. R. 810)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 adopted effective February 20, 2012 (39:3 Md. R. 260)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 amended effective September 16, 2024 (51:18 Md. R. 810)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .07B amended effective July 18, 2016 (43:14 Md. R. 780)</annotation>
    </annotations>
  </chapter>
  <chapter num="11" heading="Deanna Camille Green Rule — Contact Voltage Survey Requirement and Reporting">
    <regulation prefix="Regulation" num=".01" heading="CVRZ, Voltage Survey Plan, and Voltage Survey Requirement.">
      <paragraph num="A.">
        <text>Within 60 days after the effective date of these regulations, each electric company shall file for Commission approval:</text>
        <paragraph num="(1)">
          <text>A list and location map for all CVRZs within its service territory, if applicable; or</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If no CVRZs are designated in its service territory, its voltage survey plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Within 30 days after the Commission approves a CVRZ or CVRZs within an electric company’s service territory, the electric company shall file its voltage survey plan for Commission approval.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Upon approval of the electric company’s voltage survey plan, the electric company shall conduct an initial contact voltage survey of each CVRZ within 1 year of the approval and shall conduct subsequent contact voltage surveys of each CVRZ as set forth in its voltage survey plan.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The electric company shall conduct its initial and each subsequent contact voltage survey within each Commission-approved CVRZ of:</text>
        <paragraph num="(1)">
          <text>All publicly accessible electric distribution plant and electric company-owned or-maintained streetlights that are capable of conducting electricity;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Municipal-owned or governmental-owned streetlights and traffic signals that are publicly accessible and are capable of conducting electricity, if the consent of the municipal government or other appropriate governmental authority is received; and</text>
        </paragraph>
        <paragraph num="(3)">
          <text>All objects and surfaces that are publicly accessible in public parks and playgrounds and that are capable of conducting electricity, if the consent of the municipal government or other appropriate governmental authority is received.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>At least 60 days prior to implementing any material change to its voltage survey plan, the electric company shall file for Commission approval.</text>
      </paragraph>
      <paragraph num="F.">
        <text>For areas within each electric company’s service territory which are not located in a CVRZ, the electric company shall perform an initial contact voltage survey within 3 years of the approval of the voltage survey plan on all publicly accessible electric distribution plant, except for wooden poles, and publicly accessible electric company-owned or-maintained streetlights that are capable of conducting electricity. Subsequent contact voltage surveys for all equipment capable of conducting electricity shall be conducted in accordance with the voltage survey plan.</text>
      </paragraph>
      <paragraph num="G.">
        <text>Streetlights shall be tested for contact voltage after dark or when the light is illuminated.</text>
      </paragraph>
      <paragraph num="H.">
        <text>The Commission may increase or decrease the frequency or scope of any contact voltage survey requirement upon a showing of good cause.</text>
      </paragraph>
      <paragraph num="I.">
        <text>Contact voltage readings shall be conducted in accordance with acceptable methods described in the Institute of Electrical and Electronic Engineers Standard 1695 — 2016.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Contact Voltage Survey Equipment.">
      <text>Each electric company shall include in its voltage survey plan all equipment used for detecting contact voltage. The type of equipment shall be certified by an independent test laboratory as being able to reliably detect voltages of 6 to 600 volts and this certification shall be included with the electric company’s voltage survey plan filing.</text>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Contact Voltage Survey Test Results.">
      <paragraph num="A.">
        <text>Each electric company shall make an area safe after detecting a potential contact voltage condition during its contact voltage survey until the potential condition can be confirmed under §B of this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Each electric company shall confirm and document all contact voltage detected in its contact voltage survey using a voltmeter and a 500 ohm shunt resistor.</text>
      </paragraph>
      <paragraph num="C.">
        <text>For each contact voltage measurement under §B of this regulation greater than or equal to one volt (60 Hertz Alternating Current), each electric company shall:</text>
        <paragraph num="(1)">
          <text>Perform a contact voltage survey on all objects and surfaces that are capable of conducting electricity and are publicly accessible within a minimum 30 foot radius of the location of the measured contact voltage;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>When an electric distribution plant or an electric company-owned or-maintained streetlight is indicating contact voltage, immediately and continuously make the area safe, and use best efforts to make a permanent repair to mitigate the contact voltage as soon as possible, but not later than 45 days, however, a temporary measure to mitigate contact voltage may last longer than 45 days in extraordinary circumstances provided the area remains safe;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>When non-electric company property is indicating contact voltage, immediately use best efforts to make the area safe and immediately use best efforts to notify the customer or responsible person associated with the premises or the customer-owned facility of the unsafe condition and the need for the customer to make a permanent repair to mitigate contact voltage; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Maintain written records of its actions to make the area safe and to mitigate the contact voltage.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Compliance Reporting and Certification.">
      <paragraph num="A.">
        <text>Each electric company shall file, on a form approved by the Commission, an annual compliance report with the Commission:</text>
        <paragraph num="(1)">
          <text>Describing the results of its contact voltage surveys; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Summarizing each known contact voltage electric shock and each contact voltage electric shock complaint received from a member of the public, whether the shock affected a person or animal.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>An initial compliance report shall be filed at the direction of the Commission and subsequent compliance reports shall be filed on or before April 1 of each year for the preceding calendar year.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Civil Penalty.">
      <text>An electric company’s failure to comply with this subtitle may subject the company to civil penalties under the Public Utilities Article.</text>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Waivers and Modifications.">
      <text>The Commission may, in its discretion, waive or modify any provision of this subtitle and may also impose additional requirements as circumstances warrant.</text>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, and 5-303, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: November 28, 2011 (38:24 Md. R. 1503)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01I adopted effective August 21, 2023 (50:16 Md. R. 728)</annotation>
    </annotations>
  </chapter>
  <chapter num="12" heading="Service Quality and Reliability Standards">
    <regulation prefix="Regulation" num=".01" heading="Applicability.">
      <text>These regulations apply to an electric company under Commission jurisdiction with a total number of 40,000 or more customers served in Maryland.</text>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="System-Wide Reliability Standards.">
      <paragraph num="A.">
        <text>Reliability Data. Each utility shall collect and maintain the data required to:</text>
        <paragraph num="(1)">
          <text>Provide in its annual performance reports the reliability information specified in this regulation; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Demonstrate compliance with the reliability standards.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Reliability Reporting Period.</text>
        <paragraph num="(1)">
          <text>Except as otherwise provided in §B(2) of this regulation, the data used by a utility to determine annual reliability performance shall be from the immediately preceding calendar year.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The data used by a utility to determine the poorest performing feeders and multiple device activations shall include outage data from the 12-month period ending September 30 of the immediately preceding calendar year.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Reliability Standards — System-Wide Indices.</text>
        <paragraph num="(1)">
          <text>A utility shall collect and maintain the data necessary to report CAIDI, SAIDI, and SAIFI for its system and each operating district, consisting of all feeders assigned to Maryland under Regulation .03D of this chapter.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>For an investor-owned utility, each index shall be calculated and reported in the annual performance report using the following sets of input data:</text>
          <paragraph num="(a)">
            <text>All interruption data, including and excluding planned outages;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>All interruption data minus major outage event interruption data; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>For the calendar year 2020 and each calendar year thereafter, all interruption data minus the Institute of Electrical and Electronics Engineers’ (IEEE) major event days.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>For cooperatively owned utilities, each index shall be calculated and reported in the annual performance report using the following sets of input data:</text>
          <paragraph num="(a)">
            <text>All interruption data, including and excluding planned outages;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>All interruption data minus major outage event interruption data;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>For the calendar year 2020 and each calendar year thereafter, all interruption data minus the Institute of Electrical and Electronics Engineers’ (IEEE) major event days;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>All interruption data minus major outage event interruption data and minus outage data resulting from an outage event occurring on another utility’s electric system; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>For the calendar year 2020 and each calendar year thereafter, all interruption data minus the Institute of Electrical and Electronics Engineers’ (IEEE) major event days minus outage data resulting from an outage event occurring on another utility’s electric system.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>SAIDI and SAIFI Standards.</text>
        <paragraph num="(1)">
          <text>The SAIDI in minutes and SAIFI reliability standards for the calendar years noted and thereafter, unless changed by the Commission, are as follows:</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Each investor-owned utility's annual SAIDI and SAIFI reliability standard shall be measured against its system-wide annual SAIDI and SAIFI result, including all interruption data minus major outage event interruption data and consisting of all feeders assigned to Maryland under Regulation .03D of this chapter.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>For the calendar year 2020 and each calendar year thereafter, each investor-owned utility’s annual SAIDI and SAIFI reliability standard shall be measured against its system-wide annual SAIDI and SAIFI result, including all interruption data minus the Institute of Electrical and Electronics Engineers’ (IEEE) major event days and consisting of all feeders assigned to Maryland under Regulation .03D of this chapter.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Each cooperatively owned utility's annual SAIDI and SAIFI reliability standard shall be measured against its system-wide annual SAIDI and SAIFI result, including all interruption data minus major outage event interruption data and minus outage data resulting from an outage event occurring on another utility's electric system.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>For the calendar year 2020 and each calendar year thereafter, each cooperatively owned utility’s annual SAIDI and SAIFI reliability standard shall be measured against its system-wide annual SAIDI and SAIFI result, including all interruption data minus the Institute of Electrical and Electronics Engineers’ (IEEE) major event days minus outage data resulting from an outage event occurring on another utility’s electric system.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>A utility's annual SAIDI result shall be equal to or less than its annual SAIDI reliability standard established in §D(1) of this regulation.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>A utility's annual SAIFI result shall be equal to or less than its annual SAIFI reliability standard established in §D(1) of this regulation.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>SAIDI and SAIFI Standards after 2015.</text>
          <paragraph num="(a)">
            <text>For the calendar year 2016 and each calendar year thereafter, the Commission shall establish SAIDI and SAIFI reliability standards and any other appropriate reliability requirements for each utility.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>By March 1, 2014 and every 4 years thereafter, unless otherwise directed by the Commission, each utility:</text>
            <paragraph num="(i)">
              <text>Shall file proposed annual SAIDI and SAIFI reliability standards for its Maryland service territory;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Shall file corresponding cost estimates associated with meeting the proposed SAIDI and SAIFI reliability standards as specified by the Commission; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>May propose any other appropriate reliability requirement for the Commission’s consideration along with supporting comments.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(c)">
            <text>The proposed annual SAIDI and SAIFI reliability standards filed by each utility shall be for a 4-calendar-year period, at a minimum.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>If a utility fails to satisfy the standard §D(6) or (7) of this regulation, it shall provide a corrective action plan, preferably in its annual performance report but by no later than April 1.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Poorest Performing Feeder Standard.">
      <paragraph num="A.">
        <text>Poorest Performing Feeder Standard for Feeders Assigned to Maryland.</text>
        <paragraph num="(1)">
          <text>A utility shall report in its annual performance report CAIDI, SAIDI, and SAIFI indices for all feeders assigned to Maryland that are identified by the utility as having the poorest feeder reliability.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>For each utility, each index shall be calculated and reported in the annual performance report using all interruption data, and all interruption data minus the following exclusions:</text>
          <paragraph num="(a)">
            <text>Source loss, including any outage that occurs on the feeder by an event occurring external to the feeder;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Major outage events; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Planned outages.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>For each utility, the feeders with poorest reliability shall be all feeders having circuit reliability performance 250 percent or more above the utility’s System-Wide SAIFI and SAIDI, which shall be calculated in accordance with the exclusions identified in §A(2) of this regulation.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>No feeder shall appear in a utility’s list of poorest performing feeders during three consecutive 12-month reporting periods, unless the utility has undertaken reasonable remediation measures to improve the performance of the feeder.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Poorest Performing Feeder Standard for Feeders Not Assigned to Maryland.</text>
        <paragraph num="(1)">
          <text>For each feeder not assigned to Maryland that serves more than ten Maryland customers, the utility shall report the feeder in its annual performance report and the feeder’s CAIDI, SAIDI, and SAIFI indices, if the feeder would have been included on the poorest performing feeder list but for the fact that the feeder is not assigned to Maryland.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>For each feeder included in §B(1) of this regulation, the utility shall report the number of customers located in Maryland and the number of customers located in a bordering jurisdiction.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>For each feeder reported in §B(1) of this regulation, the utility shall implement reasonable remediation measures to improve the performance of the feeder portion serving Maryland customers, which measures shall be described by the utility in its annual performance report. If implementing a remediation plan is not reasonable, the utility shall provide an explanation of its decision in its annual performance plan.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The reliability indices and method for identifying the performance of feeders under this provision shall be consistent with §A(2), (3), and (4) of this regulation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Evaluation of Remedial Actions. For the feeders that are identified as having the poorest performance, the utility shall provide the following information:</text>
        <paragraph num="(1)">
          <text>In the annual performance report in which the feeders are identified as requiring reasonable remediation measures, a brief description of the actions taken or proposed, if any, to improve reliability and the actual or expected completion date of the action; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>In the five subsequent annual performance reports, the performance of the feeder shall be reported with its performance ranking.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Feeders Assigned to Maryland.</text>
        <paragraph num="(1)">
          <text>All feeders of a utility that serve only Maryland customers are assigned to Maryland.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>For a utility that has one or more feeders that serve a Maryland customer and at least one customer in a bordering jurisdiction:</text>
          <paragraph num="(a)">
            <text>The feeders used in determining the utility’s system-wide SAIDI and SAIFI performance results as reported to the Commission by the utility’s 2010 annual reliability report shall be assigned to Maryland unless otherwise directed by the Commission;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The utility may not change the assignment list without Commission approval; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>For a new feeder added to the utility's system, or an existing feeder that is modified, that serves more than ten Maryland customers and at least one customer in a bordering jurisdiction, the utility shall file notice with the Commission advising of the feeder's assignment.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>If a utility fails to satisfy the standard in §A(4) of this regulation with respect to a feeder assigned to Maryland, it shall provide a corrective action plan, preferably in its annual performance report but by no later than April 1.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Multiple Device Activation Standard.">
      <paragraph num="A.">
        <text>Each utility shall report in its annual performance report the number of protective devices that activated five or more times during the prior 12-month reporting period specified in Regulation .02B(2) of this chapter causing sustained interruptions in electric service, excluding major outage events and planned outages, to more than ten Maryland customers.</text>
      </paragraph>
      <paragraph num="B.">
        <text>For each device referenced in §A of this regulation, the utility shall evaluate and report in its annual performance report the cause for the multiple activations.</text>
      </paragraph>
      <paragraph num="C.">
        <text>For each device referenced in §A of this regulation, the utility shall implement reasonable remediation measures to reduce the number of activations and describe the measures in its annual performance report.</text>
      </paragraph>
      <paragraph num="D.">
        <text>For each device referenced in §A of this regulation, the device shall not experience five or more activations, including all customer sustained interruption data, during three consecutive 12- month reporting periods, unless the utility has undertaken reasonable remediation measures to improve the performance of the device.</text>
      </paragraph>
      <paragraph num="E.">
        <text>If a utility fails to satisfy the standard in §D of this regulation, it shall provide a corrective action plan, preferably in its annual performance report but by no later than April 1.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Additional Reliability Indices Reporting.">
      <paragraph num="A.">
        <text>A utility shall calculate and report in its supplemental annual performance report the following annual reliability information for its Maryland service territory:</text>
        <paragraph num="(1)">
          <text>All IEEE major event days;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Dates of all IEEE major event days; and</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Number of customers impacted by the IEEE major event day events.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>A utility shall calculate and report in its supplemental annual performance report an annual (CEMIn) for customers experiencing two or more (CEMI2),  four or more (CEMI4), six or more (CEMI6), and eight or more (CEMI8) sustained interruptions unless it does not have the means to make the calculation, in which case it shall provide an explanation of the reason, and an estimate of the cost to provide the information in the future. A utility shall calculate and report:</text>
        <paragraph num="(1)">
          <text>CEMI2, CEMI4, CEMI6, CEMI8, excluding major outage events; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>CEMI2, CEMI4, CEMI6, CEMI8, including major outage events.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>A utility shall calculate and report in its supplemental annual performance report an annual (MAIFIE) for its Maryland service territory unless it does not have the means to make the calculation, in which case it shall provide MAIFI and an explanation of the Utility’s limitation as well as estimated cost to furnish MAIFIE information going forward. A utility shall calculate and report:</text>
        <paragraph num="(1)">
          <text>MAIFIE excluding major outage events; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>MAIFIE including major outage events.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Service Interruption Standard.">
      <paragraph num="A.">
        <text>During each calendar year, a utility shall restore service within 8 hours, measured from when the utility knew or should have known of the outage, to at least 92 percent of its customers experiencing sustained interruptions during normal conditions.</text>
      </paragraph>
      <paragraph num="B.">
        <text>During each calendar year, a utility shall restore service within 50 hours, measured from when the utility knew or should have known of the outage, to at least 95 percent of its customers experiencing sustained interruptions during major outage events where the total number of sustained interruptions is less than or equal to 400,000 or 40 percent of the utility's total number of customers, whichever is less.</text>
      </paragraph>
      <paragraph num="C.">
        <text>If more than one major outage event subject to the standard set forth in §B of this regulation occurs during a calendar year, the restoration percentage shall be calculated by giving equal weight to all sustained interruptions occurring during the major outage events.</text>
      </paragraph>
      <paragraph num="D.">
        <text>During each calendar year, a utility shall restore service as quickly and safely as permitted to its customers experiencing sustained interruptions during each major outage event in which the total number of sustained interruptions is greater than 400,000 or 40 percent of the utility's total number of customers, whichever is less.</text>
      </paragraph>
      <paragraph num="E.">
        <text>If a utility fails to satisfy the standard in §A, B or D of this regulation during the previous calendar year, it shall provide a corrective action plan, preferably in its annual performance report but by no later than April 1.</text>
      </paragraph>
      <paragraph num="F.">
        <text>In the calendar year these regulations become effective, §§A and B of this regulation shall apply from the effective date of the regulations until the end of the calendar year.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".07" heading="Downed Wire Response Standard.">
      <paragraph num="A.">
        <text>Considering data for normal and major outage event conditions for a calendar year, each utility shall respond to a government emergency responder guarded downed electric utility wire within 3 hours after notification by a fire department, police department, or 911 emergency dispatcher at least 90 percent of the time.</text>
      </paragraph>
      <paragraph num="B.">
        <text>If a utility fails to satisfy the standard in §A of this regulation during the previous calendar year, it shall provide a corrective action plan, preferably in its annual performance report but by no later than April 1.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Each utility shall coordinate its response to a government emergency responder guarded downed electric wire consistent with any program established by a fire department, police department, or 911 emergency dispatcher.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Each utility shall exercise reasonable care to reduce the potential hazard caused by a downed electric wire to which its employees, its customers, and the general public may be subjected.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".08" heading="Customer Communications Standards.">
      <paragraph num="A.">
        <text>Customer Telephone Call Answer Time Standard. Each utility shall answer within 30 seconds, on an annual basis, at least 75 percent of all calls offered to the utility for customer service or outage reporting purposes.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Abandoned Call Rate Standard. Each utility shall achieve an annual average abandoned call percentage rate of 5 percent or less, calculated by dividing the total number of abandoned calls by the total number of calls offered to the utility for customer service or outage reporting purposes.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Busy Signals. Each utility shall design its telecommunications systems to accommodate expected volumes of customer calls with minimal or, if possible, no customer busy signals during both normal conditions and major outage events.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Other Customer Communications Information. Each utility shall state in its supplemental annual performance report:</text>
        <paragraph num="(1)">
          <text>Based solely upon those calls offered to its customer service representatives:</text>
          <paragraph num="(a)">
            <text>The percentage of calls that are answered within 30 seconds; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The abandoned call percentage rate; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>The average speed of answer, which shall be calculated by dividing the total amount of time callers spend in queue after requesting to speak to a customer service representative through the automated voice response system by the total number of calls handled, including calls handled by the automated voice response system.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>First Call Resolution. Each utility shall measure the percentage of customer issues resolved that are reported to the utility in a single interaction with its customer service representatives.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Average Handling Time. Each utility shall measure an average amount of time needed to resolve a customer’s request. This includes any time spent on holds, delays, or follow-up actions necessary to fulfill the customer’s needs.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Vulnerable Individuals Notified Before Storms. Each utility shall measure the percentage of vulnerable individual customers notified in advance of a storm event.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Customer Communications Standards Period.</text>
        <paragraph num="(1)">
          <text>Each standard in this regulation is measured using the 12-month period ending December 31.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>For the calendar year in which the regulations become effective, the standards shall be measured from the date the regulations are effective until and including December 31 of that year for reporting purposes only.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Reporting. Each utility shall report its year-ending performance in its annual performance report.</text>
      </paragraph>
      <paragraph num="G.">
        <text>Except as otherwise set forth in §D of this regulation, the standards in this regulation shall apply to customer calls offered to or received by a utility's call overflow system or a third-party vendor retained by the utility.</text>
      </paragraph>
      <paragraph num="H.">
        <text>Corrective Action Plan. If a utility fails to satisfy the standard in §A, B or C, of this regulation, it shall provide a corrective action plan, preferably in its annual performance report but by no later than April 1.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".09" heading="Vegetation Management Requirements.">
      <paragraph num="A.">
        <text>Intent and Scope.</text>
        <paragraph num="(1)">
          <text>It is the intent of the Commission that a utility engage in vegetation management programs that are necessary and appropriate to maintain safety and electric system reliability.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The standards set forth in this regulation shall constitute minimum vegetation management requirements applicable to utilities in the State, and are not intended to supersede or prohibit a utility’s implementation of more aggressive vegetation management standards and practices.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The vegetation management requirements in this chapter apply to the extent not limited by contract rights, property rights, or any controlling law or regulation of any unit of State or local government.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>This regulation applies to any electric transmission plant not regulated by the Federal Energy Regulatory Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Technical Standards for Vegetation Management.</text>
        <paragraph num="(1)">
          <text>Each utility shall ensure that vegetation management conducted on its energized plant is performed in accordance with the standards applicable to Maryland Licensed Tree Experts, which are incorporated by reference under COMAR 08.07.07.02.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Each utility’s vegetation management program shall address, at a minimum, all of the following activities:</text>
          <paragraph num="(a)">
            <text>Tree pruning and removal;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Vegetation management around poles, substations, and energized overhead electric plant;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Manual, mechanical, or chemical vegetation management along rights-of-way;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Inspection of areas where vegetation management is performed after the vegetation management;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Cultural control practices;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Public education regarding vegetation management practices;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Public and customer notice of planned vegetation management activities; and</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Debris management during routine vegetation management and during outage restoration efforts.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Each utility using a call center to handle vegetation management calls shall adopt a script or job aid that is specifically catered to vegetation management practices for usage by call center representatives.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Each utility shall perform periodic reviews of its vegetation management complaints with the goal of improving its complaint resolution process, as necessary.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Each utility shall develop its own vegetation management program, which shall be consistent with this regulation. In developing the program, a utility shall conduct its vegetation management and determine the extent and priority of vegetation management to be performed at a particular site based on these factors:</text>
          <paragraph num="(a)">
            <text>The extent of the potential for vegetation to interfere with poles, substations, and energized overhead electric plant;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The voltage of the affected energized conductor, with higher voltages requiring larger clearances;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The relative importance of the affected energized conductor in maintaining safety and reliability;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The type of conductors and type of overhead construction;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The likely regrowth rate for each species of vegetation at the site;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>The potential movement of energized conductors and vegetation during various weather conditions;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>The utility’s legal rights to access the area where vegetation management is to be performed;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>The maturity of the vegetation;</text>
          </paragraph>
          <paragraph num="(i)">
            <text>The identification of the structural condition of the vegetation, including the characteristics of a species as one having a high probability of causing a service interruption during weather events;</text>
          </paragraph>
          <paragraph num="(j)">
            <text>State and local statutes, regulations, or ordinances affecting utility performance of vegetation management;</text>
          </paragraph>
          <paragraph num="(k)">
            <text>Customer or owner of the property acceptance of the proposed vegetation management where the utility does not have legal rights to perform vegetation management; and</text>
          </paragraph>
          <paragraph num="(l)">
            <text>Any other appropriate factor approved by the Commission.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(6)">
          <text>Each utility shall file a copy of its vegetation management program with the Commission within 90 days of the effective date of this regulation. If a utility makes a change in its vegetation management program, the utility shall file a copy of the change with the Commission no later than 30 days prior to implementing the change, unless exigent circumstances warrant implementation without prior notice, in which case the change shall be filed by no later than 30 days after implementation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Training, Record Keeping, and Reporting.</text>
        <paragraph num="(1)">
          <text>Each utility shall adopt standards, to the extent not covered by other existing law, to be used by all persons who perform vegetation management for the utility, whether employees or contractors, for the proper care of trees and other woody plants, including safety practices and line clearance techniques.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The utility shall monitor and document scheduled vegetation management and related activities the utility or its contractor performs. Documentation shall include, but is not limited to:</text>
          <paragraph num="(a)">
            <text>Identification of each circuit or substation or, if applicable, both circuit and substation where vegetation management was performed;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The type of vegetation management performed including removal, trimming, and spraying and methods used;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The name of the Maryland Licensed Tree Expert responsible for oversight of vegetation management at the circuit or substation level;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The approximate date of activity;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Any occurrence resulting in serious injury to a person as a result of vegetation management activities; and</text>
          </paragraph>
          <paragraph num="(f)">
            <text>When a utility seeks to remove a tree or limb, but is unable to do so because permission or cooperation is not obtained.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Each utility shall include a summary of the information required under §C(2) of this regulation about its vegetation management during the preceding calendar year, and shall describe vegetation management planned for the current calendar year, as part of the annual performance report required to be filed with the Commission under Regulation .11 of this chapter. The annual performance report also shall include:</text>
          <paragraph num="(a)">
            <text>Expenditures for vegetation management measured using all-in vegetation management costs in the preceding calendar year;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Vegetation management budget for the current calendar year;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Circuits or substations, completion dates, and the estimated number of overhead circuit miles trimmed in the preceding calendar year in compliance with the cyclical vegetation management requirements set forth under §F of this regulation;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Circuits or substations and the estimated number of overhead circuit miles scheduled for the current calendar year in compliance with the cyclical vegetation management requirements set forth under §F of this regulation;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Total overhead circuit miles for the system; and</text>
          </paragraph>
          <paragraph num="(f)">
            <text>If applicable, a corrective action plan, preferably in its annual performance report or, if necessary, in the supplemental annual performance report.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>Each utility shall report its own violation of this chapter to the Commission within 60 days of discovery and include its plan for correcting each violation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Public Notice of Planned Vegetation Management.</text>
        <paragraph num="(1)">
          <text>Each utility shall make a reasonable attempt to notify an owner or occupant of all properties upon which cyclical, planned vegetation management is to be performed. This requirement will be satisfied if the utility provides notice to affected property owners or occupants at least 7 days, but not more than 120 days, prior to performing cyclical, planned vegetation management activity. Notice shall be provided by direct mailing, door hanger, postcard, personal contact, or a different method if approved by the Commission, but may not be made solely by bill insert. All direct mailings, door hangers, postcards, or any other method approved by the Commission shall include the contact information of a dedicated group for customers to call for further information. Nothing in this regulation prohibits a utility from using more than one of these methods.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Each utility or its contractor shall provide written notice of any cyclical, planned vegetation management activities to a primary contact for each county and municipality affected at least 2 months before commencing the activities unless the county or municipality notifies the utility that written notification is not required.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Each utility shall include on its website general information about upcoming vegetation management planned work and shall include a link or reference to the Maryland Department of Natural Resources’ website for additional information about tree experts and related information.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>For all tree removals that have been readily identified on residential properties, each utility shall proactively contact the customer or owner of the property to discuss the removal of the tree prior to performing the work.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Each utility shall provide the option for customers or the owner of the property to have direct communication with a utility vegetation management representative within 7 business days.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Outreach Programs.</text>
        <paragraph num="(1)">
          <text>Each utility shall conduct an annual public education program to inform its customers, as well as a primary contact for each county and municipality in the utility’s service territory, of the importance of vegetation management, and of the utility’s role and responsibility in managing vegetation near electric lines, poles, and substations.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The public education program required under this section shall be implemented by direct mail, bill inserts, or a different method if approved by the Commission.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Each utility shall post its vegetation management public education materials on its website.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Specific Requirements. Each utility shall perform vegetation management based on the following schedule:</text>
        <paragraph num="(1)">
          <text>Initially beginning on January 1 of the year immediately following the effective date of this regulation, a utility on a 4-year trim cycle shall within:</text>
          <paragraph num="(a)">
            <text>12 months perform vegetation management on not less than 15 percent of its total distribution miles;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>24 months perform vegetation management on not less than 40 percent of its total distribution miles;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>36 months perform vegetation management on not less than 70 percent of its total distribution miles; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>4 years perform vegetation management on not less than 100 percent of its total distribution miles.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Initially beginning on January1 of the year immediately following the effective date of this regulation, a utility on a 5-year trim cycle shall within:</text>
          <paragraph num="(a)">
            <text>12 months perform vegetation management on not less than 12 percent of its total distribution miles;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>24 months perform vegetation management on not less than 32 percent of its total distribution miles;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>36 months perform vegetation management on not less than 56 percent of its total distribution miles;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>48 months perform vegetation management on not less than 75 percent of its total distribution miles; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>5 years perform vegetation management on not less than 100 percent of its total distribution miles.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Each utility shall follow the vegetation management performance requirement under §F(1) or (2) of this regulation for each subsequent trim cycle.</text>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Vegetation management shall be performed based on the factors set forth under §B(3) of this regulation. The following minimum clearances shall be obtained at the time vegetation management is conducted to the extent not limited by contract rights, property rights or other controlling legal authority:</text>
        <paragraph num="(1)">
          <text>Horizontal clearances:</text>
          <paragraph num="(a)">
            <text>Greater than 34.5 kV: The clearance from the conductors shall be the greater of 15 feet or 4 years’ growth if using a 4-year trim cycle (or 5 years’ growth if using a 5-year trim cycle). Horizontal clearance beneath the conductors shall be measured radially.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>From 14 kV to 34.5 kV: The clearance from the conductors shall be the greater of 10 feet or 4 years’ growth if using a 4-year trim cycle (or 5 years’ growth if using a 5-year trim cycle). Horizontal clearance beneath the conductors shall be measured radially.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Less than 14 kV but at least 600 volts: The clearance from the conductors shall be 4 years’ growth if using a 4-year trim cycle (or 5 years’ growth if using a 5-year trim cycle). Horizontal clearance beneath the conductors shall be measured radially.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>For a conductor with a voltage from 14 kV to 34.5 kV which is operated only as a distribution feeder, the horizontal clearance shall be as set forth under §G(1)(c) of this regulation as if its voltage were less than 14 kV but at least 600 volts.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The horizontal clearances are the minimum clearances the utility shall establish during each cyclical planned vegetation management trim cycle.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Vertical clearances:</text>
          <paragraph num="(a)">
            <text>Greater than 34.5 kV: The vertical clearance above the conductors shall be established by removing all overhanging limbs within the maximum horizontal clearance zone specified under §G(1)(a) of this regulation. The vertical clearance below the conductors shall be the greater of 15 feet or 4 years’ growth (or 5 years’ growth if using a 5-year trim cycle). The vertical clearance below the conductors shall be measured radially. See Figure No. 1</text>
          </paragraph>
          <paragraph num="(b)">
            <text>From 14 kV to 34.5 kV: The vertical clearance above the conductors shall be established by removing all overhanging limbs above the conductors within the horizontal clearance zone specified under §G(1)(b) of this Regulation. The vertical clearance below the conductors shall be the greater of 10 feet or 4 years’ growth (or 5 years’ growth if using a 5-year trim cycle). The vertical clearance below the conductors shall be measured radially. See Figure No. 2.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Less than 14 kV but at least 600 volts:</text>
            <paragraph num="(i)">
              <text>Multiple open wires on a cross-arm or armless construction from the substation to the first protective device: The vertical clearance above the conductors shall be established by removing all overhanging limbs above the conductors within the horizontal clearance zone specified under §G(1)(c) of this regulation. The vertical clearance below the conductors shall be 4 years’ growth (or 5 years’ growth if using a 5-year trim cycle). The vertical clearance below the conductors shall be measured radially. See Figure 3.</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Except as provided in §G(2)(c)(i) for multiple open wires on a cross-arm or armless construction, the vertical clearance above the conductors shall be 15 feet. The vertical clearance below the conductors shall be 4 years’ growth (or 5 years’ growth if using a 5-year trim cycle). The vertical clearances above and below the conductor shall be measured radially.</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Spacer cable, tree wire with messenger cable above, aerial cable, and single-phase: The vertical clearance above the conductors shall be 6 feet. The vertical clearance below the conductors shall be 4 years’ growth (or 5 years’ growth if using a 5-year trim cycle). The vertical clearance above and beneath the conductors shall be measured radially.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(d)">
            <text>For a conductor with a voltage from 14 kV to 34.5 kV which is operated only as a distribution feeder, the vertical clearance shall be as set forth in the corresponding standard contained in §G(2)(c) of this regulation as if its voltage were less than 14 kV but at least 600 volts.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The vertical clearances are the minimum clearances the utility shall establish during each cyclical planned vegetation management trim cycle.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Mature trees may be exempt from the minimum clearance requirements specified above at the utility's reasonable discretion for voltage levels at 34.5 kV and below.</text>
        </paragraph>
      </paragraph>
      <paragraph num="H.">
        <text>Federal Energy Regulatory Commission Jurisdictional Transmission Plant. Each utility shall file with the Commission’s Engineering Division a copy of all Vegetation Management Transmission Outage Report filings associated with a transmission line outage in Maryland that are filed with the Federal Energy Regulatory Commission or an entity approved by the Federal Energy Regulatory Commission. If the information is confidential or critical energy infrastructure information, the utility shall advise the Commission’s Engineering Division in writing and make the information available for review at a mutually agreeable time and location.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".10" heading="Periodic Equipment Inspections.">
      <paragraph num="A.">
        <text>Each utility shall adopt and follow written operation and maintenance procedures for its electric plant in order to maintain safe and reliable service. The operation and maintenance programs shall account for the utility's experience, good engineering practices, and judgment, and manufacturer’s recommendations.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Each electric utility shall file its written operation and maintenance programs required under §A of this regulation with the Commission within 60 days from the effective date of these regulations and the programs shall be designed to achieve, at a minimum, the level of reliability established by the Commission's regulations.</text>
      </paragraph>
      <paragraph num="C.">
        <text>If the electric utility makes a material change to its written operation and maintenance programs required under §B of this regulation, the utility shall file the change with the Commission not less than 60 days prior to implementing the change, unless exigent circumstances warrant implementation without prior notice, in which case the change shall be filed by no later than 30 days after implementation. The filing shall describe each change and the reason for the change.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The operation and maintenance programs required by §B of this regulation shall:</text>
        <paragraph num="(1)">
          <text>Include the frequency or triggers for performing an inspection;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Identify the electric plant inspections to be performed; and</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Identify acceptance criteria for the inspections.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Except as provided under §D of this regulation and Regulation .09 of this chapter, the operation and maintenance programs required by §B of this regulation need not include detailed procedures and shall include a description of the corrective maintenance priorities and general timelines for the overall repair of the electric plant.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Each utility shall maintain sufficient records to give evidence of compliance with its operation and maintenance programs and shall self-report compliance and non-compliance with its maintenance program each year in its annual performance report.</text>
      </paragraph>
      <paragraph num="G.">
        <text>If a utility fails to comply with its operation and maintenance programs and has not received a stay of enforcement pursuant to §H of this regulation, the utility shall provide a corrective action plan, preferably in its annual performance report but by no later than April 1.</text>
      </paragraph>
      <paragraph num="H.">
        <text>If a utility cannot perform regular periodic electric plant maintenance work on its electric distribution system according to timeline requirements documented in its operation and maintenance program manual or its vegetation management program pursuant to Regulation .09 of this chapter, the electric company may request a stay of enforcement on a form specified by the Commission. The stay of enforcement request shall demonstrate that the electric company has a good cause for delay, can maintain safety and reliability for the duration of the stay of enforcement, and provides an abatement plan to return to normal timeline requirements. Approval of both the stay of enforcement request and the return to normal shall be delegated to the Commission’s Engineering Division.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".11" heading="Annual Performance Reports.">
      <paragraph num="A.">
        <text>On or before April 1 of each year, each utility shall file an annual performance report which shall include, at a minimum, the following:</text>
        <paragraph num="(1)">
          <text>The reliability index information and results required in this chapter, including a table showing the actual values of the reliability indices required in this chapter for each of the preceding 3 calendar years;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Annual year-end and 3-year average performance results as required under Public Utilities Article, §7-213(g)(2)(i) and (ii), Annotated Code of Maryland, including a table showing the actual values for each of the preceding 3 calendar years;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The time periods during which major outage event interruption data and, if a cooperatively owned utility, the outage data resulting from an outage event occurring on another utility's electric system was excluded from the CAIDI, SAIDI, and SAIFI indices, including a brief description of the interruption causes during each time period;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>A description of the utility’s reliability objectives, planned actions and projects, and programs for providing reliable electric service;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>An assessment of the results and effectiveness of the utility’s reliability objectives, planned actions and projects, programs, and load studies in achieving an acceptable reliability level as required under Public Utilities Article, §7-213(g)(2)(iii), Annotated Code of Maryland. The assessment of the results and effectiveness shall include, to the extent estimated or determined by the utility, the program's, project’s, or planned action’s impact on reliability indices, including CAIDI, SAIDI, and SAIFI and any other reliability index considered. The method for estimating or determining the impact on any reliability index shall be explained;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Current year expenditures, an estimate or budget amount for the following 2 calendar years, if available, current year labor resources hours, and progress measures for each capital and maintenance program designed to support the maintenance of reliable electric service as required under Public Utilities Article, §7-213(g)(2)(iv)(1), Annotated Code of Maryland;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>An explanation for any material differences between current year expenditures and cost estimates filed pursuant to §A(6) of this regulation;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>The number of outages by outage type as required under Public Utilities Article, §7-213(g)(2)(iv)(2), Annotated Code of Maryland, including planned outage, nonplanned outage minus major outage event, and major outage event;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>The number of outages by outage cause required under Public Utilities Article §7-213(g)(2)(iv)(3), Annotated Code of Maryland, including, but not limited to, animals, overhead equipment failure, and underground equipment failure;</text>
        </paragraph>
        <paragraph num="(10)">
          <text>The total number of customers that experienced an outage required under Public Utilities Article, §7-213(g)(2)(iv)(4), Annotated Code of Maryland;</text>
        </paragraph>
        <paragraph num="(11)">
          <text>The total number of customer minutes of outage time required under Public Utilities Article, §7-213(g)(2)(iv)(5), Annotated Code of Maryland;</text>
        </paragraph>
        <paragraph num="(12)">
          <text>To the extent practicable, a breakdown, by the number of days each customer was without electric service, of the number of customers that experienced an outage required under Public Utilities Article, §7-213(g)(2)(iv)(6), Annotated Code of Maryland;</text>
        </paragraph>
        <paragraph num="(13)">
          <text>Poorest performing feeder information and results required in this chapter; and</text>
        </paragraph>
        <paragraph num="(14)">
          <text>Multiple device activation information and results required in this chapter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>On or before April 1 of each year, each utility shall file a supplemental annual performance report which shall include, at a minimum, the following:</text>
        <paragraph num="(1)">
          <text>The actual operation and maintenance and capital expenditures for the past 3 calendar years for each of the utility's reliability programs, including, but not limited to underground and overhead distribution plant inspection, maintenance and replacement programs, vegetation management, subtransmission inspection and maintenance programs, and distribution substation plant inspection and maintenance programs;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Service restoration requirement information and results required in this chapter;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Downed wire response performance information and results required in this chapter;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Customer communications performance information and results required in this chapter;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The vegetation management information required in this chapter;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Periodic equipment inspection information and results required in this chapter;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>For the immediately preceding calendar year, and considering normal conditions only:</text>
          <paragraph num="(a)">
            <text>The number of downed electric utility wires to which the utility responded in:</text>
            <paragraph num="(i)">
              <text>3 hours or less;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>More than 3 hours but less than 8 hours; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>8 hours or more; and</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>The total number of downed electric utility wires reported to the utility;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(8)">
          <text>Any corrective action plans required under Public Utilities Article, §7-213(e)(1)(iii), Annotated Code of Maryland, or this chapter; and</text>
        </paragraph>
        <paragraph num="(9)">
          <text>The number of manhole and conduit events during the preceding year that result in a lid displacement, the date of the event, the location and feeder designation, whether the event involved a feeder, primary or secondary services, and the number of customer outages recorded.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>The Commission may designate a specific report format for the information required to be included in the written reports mandated under §§A and B of this regulation.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The Commission may require reporting information required to track performance under these regulations on a quarterly basis on a form approved by the Commission.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".12" heading="Major Outage Event Plan.">
      <paragraph num="A.">
        <text>Within 60 days of the effective date of this regulation, each utility shall file a major outage event response plan providing a description of and procedures for its response to major outage events, and performance measures associated with the assessment of the implementation of the major outage event response plan, including, but not limited, to the following topics and issues:</text>
        <paragraph num="(1)">
          <text>Preparation, training, and drills;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Early warning and storm tracking;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Emergency organization structure;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Activation and mobilization;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Materials management and logistics;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Major outage event restoration priorities, including, but not limited to:</text>
          <paragraph num="(a)">
            <text>How the utility prioritizes restoration customers; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>How the utility communicates with customers that are identified as high priority due to medical needs for electricity and how it schedules restoration actions for such customers;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(7)">
          <text>Damage assessment;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>Public safety, including wire down response;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>Crew deployment;</text>
        </paragraph>
        <paragraph num="(10)">
          <text>External communications, including communications with emergency officials, the public, and other persons;</text>
        </paragraph>
        <paragraph num="(11)">
          <text>Internal communications;</text>
        </paragraph>
        <paragraph num="(12)">
          <text>Communications technology use, including high call volume capability and capacity;</text>
        </paragraph>
        <paragraph num="(13)">
          <text>Development of estimated times of restoration and assessment of estimated times of restoration accuracy;</text>
        </paragraph>
        <paragraph num="(14)">
          <text>Ramp-down; and</text>
        </paragraph>
        <paragraph num="(15)">
          <text>Major outage event performance review.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Each utility shall file with the Commission any material change to its major outage event response plan at least 60 days prior to implementation, unless it will delay implementation of the change in a manner inconsistent with restoring service in the shortest time practicable, in which case the change shall be filed by no later than 30 days after implementing the change.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Each utility shall comply with its major outage event response plan when preparing for and responding to major outage events.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The major outage event response plan shall be filed as a publicly available document. To the extent that some information may be considered confidential, a redacted version shall also be filed.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Major outage event response plan information may be shared without restriction with state officials that participate in a Maryland Department of Emergency Management activation of the State Emergency Operations Center.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".13" heading="Major Outage Event Reporting.">
      <paragraph num="A.">
        <text>Written Reports. Each utility shall file a written report with the Commission within 35 calendar days of the end of a major outage event.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Contents. The written report shall contain:</text>
        <paragraph num="(1)">
          <text>The total number of Maryland customers served by the utility;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The date and time when the major outage event started;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The date and time when all sustained interruptions in Maryland related to the major outage event were restored;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The total number of Maryland customers who experienced a sustained interruption of service related to the major outage event;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The total number of customer interruption hours experienced by customers reported under §B(4) of this regulation;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>The average duration of customer service interruption, expressed in hours, and calculated by dividing the total number of customer interruption hours reported in §B(5) of this regulation by the total number of Maryland customers who experienced an interruption reported in §B(4) of this regulation;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>The maximum number of Maryland customers who concurrently experienced a sustained interruption related to the major outage event and the date and time this occurred;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>The number of Maryland customers who experienced a sustained interruption recorded at a maximum of 6-hour intervals throughout the major outage event;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>Information about requests for outside assistance, including the:</text>
          <paragraph num="(a)">
            <text>Name of the organization to which the request was made;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Date and time of the request; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Resources requested;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(10)">
          <text>Information about outside assistance received, including the:</text>
          <paragraph num="(a)">
            <text>Name of the organization providing crews and the nature of the assistance, i.e., mutual assistance, third-party contractor crew normally dedicated to the utility, additional third-party contractor crew, or other (explain in report);</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Date and time of crew arrivals and departures;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Number and types of vehicles;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Total number of personnel;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Number of personnel on primary overhead line crews;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Number of personnel on secondary overhead line crews;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Number of personnel on tree trimming crews; and</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Number of other personnel.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(11)">
          <text>Information about electric utility crews working on restoration, including the following:</text>
          <paragraph num="(a)">
            <text>Number and types of vehicles;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Total number of personnel;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Number of personnel on primary overhead line crews;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Number of personnel on secondary overhead line crews;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Number of personnel on damage assessment crews;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Number of personnel on tree trimming crews; and</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Number of other personnel.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(12)">
          <text>The following information about communications with customers:</text>
          <paragraph num="(a)">
            <text>The total number of calls received by the utility during each hour of the major outage event;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The total number of calls answered by the utility’s voice response system, customer service representatives, and any high volume call systems during each hour of the major outage event;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The total number of customer service representatives logged into the call center and supporting phone systems actively taking or waiting to take customer calls on an hourly basis during the major outage event; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>On a daily basis during the length of the outage and for the entire major outage event, the percentage of all calls that were offered and answered by the utility’s voice response system, customer service representatives, and any high volume call systems within a 30-second timeframe and within a 60-second timeframe.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(13)">
          <text>With regard to system damage, the number of each of the following occurring during restoration:</text>
          <paragraph num="(a)">
            <text>Poles replaced as a percentage of total utility owned or partially owned poles;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Distribution transformers replaced;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Fuses replaced;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Downed wires;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Substations with damaged equipment and substations outages due to loss of one or multiple supplies;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>State highways blocked due to electric utility wires that are referred to the utility for remediation; and</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Traffic signals reported out of service by government agencies that are referred to the utility for remediation;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(14)">
          <text>Any issues concerning the availability of materials or equipment that affected restoration progress, including a description of how any unavailability affected restoration, and a description of the emergency measures taken to resolve the issues;</text>
        </paragraph>
        <paragraph num="(15)">
          <text>A self-assessment, including lessons learned and future plans to improve service restoration efforts during major outage events;</text>
        </paragraph>
        <paragraph num="(16)">
          <text>A description of the manner in which customers were informed of the status of the outages in their geographic area by means of the customer call center or by other means of customer communications;</text>
        </paragraph>
        <paragraph num="(17)">
          <text>A description of the manner in which the utility informed elected officials, government officials, and members of the public of the status of the outage and restoration efforts;</text>
        </paragraph>
        <paragraph num="(18)">
          <text>A description of the manner in which the utility estimated restoration times;</text>
        </paragraph>
        <paragraph num="(19)">
          <text>A description of any areas where the utility did not comply with its major outage event response plan;</text>
        </paragraph>
        <paragraph num="(20)">
          <text>The number of customer service interruptions under §B(4) of this regulation and the number of customer service interruption hours under §B(5) of this regulation categorized by outage caused by each one of the following:</text>
          <paragraph num="(a)">
            <text>All outage causes typically provided in annual performance reports pursuant to Regulation .11 of this chapter;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A description of the outage causes due to physical security or cybersecurity attacks;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A description of any outage causes due to transmission or energy supply disruptions;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>A description of any other outage causes due to natural weather phenomena not typically encountered;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Ice accumulation on conductors; and</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Each other direct cause of interruption of service to 5 percent or more of total customers interrupted, listing and providing a descriptive name for each cause;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(21)">
          <text>For each interruption to normal expected information technology systems used to manage a major outage event, details on deficiencies experienced in these systems including dates, time, and duration of any interruptions to normal expected functionality for the following:</text>
          <paragraph num="(a)">
            <text>Real time operating systems used to monitor and control the event including, but not limited to, distribution automation systems, energy management systems, and outage management systems;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Advanced meter infrastructure systems;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Web-based outage reporting systems;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Web-based outage information systems such as outage maps;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Interactive Voice Response (IVR) systems;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Phone systems;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Mobile data systems used to receive information from field crews;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>The data interface that provides outage information to the Maryland Department of Emergency Management outage map application; and</text>
          </paragraph>
          <paragraph num="(i)">
            <text>Any utility business systems directly impacted by the major outage event;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(22)">
          <text>The percentage of total Maryland customers who had service restored in 50 hours pursuant to Regulation .06B of this chapter;</text>
        </paragraph>
        <paragraph num="(23)">
          <text>If the company could not safely work due to high wind conditions for the major outage event, an explanation of the company policy and how this impacted restoration;</text>
        </paragraph>
        <paragraph num="(24)">
          <text>The percentage of calls that are answered within 30 seconds, the abandoned call percentage rate, and the average speed of answer pursuant to Regulation .08D of this chapter, except measured only for the duration of the major outage event;</text>
        </paragraph>
        <paragraph num="(25)">
          <text>The average amount of time customers were put on hold for every hour during the major outage event after the customer selected the option to talk to a call center representative in the electric company’s Interactive Voice Response (IVR) system:</text>
          <paragraph num="(a)">
            <text>Before talking to a call center representative; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Before dropping off the call after waiting unsuccessfully to reach a call center representative.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(26)">
          <text>For the duration of the major outage event, the number of customers experiencing multiple sustained interruptions, categorized by the number of multiple sustained interruptions, such as the number of customers experiencing “n” sustained interruptions, where n= 1, 2, 3, etc.;</text>
        </paragraph>
        <paragraph num="(27)">
          <text>The downed wire response performance to a government emergency responder guarded downed electric utility wire within 3 hours after notification by a fire department, police department, or 911 emergency dispatcher pursuant to Regulation .07A of this chapter, except measured only for this major outage event;</text>
        </paragraph>
        <paragraph num="(28)">
          <text>The number of peak sustained interruptions restored by county and municipal jurisdiction for the duration of the major outage event;</text>
        </paragraph>
        <paragraph num="(29)">
          <text>The number of customers sustained interruptions caused by off-right-of-way trees;</text>
        </paragraph>
        <paragraph num="(30)">
          <text>All press releases, if any, issued and details on the date, time, location, and company participants in all press conferences held, if any;</text>
        </paragraph>
        <paragraph num="(31)">
          <text>The date and time centralized and regional emergency operations centers, district headquarters, and mutual assistance staging areas activated for the major outage event were operational completed;</text>
        </paragraph>
        <paragraph num="(32)">
          <text>Electric system infrastructure that was damage assessed and how this damage assessment information was used to establish a Global ETR;</text>
        </paragraph>
        <paragraph num="(33)">
          <text>The number of Maryland critical facilities who experienced a sustained interruption recorded at a maximum of 6-hour intervals throughout the major outage event; and</text>
        </paragraph>
        <paragraph num="(34)">
          <text>The percentage critical facility sustained interruptions restored within 24 hours and 48 hours of the start of the major outage event.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>The Commission may designate a specific report format for the information required to be included in the written report mandated under this regulation.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".14" heading="Customer Perception Surveys.">
      <paragraph num="A.">
        <text>Each utility shall perform a customer perception survey no less than every 4 years.</text>
      </paragraph>
      <paragraph num="B.">
        <text>The objective of the survey is to measure customer perceptions regarding the utility's overall performance, reliability performance, vegetation management activities, effectiveness of customer communications, and service quality performance.</text>
      </paragraph>
      <paragraph num="C.">
        <text>By April 1, 2026, and every 4 years thereafter, unless otherwise directed by the Commission, each utility shall file customer perception survey results that shall be included with each utility’s submittal under Regulation .02D(7)(b) of this chapter.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Each utility shall use a survey process as determined by the Commission, in which the survey question themes and associated rating scales shall be consistent among all utilities.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Each utility shall determine a communication methodology to reach customers in regard to collecting survey data and survey sample size to reflect a margin of error of plus or minus 5 percent at a minimum 90 percent confidence level for both the residential and commercial customer segments.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".15" heading="Resilience Plans.">
      <paragraph num="A.">
        <text>This regulation applies after January 1, 2024.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An electric utility shall have resilience plans to prepare for and recover from various utility-defined credible event threat scenarios such as pandemics, physical attacks, cyber attacks, electric supply shortages, weather events, significant infrastructure failures, and other credible disturbances with the potential to lead to large and widespread electric outages or loss of critical facilities essential for public health and safety.</text>
      </paragraph>
      <paragraph num="C.">
        <text>In consultation with State and local jurisdictions, a utility’s resilience plans shall identify critical facilities.</text>
      </paragraph>
      <paragraph num="D.">
        <text>An electric utility’s resilience plans shall be made confidentially available for Commission inspection, upon request.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".16" heading="Specific Information Request.">
      <paragraph num="A.">
        <text>After a complaint, report, or inspection, the Commission’s Engineering Division may send an electric company a specific information request.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An electric company shall respond within 10 working days after receipt of a specific information request relating to a possible reportable incident under COMAR 20.50.03.04F.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Except as provided under §B of this regulation, an electric company shall respond within 30 days after receipt of a specific information request.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The Commission’s Engineering Division may waive the requirements of §B or C of this regulation upon written request from an electric company operator demonstrating sufficient cause.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".17" heading="Electric Underground Location Services.">
      <paragraph num="A.">
        <text>A utility shall make available suitable equipment and personnel to provide electric underground location services upon reasonable request of interested persons, in compliance with Public Utilities Article, Title 12, Subtitle 1, Annotated Code of Maryland.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".18" heading="Estimated Times of Restoration and Associated Messaging.">
      <paragraph num="A.">
        <text>In the absence of conditions that allow or dictate a more circumscribed ETR, a utility shall issue a Global ETR within 24 hours of the end of the cause of the major outage event. Should completion of the damage assessment required as the result of the major outage event require more time, this period shall be extended by the electric company.</text>
      </paragraph>
      <paragraph num="B.">
        <text>The Global ETR should be reviewed at least once every 24 hours and modified when information is received that would significantly change the Global ETR or allow a more precise ETR for a specific, smaller area.</text>
      </paragraph>
      <paragraph num="C.">
        <text>An assessment message statement that indicates the electric company is assessing the system, including a safety message, should be posted within 4 hours, if not immediately, upon the end of the cause of the major outage event.</text>
      </paragraph>
      <paragraph num="D.">
        <text>A restoration message statement that indicates when a majority of the electric company’s customers within the entire service territory will be restored shall be delivered to customers within 24 hours following completion of the initial damage assessment.</text>
      </paragraph>
      <paragraph num="E.">
        <text>When a Zonal ETR can be established, the electric company shall issue a restoration message statement that indicates when at least 90 percent of the electric company’s customers, who were affected by the original major outage event within a zone, will be restored.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Global and Zonal ETRs will be reviewed by the utility, at least once every 24 hours during a major outage event and updated when better information becomes available.</text>
      </paragraph>
      <paragraph num="G.">
        <text>An ETR, whether Global or Zonal, shall be considered accurate if at least 90 percent of the customers affected by the original storm event are restored by the last applicable Global or Zonal ETR provided to the customer.</text>
      </paragraph>
      <paragraph num="H.">
        <text>Following a major outage event, utilities shall perform a self-assessment of the quality of Global and Zonal ETRs provided to customers as part of lessons learned activities in its Major Outage Event Report pursuant to COMAR 20.50.12.13. Elements to be considered include the accuracy of the original ETR in terms of hours, the number of adjustments to the original ETR, the reasons for updating the ETR, significant external influences that may have contributed to the changes, and the accuracy of the final ETR in terms of hours.</text>
      </paragraph>
      <paragraph num="I.">
        <text>All utilities shall engage in consumer education programs to help customers better understand all aspects of emergency preparedness and outage restoration related to a major outage event.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§7-213, 13-201, and 13-202, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: May 28, 2012 (39:10 Md. R. 661)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01 amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02 amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02C, D amended effective December 2, 2019 (46:24 Md. R. 1104)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02D amended effective January 7, 2016 (42:26 Md. R. 1596)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04A, D amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05 amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .05A amended effective December 2, 2019 (46:24 Md. R. 1104)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .07A amended effective December 2, 2019 (46:24 Md. R. 1104)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .08D amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .09 amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .10 amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .11A amended effective March 18, 2013 (40:5 Md. R. 412); December 2, 2019 (46:24 Md. R. 1104)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .11B amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .12A, B amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .12D, E adopted effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .13 amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .14 amended effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .15 adopted effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .16 adopted effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .17 adopted effective August 21, 2023 (50:16 Md. R. 728)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .18 adopted effective August 21, 2023 (50:16 Md. R. 728)</annotation>
    </annotations>
  </chapter>
  <chapter num="15" heading="Electric System Planning">
    <regulation prefix="Regulation" num=".01" heading="Applicability.">
      <paragraph num="A.">
        <text>This chapter applies to Electric System Plans for the advancement of the State policy goals and legislative intent set forth at Public Utilities Article, §§7-801—7-804, et seq., Annotated Code of Maryland, and all other relevant State goals and targets in effect during plan development. The objective of the final Electric System Plan is an electric system that advances State policy goals and is built in a manner that enables an electric company to provide safe, reliable, and cost-effective services and otherwise operates for the public good.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An Electric System Plan shall demonstrate a holistic approach to grid planning by:</text>
        <paragraph num="(1)">
          <text>Considering cost-effective solutions to electric system needs;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Incorporating new cost-effective technologies and analytical tools into planning processes to create a modern distribution system;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Utilizing real-time data to improve forecasting and planning for grid investments; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Addressing issues related to other relevant Commission proceedings.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>This chapter shall not become effective for electric cooperatives and municipal electric companies until January 1, 2028.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Electric company and gas company coordination on Electric System Plans may be performed, but shall not be required, unless required by law or as otherwise directed by the Commission.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Waiver of Regulations. Upon written request, a regulation in this chapter may be waived by the Commission for “good cause shown”.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Definitions.">
      <paragraph num="A.">
        <text>Terms Defined.</text>
        <paragraph num="(1)">
          <text>“Annual Electric System Plan Update” means the update that electric companies publish annually at the end of the distribution system planning cycle in the years that they do not publish an Electric System Plan and that contains the information in Regulation .04B of this chapter.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>“Baseline scenario” means an expected future state of a system or situation if no new interventions or policies are implemented beyond those already in place. It serves as a point of comparison to assess the impact of proposed actions or policies.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>“Cost-effective” means having projected benefits that are greater than projected costs while considering other factors as determined by the Commission.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>“Demand response” means changes in electric usage by demand-side resources from their normal consumption patterns in response to changes in the price of electricity over time or to incentive payments designed to induce lower electricity use at times of high wholesale market prices or ensure system reliability.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>“Distributed energy resource (DER)” has the meaning stated in COMAR 20.50.09.02B.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>“Distributed generation” means the same definition as Small Generator Facility in COMAR 20.50.09.02B.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>“Electric company” has the meaning stated in Public Utilities Article, §1-101, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>“Energy storage device” has the meaning stated in Public Utilities Article, §7-216, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>“Electric System Plan” means the plan that electric companies publish pursuant to Regulation .04J of this chapter that concludes the distribution system planning cycle.</text>
        </paragraph>
        <paragraph num="(10)">
          <text>“Electric vehicle (EV)” has the meaning stated in COMAR 20.50.09.02B.</text>
        </paragraph>
        <paragraph num="(11)">
          <text>“Goal scenario” means a potential future state of a system or situation if policy goals are fully realized and it serves as a point of comparison to assess the progress towards policy goals.</text>
        </paragraph>
        <paragraph num="(12)">
          <text>“Grid needs” means the need for a specific mitigating action to alleviate an identified system constraint found during the electric system planning process. The specific characteristic of the system constraint and commensurate grid need will inform the solution that will mitigate the issue.</text>
        </paragraph>
        <paragraph num="(13)">
          <text>“Grid services” means the dispatch and control of one or more DERs to provide service to the electric company’s electric grid pursuant to an electric company tariff, service contract between the electric company and the owner of DERs or providing transmission-level grid services by participating in PJM Interconnection, LLC wholesale markets.</text>
        </paragraph>
        <paragraph num="(14)">
          <text>“Hosting capacity” has the meaning stated in COMAR 20.50.09.02B.</text>
        </paragraph>
        <paragraph num="(15)">
          <text>“Locational value assessment” means a process that provides price signals based on the benefits and costs of deploying distributed energy resources in a specific location and over time, considering grid conditions and the potential to defer or avoid traditional electric distribution infrastructure investments.</text>
        </paragraph>
        <paragraph num="(16)">
          <text>“Non-wires solution (NWS)” means a project or other solution that makes use of one or more DERs, technologies, and/or leads to the introduction of new or modification of existing energy management practices, standards, or protocols to address a system constraint or provide other grid services to the electric system.</text>
        </paragraph>
        <paragraph num="(17)">
          <text>“Planning metrics” means quantifiable measurements used to assess performance, track progress, and/or measure success of a process that an electric company electric system plan directly affects.</text>
        </paragraph>
        <paragraph num="(18)">
          <text>“Preliminary Electric System Plan” means the plan that electric companies file before the annual technical conference that contains the information in Regulation .04F of this chapter.</text>
        </paragraph>
        <paragraph num="(19)">
          <text>“Rightsizing” has the meaning stated in COMAR 20.50.09.02B.</text>
        </paragraph>
        <paragraph num="(20)">
          <text>“System constraints” means specific violations caused by physical characteristics of the electric distribution system exceeding electric company planning criteria, the result of which would threaten safe and reliable delivery of power.</text>
        </paragraph>
        <paragraph num="(21)">
          <text>“Stakeholder” means a person who is granted leave to intervene in an electric system plan proceeding pursuant to Public Utilities Article, §3-106, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(22)">
          <text>“Traditional wires solution” means a solution to address a system constraint that would be deferred or replaced by a non-wires solution.</text>
        </paragraph>
        <paragraph num="(23)">
          <text>“Virtual power plant (VPP)” has the meaning stated in Public Utilities Article, §7-216, Annotated Code of Maryland.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Electric System Planning Process.">
      <paragraph num="A.">
        <text>An electric system planning process shall align with the following components for each planning cycle and scenario and related requirements specified in this chapter:</text>
        <paragraph num="(1)">
          <text>Considerations feeding into types of projections;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Goals/ objectives;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>DER forecast;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Load forecast;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Hosting capacity assessment;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Grid needs and locational value assessment;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>Identify possible solutions to grid needs;</text>
        </paragraph>
        <paragraph num="(8)">
          <text>Screen and evaluate possible solutions;</text>
        </paragraph>
        <paragraph num="(9)">
          <text>Choose solutions and publish plan;</text>
        </paragraph>
        <paragraph num="(10)">
          <text>Program and project design; and</text>
        </paragraph>
        <paragraph num="(11)">
          <text>Assess results.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Considerations Feeding into Types of Projections.</text>
        <paragraph num="(1)">
          <text>Time Horizons for DER and Load Forecasting.</text>
          <paragraph num="(a)">
            <text>DER and load forecasting processes for electric companies other than electric cooperatives and municipal electric companies shall include at least three planning time horizons:</text>
            <paragraph num="(i)">
              <text>1 to 3 years;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>4 to 6 years; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>7 to 10  years.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>DER and load forecasting processes for electric cooperatives and municipal electric companies shall include at least two planning time horizons:</text>
            <paragraph num="(i)">
              <text>1 to 3 years; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>4 years up to 20 years.</text>
            </paragraph>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Level of Granularity. The granularity of information in an electric system plan may vary as described in other sections of this regulation.</text>
          <paragraph num="(a)">
            <text>As a near-term objective:</text>
            <paragraph num="(i)">
              <text>Information shall be provided in an Electric System Plan at the substation level; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Feeder-level information shall be provided as part of the planning process for feeders where there are identified system constraints;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>As a longer-term objective, electric companies shall report on progress regarding incorporating more granular electric system and customer information and data into forecasting and planning processes in their electric system plan or annual electric system plan update.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Scenarios/Projections to be Analyzed. An electric system plan shall include a minimum of two scenarios to provide a range of outcomes to inform planning analysis and the determination of the scale and pace of grid needs:</text>
          <paragraph num="(a)">
            <text>A baseline scenario; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A goal scenario.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>The Commission may request an electric company to analyze scenarios in addition to a baseline scenario and goal scenario.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>Data Sources, Scope, and Access. Electric companies shall provide for data collection and access that:</text>
          <paragraph num="(a)">
            <text>Allows stakeholders the opportunity to provide data inputs at pre-identified time periods defined by the electric company;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Provides collected data in a format that can be easily accessed by stakeholders; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Provides stakeholders transparency into data sources, data and assumptions used to develop electric system plans and annual electric system plan updates.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>Already-Approved Resource Retirements and Additions. Electric companies shall consider in their electric system plans whether distribution-level electric system planning can be used to mitigate potential gaps caused by generation retirements.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>PJM Wholesale Markets. Electric companies shall consider DERs and VPPs that participate in the PJM wholesale markets in electric distribution planning as applicable.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>Resource Costs and Capabilities. Electric companies contracting decisions to implement electric system plans and annual electric system plan updates shall be left to electric company discretion.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Goals/Objectives. An electric system plan shall promote applicable State policy goals pursuant to Public Utilities Article, §§7-801—7-804, et seq., Annotated Code of Maryland, and other applicable goals and targets as directed by the Commission.</text>
      </paragraph>
      <paragraph num="D.">
        <text>DER Forecast. An electric system plan shall account for the following considerations for each electric system planning cycle and scenario.</text>
        <paragraph num="(1)">
          <text>Electric companies shall develop separate forecasts for each relevant DER type, including energy efficiency, demand response, distributed generation, energy storage devices, VPPs and managed EV charging-discharging.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Electric Companies shall develop hourly DER forecasts.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Load Forecast. Load forecasts shall account for the following considerations for each planning cycle and scenario as follows:</text>
        <paragraph num="(1)">
          <text>Electric companies shall incorporate load impacts of current and future transportation and building electrification based on known information and assumptions; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Electric company distribution-level forecasts in aggregate shall be aligned to a reasonable extent with available electric company developed transmission-level forecasts and with PJM-developed system-level forecasts with an explanation provided in electric system plans for any differences and the associated factors, including differences in assumptions.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Hosting Capacity Assessment. An electric system plan shall account for the following considerations for each planning cycle and scenario.</text>
        <paragraph num="(1)">
          <text>Hosting capacity calculations shall be determined using a circuit-specific calculation including installed and forecasted DER interconnections.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>DER forecasting shall be incorporated into reserve hosting capacity determinations and the rightsizing of hosting capacity upgrades.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Electric companies shall establish methodologies for calculating available hosting capacity and, in the annual electric system plan update and electric system plan, discuss planned hosting capacity capability improvements.</text>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Grid Needs and Locational Value Assessment.</text>
        <paragraph num="(1)">
          <text>Grid Needs Assessment.</text>
          <paragraph num="(a)">
            <text>An electric company’s grid needs assessment shall include current and forecast distribution substation and feeder constraints identified as part of each planning cycle, including the timing, magnitude and other relevant characteristics for each identified system constraint.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The annual electric system plan update shall discuss changes to an electric company’s grid needs assessment that may occur between planning cycles.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Electric companies shall cost-effectively pursue industry best practice methods and analytical tools to improve their planning analysis and processes, the choice of which to adopt shall be at the discretion of the electric companies.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Locational Value Assessment.</text>
          <paragraph num="(a)">
            <text>An electric system plan shall provide locational value for each identified electric system constraint.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Locational value shall include the potential deferral or avoided value of a traditional wires solution.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Electric companies shall develop a locational value assessment using the Commission's uniform benefit cost analysis framework.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Electric companies shall report on the progress towards implementation of locational value assessments at annual technical conferences.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="H.">
        <text>Identify Possible Solutions to Grid Needs. An electric system plan shall account for the following considerations for each planning cycle and scenario:</text>
        <paragraph num="(1)">
          <text>Near-Term Objective.</text>
          <paragraph num="(a)">
            <text>An electric system plan shall identify solutions for identified grid needs.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Electric companies shall identify non-wires solutions considered to address system constraints.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>For any proposed upgrade projects resulting from Regulations .03H and .03I of this chapter, future hosting capacity constraints that incorporate DER forecasts shall be considered.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>As A Longer-Term Objective.</text>
          <paragraph num="(a)">
            <text>Electric companies shall assess the feasibility of utilizing new cost-effective technologies and methodologies for solutions to grid needs.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Electric companies shall report on the progress towards utilizing new cost-effective technologies and methodologies at annual technical conferences.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>Pursuant to Public Utilities Article, §7-804, Annotated Code of Maryland, electric companies shall consider investment in, or procurement of cost-effective demand-side methods and technology to improve reliability and efficiency, including VPPs.</text>
        </paragraph>
      </paragraph>
      <paragraph num="I.">
        <text>Screen and Evaluate Possible Solutions.</text>
        <paragraph num="(1)">
          <text>An electric company shall screen and evaluate possible solutions for each planning cycle and scenario.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The electric system plan shall include the criteria used to evaluate possible solutions, including cost-effectiveness considerations.</text>
          <paragraph num="(a)">
            <text>Electric companies shall evaluate cost-effectiveness for alternatives considered, if applicable.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Electric companies shall utilize the Commission's Unified Benefit Cost Analysis framework for solutions involving DERs in determining cost-effectiveness.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="J.">
        <text>Choose Solutions and Publish Plan. An electric company shall choose a solution or solutions for each scenario and publish a plan for each planning cycle as described in Regulation .04 of this chapter.</text>
        <paragraph num="(1)">
          <text>Electric companies shall present their rationale for solution selection in electric system plans, including why alternative solutions were not selected.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Information and data shall be provided in an electric system plan at the substation level.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>When project solutions are proposed in response to system constraints, electric companies shall provide feeder-level information, where applicable.</text>
        </paragraph>
      </paragraph>
      <paragraph num="K.">
        <text>Program and Project Design.</text>
        <paragraph num="(1)">
          <text>Program and project design including construction, procurement, and electric company contracting are factors in the electric companies’ mandate to provide safe and reliable service and a consideration in overall cost which shall be estimated in electric system plans.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Program and project design including construction, procurement, and electric company contracting decisions shall be left to electric company discretion in executing an electric system plan although these factors will remain subject to review in rate cases.</text>
        </paragraph>
      </paragraph>
      <paragraph num="L.">
        <text>Assess Results. An electric company shall account for the following considerations for each planning cycle:</text>
        <paragraph num="(1)">
          <text>An electric company shall assess the results of their electric system plans to determine lessons learned and changes to future planning assumptions.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Rate case filings shall provide explanations for projects that do not reconcile with electric system plans.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Electric System Plan, Annual Electric System Plan Update and Preliminary Electric System Plan: Development, Reporting, and Stakeholder Engagement Process.">
      <paragraph num="A.">
        <text>Electric System Plan Frequency.</text>
        <paragraph num="(1)">
          <text>Electric companies shall retain flexibility to determine the frequency of their respective electric system plan that best aligns with their internal planning cycles and considerations based upon their unique processes, system characteristics, and customer needs.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An electric company’s electric system plan publishing frequency shall be at least once every 3 years.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Electric companies shall publish a preliminary electric system plan and the electric system plan on the electric companies’ websites and file these plans with the Commission under the electric system plan docket assigned to each electric company.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>An electric company shall file an annual electric system plan update during the years in which a complete electric system plan is not filed.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>An electric company shall redact all confidential information from the electric system plan published to its website or otherwise submitted on a public basis, however, a full version of the electric system plan, including any confidential information, shall be filed with the Commission in accordance with the Commission’s rules for filing confidential material, unless otherwise restricted from doing so by applicable law.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Annual Electric System Plan Update.</text>
        <paragraph num="(1)">
          <text>Electric companies shall include the following annual electric system plan updates:</text>
          <paragraph num="(a)">
            <text>A narrative describing the existing planning and forecasting processes, current capabilities that exist, and plans for potential future improvements;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Relevant planning criteria utilized to identify system constraints;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Description of any new market or policy conditions that are impacting the planning environment and how they plan to incorporate them into future planning;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Description of any updates to system constraints or constraint solutions that may have changed from the previous year, including, but not limited to, updates on progress regarding projects and programs that have changed from the previous year and rationale for the change;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>A report using a common framework for electric company reporting as directed by the Commission, with information regarding the current status of projects designed to promote State policy goals identified in Public Utilities Article, §7-802, Annotated Code of Maryland, including information on planning processes and implementation that promote these goals; and</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Electric system plan targets and planning metrics pursuant to Regulation .05 of this chapter.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Electric companies shall file an annual electric system plan update no less than 75 days prior to the annual technical conference.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>In the year an electric company files a preliminary electric system plan, an annual electric system plan update is not required.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Data Collection: Electric companies shall identify a discrete opportunity to collect stakeholder inputs for consideration in the electric system plan.</text>
        <paragraph num="(1)">
          <text>The electric company shall provide an overview of the already-collected data including data sources.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Electric companies shall provide a method for collecting this data.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Electric companies shall provide a list of the parties they engaged as part of their published electric system plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Align Inputs and Assumptions. Electric companies shall develop electric system planning inputs and assumptions or develop forecasts, scenarios, or other electric system planning criteria and identify a discrete opportunity for stakeholders and other persons to provide feedback.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Run Analyses. Electric companies shall run analyses using data, planning inputs, and assumptions while considering stakeholder and other person feedback from §§C and D of this regulation and provide a preliminary electric system plan in years that an electric system plan is due.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Provide Preliminary Electric System Plan.</text>
        <paragraph num="(1)">
          <text>Electric companies shall include the following in their preliminary electric system plan:</text>
          <paragraph num="(a)">
            <text>Lessons learned and process improvements from the previous electric system plan cycle;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A narrative describing the existing electric system planning process, current capabilities, and plans for potential future changes including the methodology used to develop aggregate electric distribution-level net load forecasts;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Descriptions of electric system planning scenarios describing the data used as inputs and assumed adoption rates used for load and DER forecasting;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Summary of feedback received in §§C and D of this regulation;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Electric company response to feedback received in §§C and D of this regulation;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Any change in system constraints since the last electric system plan;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>The nature, magnitude, and timing of system constraints;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>System constraint solutions that have not yet been initiated as projects, including:</text>
            <paragraph num="(i)">
              <text>Projected timeline for solution implementation to address system constraints and policy targets over the forecast period; and</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>Implementation interdependencies with current and identified system constraint solutions and other electric company projects;</text>
            </paragraph>
          </paragraph>
          <paragraph num="(i)">
            <text>Cost-effectiveness analysis for identified system constraint solutions, if applicable;</text>
          </paragraph>
          <paragraph num="(j)">
            <text>A description of the final methodology, inputs, and results of the analyses;</text>
          </paragraph>
          <paragraph num="(k)">
            <text>Locational value for each identified system constraint; and</text>
          </paragraph>
          <paragraph num="(l)">
            <text>Electric system plan targets and planning metrics pursuant to Regulation .05 of this chapter.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>The preliminary electric system plan shall be published to align with the electric system plan frequency pursuant to §A of this regulation.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>An electric company shall publish on its website and file with the Commission its preliminary electric system plan no less than 75 days prior to the annual technical conference.</text>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Comments Filed By Parties.</text>
        <paragraph num="(1)">
          <text>Comments shall be filed by any stakeholders or other persons no less than 30 days prior to the annual technical conference.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Stakeholders and electric companies shall have the opportunity to obtain discovery.</text>
        </paragraph>
      </paragraph>
      <paragraph num="H.">
        <text>Annual Technical Conference. The annual technical conference shall provide a venue for stakeholders and other persons to comment on the assumptions, inputs, and results of the preliminary electric system plan and annual electric system plan update.</text>
      </paragraph>
      <paragraph num="I.">
        <text>Electric Companies’ Consideration of Feedback.</text>
        <paragraph num="(1)">
          <text>The Commission may provide an order noting the preliminary electric system plan after an annual technical conference which may include direction for the electric companies.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Electric companies shall evaluate any feedback received from the Commission in any order following the annual technical conference.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Electric companies shall evaluate feedback received from stakeholders in §§C, D, G, and H of this regulation.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Within 90 days of the annual technical conference, except as otherwise required by the Commission, electric companies shall publish on their website and file a response to stakeholder and other person  feedback with the Commission, including what stakeholder and other person  proposals will be considered or not considered in the development of the electric system plan and the reasoning for these decisions under the electric system plan docket assigned to each electric company.</text>
        </paragraph>
      </paragraph>
      <paragraph num="J.">
        <text>Electric System Plan Publishing. Electric companies shall publish a final electric system plan under the electric system plan docket assigned to each electric company after the consideration of feedback in Regulation .04I of this chapter.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Electric System Planning Metrics.">
      <paragraph num="A.">
        <text>An electric company shall include planning metrics listed in §C of this regulation in its preliminary electric system plan and other planning metrics as determined by the Commission.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An electric company shall include planning metrics listed in §C of this regulation in its annual electric system plan update and other planning metrics as determined by the Commission.</text>
      </paragraph>
      <paragraph num="C.">
        <text>An electric company shall include in its preliminary electric system plan, electric system plan, and annual electric system plan update a set of planning metrics that will allow monitoring of progress in at minimum the following plan areas:</text>
        <paragraph num="(1)">
          <text>State goals and targets;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Reliability;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Resilience;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>DER integration, by DER category;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Load and demand management;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Hosting capacity;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>System constraint resolution including:</text>
          <paragraph num="(a)">
            <text>Substation overload conditions defined as overload conditions identified on substations that require remediation; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Feeder overload conditions defined as overload conditions identified on substations that require remediation;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(8)">
          <text>NWS incorporation; and</text>
        </paragraph>
        <paragraph num="(9)">
          <text>Stakeholder and other person engagement.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Legislative Reporting Requirements.">
      <paragraph num="A.">
        <text>Annual Maryland General Assembly Report.</text>
        <paragraph num="(1)">
          <text>On or before November 1 annually, each electric company shall file material updates to project status reported pursuant to Regulation .04B(1)(e) of this chapter.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>On or before December 1 annually, the Commission’s Technical Staff shall submit a report to the Maryland General Assembly regarding the current status of projects designed to promote the State’s policy goals identified in Public Utilities Article, §7-802, Annotated Code of Maryland, including information on planning processes and implementation that promote these goals.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§1-101, 2-113, 2-121, 7-216, and 7-801—7-804, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: November 24, 2025 (52:23 Md. R. 1140)</annotation>
    </annotations>
  </chapter>
  <chapter num="14" heading="Energy Storage">
    <regulation prefix="Regulation" num=".01" heading="Applicability.">
      <paragraph num="A.">
        <text>This chapter applies to the following:</text>
        <paragraph num="(1)">
          <text>All front-of-the meter energy storage devices in Maryland pursuant to Public Utilities Article, §7–219, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Any energy storage devices eligible to be enrolled or registered in the Maryland Energy Storage Program pursuant to Public Utilities Article, §7-216.1, Annotated Code of Maryland.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Electric vehicles that are part of a renewable on-site generating system and mobile energy storage devices are ineligible for registration in the Maryland Energy Storage Program pursuant to Public Utilities Article, §7-1005(E)(2)(II)(1), Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="C.">
        <text>A virtual power plant or microgrid is ineligible for registration in the Maryland Energy Storage Program as a stand-alone energy storage device.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Any energy storage device that constitutes part of a virtual power plant, microgrid, or a renewable on-site generating system, except as specified in Regulation .01B of this chapter, is eligible to register in the Maryland Energy Storage Program or enroll in Administrator Initiatives.</text>
      </paragraph>
      <paragraph num="E.">
        <text>Electric company owned energy storage devices used for substation control, support, and emergency back-up of utility equipment and facilities are exempt from the requirements of this chapter.</text>
      </paragraph>
      <paragraph num="F.">
        <text>An energy storage device as defined in Public Utilities Article, §7-216, Annotated Code of Maryland that off-sets grid demand, but does not deliver energy to the grid, shall not be subject to the requirements of in Regulation .03 of this chapter, except for §G of this regulation and other conditions as determined by the Commission for inclusion in a Maryland Energy Storage Program Initiative.</text>
        <paragraph num="(1)">
          <text>The applicant shall make a filing with the Commission regarding the technical details of its proposed energy storage device and the applicant’s rationale for inclusion in a Maryland Energy Storage Program Initiative.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The Commission shall determine the next steps necessary to consider the matter as a special case in the Maryland Energy Storage Program.</text>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Applicable Standards. Unless otherwise specified by the Commission, an energy storage device shall, to the extent applicable, comply with the provisions in the National Fire Protection Association (NFPA) 855 Standard for the Installation of Stationary Energy Storage Systems, 2023 Edition, which is incorporated by reference in Regulation .03 of this chapter.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Definitions.">
      <paragraph num="A.">
        <text>Terms Defined.</text>
        <paragraph num="(1)">
          <text>“Administrator” means an approved electric company, state agency, or Commission approved entity responsible for the enrollment in and general administration of an initiative under the Maryland Energy Storage Program.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>“Affected community” means the residential individuals, organizations, and other entities located within 1 mile of the proposed location of an energy storage device.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>“Applicant” means an energy storage device owner that submits an application to an administrator to enroll in an initiative in the Maryland Energy Storage Program or to construct a front-of-the-meter energy storage device.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>“Behind-the-meter energy storage device” means an energy storage device that is installed on the customer side of an electric company meter and serves a particular electric company customer electric load.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>“Construction” has the meaning stated in Public Utilities Article, §7-207(a)(3), Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>“Cost-effective” means having projected benefits that are greater than projected costs while considering other factors as determined by the Commission.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>“Delivery year” has the meaning stated in Public Utilities Article, §7-216.1, Annotated Code of Maryland and is a planning period consisting of the 12 months beginning June 1 and extending through May 31 of the following year.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>“Deployment incentive mechanism” means an incentive or rebate provided by an administrator to accelerate the deployment of cost-effective energy storage devices providing grid services as part of the Maryland Energy Storage Program and is not a payment for performance or specific operations.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>“Distributed energy resource” has the meaning stated in COMAR 20.50.09.02.</text>
        </paragraph>
        <paragraph num="(10)">
          <text>“Electric company” has the meaning stated in Public Utilities Article, §1-101, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(11)">
          <text>“Energy storage device” has the meaning stated in Public Utilities Article, §7-216, Annotated Code of Maryland and may be classified by market segment for the purposes of registration in the Maryland Energy Storage Program or enrollment in Administrator Initiatives.</text>
        </paragraph>
        <paragraph num="(12)">
          <text>“Enrollment” means the acceptance by an administrator of an application of an energy storage device in an initiative for a delivery year and occurs in parallel with the PJM Interconnection LLC or the electric company’s interconnection process.</text>
        </paragraph>
        <paragraph num="(13)">
          <text>“Front-of-the-meter energy storage device” means an energy storage device where there is no load on the customer side of the meter beyond loads required to operate the energy storage device and includes:</text>
          <paragraph num="(a)">
            <text>A separate electrical isolation device to prevent the flow of electricity when required for operation or maintenance;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A separate energy measurement meter;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>At least one inverter; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The ability to be operated in an independent manner from other energy storage devices.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(14)">
          <text>“Generating station” has the meaning stated in COMAR 20.79.01.02.</text>
        </paragraph>
        <paragraph num="(15)">
          <text>“Grid services” means the dispatch and control of an energy storage device to provide service to the electric company’s electric grid pursuant to an electric company tariff, service contract between the electric company and the owner of a registered energy storage device, or providing transmission-level grid services by participating in PJM Interconnection LLC wholesale markets.</text>
        </paragraph>
        <paragraph num="(16)">
          <text>“Grid services mechanism” means “pay-for-performance” compensation from an electric company to owners of energy storage devices registered in the Maryland Energy Storage Program that provide grid services to the electric system.</text>
        </paragraph>
        <paragraph num="(17)">
          <text>“Initiative” means an administrator’s Commission-approved structure in which energy storage devices can enroll that offers a mechanism targeted at a specific market segment.</text>
        </paragraph>
        <paragraph num="(18)">
          <text>“Long-duration energy storage system (LDES)” means an energy storage device capable of continuously discharging electricity at its full rated capacity for 10 hours or longer but less than 24 hours.</text>
        </paragraph>
        <paragraph num="(19)">
          <text>“Market segment” means the categorization of energy storage devices in the Maryland Energy Storage Program as front-of-the-meter electric transmission, front-of-the meter electric distribution, or behind-the-meter electric distribution.</text>
        </paragraph>
        <paragraph num="(20)">
          <text>“Maryland energy storage program” means the initiatives and registrations that the Commission established to meet State energy storage targets pursuant to Public Utilities Article, §7-216.1, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(21)">
          <text>“Mechanism” means a procurement mechanism, a grid services mechanism, or a deployment incentive mechanism and may be implemented as a tariff, grant, rebate, or a contract.</text>
        </paragraph>
        <paragraph num="(22)">
          <text>“Microgrid” means a network that can consist of interconnected loads, distributed energy resources, and energy storage devices within clearly defined electrical boundaries that acts as a single controllable network with respect to the electric system and that can be disconnected from the electric distribution or transmission system to operate independently.</text>
        </paragraph>
        <paragraph num="(23)">
          <text>“Multi-day energy storage (Multi-day ES)” means an energy storage device capable of continuously discharging electricity at its full rated capacity for 24 hours or longer.</text>
        </paragraph>
        <paragraph num="(24)">
          <text>“Notice to affected community” means by advertisement in a newspaper of general circulation in the county or municipal corporation affected by the application and on two types of social media platforms.</text>
        </paragraph>
        <paragraph num="(25)">
          <text>“Overburdened community” has the same meaning as defined in Environment Article, §1–701, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(26)">
          <text>“Ownership and operations model” means the role that third-parties and electric companies play in owning and operating energy storage devices and may include, but are not limited to:</text>
          <paragraph num="(a)">
            <text>A third-party ownership and operations model;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An electric company ownership and operations model;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>An electric company owned and third party-operated model;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>A third-party owned and electric company operated model; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>An electric company ownership and leaseback model.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(27)">
          <text>“Parcel” means a lot or group of lots devoted to a particular use including open spaces required or used in connection with that particular use.</text>
        </paragraph>
        <paragraph num="(28)">
          <text>“Pre-existing energy storage device” means an energy storage device that is in-service or under construction prior to the effective date of this chapter.</text>
        </paragraph>
        <paragraph num="(29)">
          <text>“Procurement mechanism” means a competitive solicitation by an administrator for energy storage devices providing grid services or a contract established by an administrator for grid services from energy storage devices.</text>
        </paragraph>
        <paragraph num="(30)">
          <text>“Registrant” means the person that obtains registration of an energy storage device in the Maryland Energy Storage Program.</text>
        </paragraph>
        <paragraph num="(31)">
          <text>“Registration” means the counting of an energy storage device in the Maryland Energy Storage Program energy storage device targets stated in Public Utilities Article, §7-216.1, Annotated Code of Maryland as of the date it is in-service.</text>
        </paragraph>
        <paragraph num="(32)">
          <text>“Renewable on-site generating system” has the meaning stated in Public Utilities Article, §7-1001(i), Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(33)">
          <text>“Short-duration energy storage (SDES)” means an energy storage device capable of continuously discharging electricity at its full rated capacity for less than 10 hours.</text>
        </paragraph>
        <paragraph num="(34)">
          <text>“Technology type” means all types of electric storage device technologies, regardless of their size, storage medium, or operational purpose as classified in Public Utilities Article, §7-216, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(35)">
          <text>“Unclassified technology type” means a technology that is not stated in Public Utilities Article, §7-216, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(36)">
          <text>“Underserved community” has the same meaning as defined in Environment Article, §1–701, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(37)">
          <text>“Virtual power plant” means a collection of distributed energy resources, potentially including energy storage devices, that can provide grid services when aggregated together and coordinated with grid operations.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Incorporation by Reference.">
      <text>In this chapter, NFPA 855, Standard for the Installation of Stationary Energy Storage Systems, 2023 is incorporated by reference.</text>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Maryland Energy Storage Program Administration.">
      <paragraph num="A.">
        <text>Targets.</text>
        <paragraph num="(1)">
          <text>Targets for the cost-effective deployment of new energy storage devices may be established by the Commission in a manner as determined by the Commission or the legislature.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The Commission may assign an administrator individual targets in a manner as determined by the Commission to help meet state energy storage targets pursuant to Public Utilities Article, §7-216.1, Annotated Code of Maryland and to support state policy goals in Public Utilities Article, §§7–801 and 7–802, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>An administrator shall propose to the Commission achievable goals for the enrollment of cost-effective energy storage devices in its initiatives in a manner as determined by the Commission.</text>
          <paragraph num="(a)">
            <text>Targets may be proposed for front-of-the-meter and behind-the-meter energy storage device initiative installations.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Targets may be proposed for energy storage device initiative installations on the electric distribution system and the electric transmission system.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Targets may be proposed for energy storage device deployment using different ownership and operating models.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Targets may consider energy storage device characteristics including but not limited to attributes such as SDES, LDES, and Multi-day ES durations.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Targets may be proposed by electric companies for performance incentive mechanisms for goal achievement and the establishment of retail tariffs to support the Maryland Energy Storage Program.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>An administrator shall meet its assigned targets in a cost-effective manner.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>If an administrator determines at any time that it cannot meet its assigned targets cost-effectively, the administrator shall make a filing with the Commission seeking to reduce the targets, pursuant to Public Utilities Article, §7-216.1, Annotated Code of Maryland or propose an alternative.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Counting for Enrollment and Registration.</text>
        <paragraph num="(1)">
          <text>Administrators shall develop applications to enroll energy storage devices in an initiative.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An energy storage device is enrolled in an initiative on the date the administrator sends notification of enrollment to the applicant.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>An administrator shall use information regarding energy storage device enrollments to determine the amount of energy storage devices required to meet end of delivery year targets.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The Maryland Energy Storage Program Manager shall use information regarding registered energy storage devices to determine if end of delivery year targets were met.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>A pre-existing energy storage device shall be registered in the Maryland Energy Storage Program on the date it is discovered and cannot be enrolled in an initiative offering a deployment incentive mechanism or a procurement mechanism.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>To enroll in an initiative offering a procurement mechanism or a deployment mechanism, an energy storage device shall provide grid services.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>An administrator shall not double count an energy storage device participating in two mechanisms for reporting purposes pursuant to Regulation .13 of this chapter.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>An energy storage device shall not be enrolled in an initiative offering a deployment incentive mechanism and a procurement mechanism at the same time.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>An energy storage device may enroll in an electric company initiative offering a grid services mechanism and be registered in the Maryland Energy Storage Program and counted towards the targets stated in the Public Utilities Article, §7-216.1, Annotated Code of Maryland without enrolling in an initiative offering a procurement mechanism or deployment incentive mechanism.</text>
        </paragraph>
        <paragraph num="(10)">
          <text>An energy storage device that is eligible for a deployment incentive mechanism shall receive a deployment incentive from the administrator only after the energy storage device is registered in the Maryland Energy Storage Program.</text>
        </paragraph>
        <paragraph num="(11)">
          <text>An electric company shall not enroll an electric-company-owned energy storage device in an initiative in which it is the administrator unless approved by the Commission.</text>
        </paragraph>
        <paragraph num="(12)">
          <text>An electric company may enroll an electric company-owned energy storage device in an initiative in which it is not an administrator.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Grid Services.</text>
        <paragraph num="(1)">
          <text>Each electric company shall implement necessary retail tariffs or service contracts for energy storage devices to provide grid services and to support initiative targets assigned by the Commission.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Retail tariffs that include grid services shall also recognize the unique role that energy storage plays in reducing peak demand in the development of demand charges.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Energy storage devices providing transmission-level grid services under PJM Interconnection LLC tariffs shall be counted toward achieving the Maryland Energy Storage Program targets set forth in Public Utilities Article, §7-216.1, Annotated Code of Maryland.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Pre-Existing Energy Storage Devices.</text>
        <paragraph num="(1)">
          <text>Pre-existing energy storage devices are not eligible to participate in an initiative offering a deployment incentive mechanism or a procurement mechanism.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Pre-existing energy storage devices are eligible to participate in a grid services mechanism.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Pre-existing energy storage devices participating in a grid services mechanism shall be registered in the Maryland Energy Storage Program as a pre-existing energy storage device.</text>
        </paragraph>
      </paragraph>
      <paragraph num="E.">
        <text>Administration.</text>
        <paragraph num="(1)">
          <text>An administrator shall be approved by the Commission in a manner as determined by the Commission.</text>
          <paragraph num="(a)">
            <text>An electric company may provide administration for an initiative it creates or contract with a third party to provide administration on its behalf.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A State agency may provide administration for an initiative it creates or contract with a third party to provide administration on its behalf.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>The Commission shall assign a Commission person, whether internal or contracted, to serve as the Maryland Energy Storage Program Manager to:</text>
          <paragraph num="(a)">
            <text>Coordinate with administrators on federal and State funding requests;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Manage and report on the status of meeting energy storage targets stated in the Public Utilities Article, §7-216.1, Annotated Code of Maryland;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Coordinate and develop initiative target allocation recommendations; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Advise the Commission on the plans of their initiatives.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>An administrator shall post information on applying for an initiative on an administrator’s website and through other standard promotional methods, as appropriate, and all promotional efforts shall include information to enable prospective owners of eligible energy storage devices to apply for initiatives.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>An electric company may identify desired locations for energy storage devices on its website and update this information at least annually.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>An administrator shall issue a notice to an energy storage device applicant following its approval or denial for enrollment in its initiative.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>An administrator shall make reasonable efforts to apply for all applicable State and federal grants, rebates, tax credits, loan guarantees, and other similar benefits as the benefits become available to help offset the cost of its initiative.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>An administrator shall also update initiative data as required in Regulation .13 of this chapter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>Complaints. Any person may file a complaint with the Commission’s Executive Secretary regarding fairness, transparency, conflicts of interest, and timely resolutions, among other things.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Electric Company Owned Front-Of-The Meter Energy Storage Device Enrollment and Registration in the Maryland Energy Storage Program.">
      <paragraph num="A.">
        <text>All energy storage devices owned by an electric company that inject power into the electric system shall be considered registered in the Maryland Energy Storage Program at the in-service date as reported to the Maryland Energy Storage Program Manager by the electric company. Electric company-owned pre-existing energy storage devices are registered as provided in Regulation .04(B) of this chapter.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Prior to the commencement of the stakeholder engagement and participation requirements pursuant to Regulation .09 of this chapter, the electric company shall file a notification with the Commission containing information about the energy storage device. The date of this notification shall be the energy storage device enrollment date provided that the energy storage device is enrolled in an initiative.</text>
      </paragraph>
      <paragraph num="C.">
        <text>An electric company-owned energy storage device shall be subject to the stakeholder engagement and participation requirements for front-of-the-meter energy storage device applicants in Regulation .09 of this chapter and shall also be subject to the safety, siting, and environmental requirements for front-of-the-meter energy storage devices in Regulation .10 of this chapter, except to the extent exempted under Regulation .08G of this chapter, and the Department of Natural Resources Power Plant Research Program review and recommendations in Regulation .11 of this chapter, except to the extent exempted under Regulation .08G of this chapter.</text>
      </paragraph>
      <paragraph num="D.">
        <text>An electric company-owned energy storage device shall be subject to Commission approvals in Regulation .12 of this chapter, except to the extent exempted under Regulation .08G of this chapter.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".06" heading="Behind-The-Meter Energy Storage Device Enrollment and Registration in the Maryland Energy Storage Program.">
      <paragraph num="A.">
        <text>All applicants seeking to enroll an energy storage device in an initiative offering a behind-the-meter mechanism shall submit an application to an administrator prior to the beginning of construction, except for pre-existing energy storage devices seeking to enroll in a grid services mechanism, which may submit an application before or after construction.</text>
      </paragraph>
      <paragraph num="B.">
        <text>An application seeking to enroll in a behind-the-meter mechanism shall include an attestation by the applicant that:</text>
        <paragraph num="(1)">
          <text>The energy storage device shall meet the definition of an “energy storage device” in the Public Utilities Article, §7-216, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>At the time of enrollment, the energy storage device’s planned electrical capacity in kilowatts and energy in kilowatt-hours that can be delivered to the grid or offset grid demand.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The energy storage device shall meet NFPA 855 standards, if applicable, in addition to any other applicable federal and State requirements and local codes and standards.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The energy storage device applicant shall meet a specified in-service date.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>An administrator shall deny any application for enrollment in a mechanism if the conditions in §B of this regulation, as applicable, are not met and shall provide the applicant an explanation for denial to aid the applicant in curing and resubmitting the application.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The enrollment date shall be the date the administrator notifies the applicant that its application is approved.</text>
      </paragraph>
      <paragraph num="E.">
        <text>The date of registration in the Maryland Energy Storage Program is the in-service date, as noted in a certificate of completion to be tendered by the Program Administrator. Pre-existing energy storage devices are registered as required in Regulation .04(B) of this chapter.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Should an applicant not meet the expected in-service date within 60 days of the certificate of completion, an administrator shall provide notification to an applicant that its enrollment will be withdrawn unless a request for extension is submitted to the administrator within 30 days and a notice is submitted to the electric company with a new projected in-service date.</text>
        <paragraph num="(1)">
          <text>An administrator may approve an extension request for good cause or otherwise deny the request if good cause is not provided.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An applicant may appeal to the Commission an administrator’s decision regarding an extension by filing an appeal with the Commission's Executive Secretary.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".07" heading="Non-Electric Company Owned Front-Of-The-Meter Energy Storage Device Enrollment and Registration in the Maryland Energy Storage Program.">
      <paragraph num="A.">
        <text>All energy storage devices that are not owned by an electric company seeking to enroll in a procurement mechanism or deployment incentive mechanism shall submit an application form with an administrator prior to beginning construction.</text>
      </paragraph>
      <paragraph num="B.">
        <text>All non-electric company front-of-the meter energy storage device applications to enroll in a deployment incentive mechanism or procurement mechanism shall include an attestation that:</text>
        <paragraph num="(1)">
          <text>The energy storage device meets the definition of an “energy storage device” in the Public Utilities Article, §7-216, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The energy storage device is not a pre-existing energy storage device.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>At the time of enrollment, the energy storage device’s planned electrical capacity in kilowatts and energy in kilowatt-hours that can be delivered to the grid.</text>
          <paragraph num="(a)">
            <text>If an energy storage device does not have capacity ratings in kilowatts and energy ratings in kilowatt-hours supplied by a manufacturer, the applicant shall provide these ratings in kilowatts and kilowatt-hours in a document describing the calculation methodology and showing the rating calculations.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>These capacity and energy rating calculations shall be certified by a professional engineer licensed in Maryland.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>The applicant shall make reasonable efforts to meet a specific in-service date.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>The energy storage device shall have a position in either the PJM new services queue or have filed an interconnection request with the electric company.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>An administrator shall deny any application for enrollment if the conditions in §B of this regulation, as applicable, are not met and shall provide the applicant an explanation for the denial to aid the applicant in curing and resubmitting the application.</text>
      </paragraph>
      <paragraph num="D.">
        <text>An administrator shall make a proposal when seeking Commission approval of an initiative for project maturity requirements to avoid speculative projects entering into enrollment.</text>
      </paragraph>
      <paragraph num="E.">
        <text>The registration date is the in-service date stated on a certificate of completion tendered by the administrator.</text>
      </paragraph>
      <paragraph num="F.">
        <text>Should an applicant for a deployment incentive mechanism initiative not meet the expected in-service date within 60 days of the certificate of completion, an administrator shall provide notification to an applicant that its enrollment will be withdrawn unless a request for extension is submitted to the administrator.</text>
        <paragraph num="(1)">
          <text>An administrator may approve an extension request for good cause or otherwise deny the request if good cause is not provided.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An applicant may appeal an administrator’s decision regarding an extension to the Commission by filing an appeal with the Commission's Executive Secretary.</text>
        </paragraph>
      </paragraph>
      <paragraph num="G.">
        <text>Should an applicant for a procurement mechanism initiative or a grid services mechanism initiative fail to meet the expected in-service date the terms and conditions of the executed contract apply.</text>
      </paragraph>
      <paragraph num="H.">
        <text>Non-electric company-owned front-of-the meter energy storage devices enrolling in an initiative shall be subject to the stakeholder engagement and participation requirements for all front-of-the-meter energy storage devices in Regulation .09 of this chapter and shall be subject to the safety, siting, and environmental requirements for front-of-the-meter energy storage devices in Regulation .10 of this chapter and the Department of Natural Resources Power Plant Research Program review and recommendations in Regulation .11 of this chapter, except to the extent exempted under Regulation .08G of this chapter.</text>
      </paragraph>
      <paragraph num="I.">
        <text>Non-electric company owned front-of-the meter energy storage devices shall be subject to Commission approvals in Regulation .12 of this chapter, except to the extent exempted under Regulation .08G of this chapter.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".08" heading="Exemptions and Waivers from Regulations for Front-Of-The-Meter Energy Storage Devices.">
      <paragraph num="A.">
        <text>A front-of-the-meter energy storage device applicant or registrant or an electric utility proposing a front-of-the-meter energy storage device may request from the Commission, a waiver or to be exempted from a requirement of this chapter that is not applicable to its energy storage device.</text>
      </paragraph>
      <paragraph num="B.">
        <text>All waiver requests shall state whether the energy storage device is currently:</text>
        <paragraph num="(1)">
          <text>Operational, including the in-service date;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Under construction, including the projected in-service date; or</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Proposed, including the expected construction start date and projected in-service date.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>All waiver requests shall describe the energy storage device’s technical and operational characteristics and explain why those characteristics, or other factors, make a requirement of the regulation inapplicable or would result in undue hardship.</text>
      </paragraph>
      <paragraph num="D.">
        <text>All waiver requests shall be served on the electric company with jurisdiction over the electric system to which the energy storage device seeks to enroll or register in an initiative or submits an application for Commission Energy Storage Construction Approvals and Waivers for energy storage devices not seeking to enroll in an initiative.</text>
      </paragraph>
      <paragraph num="E.">
        <text>For waiver requests for front-of-the-meter energy storage devices equal to or greater than 20 megawatt-hours per parcel, the waiver request shall be subject to state agency review pursuant to Regulation .11C of this chapter.</text>
      </paragraph>
      <paragraph num="F.">
        <text>For waiver requests for front-of-the-meter energy storage devices under 20 megawatt-hours per parcel, the Commission shall either approve, approve with modifications, or deny the waiver request after notice and an opportunity for public comment. The Commission may set a date for consideration of the waiver request at a hearing in the Commission’s Administrative Docket.</text>
      </paragraph>
      <paragraph num="G.">
        <text>An energy storage device that is approved in a Certificate of Public Convenience and Necessity (CPCN) proceeding conducted pursuant to Public Utilities Article, §7-207, Annotated Code of Maryland shall be enrolled by an administrator in the Maryland Energy Storage Program upon Commission approval of the CPCN and shall be registered by the Maryland Energy Storage Program Manager upon being placed in-service. The energy storage device is otherwise exempt from the engagement, safety, environmental, and siting regulations in Regulations .09, .10, .11 and .12 of this chapter that are replicated in the CPCN review process.</text>
      </paragraph>
      <paragraph num="H.">
        <text>A waiver request may cover multiple energy storage devices provided that all applicable sections of this regulation are followed.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".09" heading="Stakeholder Engagement and Participation Requirements for Front-Of-The-Meter Energy Storage Devices.">
      <paragraph num="A.">
        <text>General Stakeholder Engagement and Participation Requirements Under Public Utilities Article, §7-219(c) and (d), Annotated Code of Maryland.</text>
        <paragraph num="(1)">
          <text>The applicant or electric company, for a utility-owned energy storage device, shall provide immediate notice to affected communities on submission of an application for approval of the construction of a front-of-the-meter energy storage device to:</text>
          <paragraph num="(a)">
            <text>The governing body of each county or municipal corporation in which any portion of the energy storage device is to be constructed;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>The governing body of each county or municipal corporation within 1 mile of the proposed location of the energy storage device;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Each member of the General Assembly representing any part of a county in which any portion of the energy storage device is proposed to be constructed;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Each member of the General Assembly representing any part of a county within 1 mile of the proposed location of the energy storage device; and</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The affected communities that are within 1 mile of the proposed location of the energy storage device.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>The applicant or electric company, for a utility-owned energy storage device, shall:</text>
          <paragraph num="(a)">
            <text>Hold at least two public meetings in the affected community if the proposed location of the front-of-the-meter energy storage device is in an area considered to be an overburdened community or underserved community.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Be exempt from meeting the requirements of §A(2)(a) of this regulation if an owner of a proposed front-of-the-meter energy storage device is located within the boundaries of an existing electricity generating station.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Stakeholder Engagement and Participation for Proposed Energy Storage Devices with 20 Megawatt-Hours or Greater Energy Storage Device Capacity Total Sited Per Parcel.</text>
        <paragraph num="(1)">
          <text>This section applies to an applicant or electric company, for a utility-owned energy storage device, with proposed energy storage devices greater than or equal to 20 megawatt-hours storage capacity total sited per parcel regardless of energy storage device technology.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A minimum of 90 days prior to submitting an application for enrolling in an initiative or prior to filing for a zoning variance or permits, whichever is earlier, an applicant or electric company, for a utility-owned energy storage device, shall take the following steps to engage and consult with the county or municipal corporation in which any portion of the energy storage device is proposed to be located.</text>
          <paragraph num="(a)">
            <text>Submit to the affected county or municipal corporation and each owner of land on which the energy storage device is located and owner of adjacent land, a conceptual site plan for the energy storage device.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Submit to the affected county or municipal corporation a request for a meeting. The applicant shall make a good faith effort to meet with the staff of the affected county or municipal corporation.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Submit to the affected county or municipal corporation a request for a preliminary report containing the following:</text>
            <paragraph num="(i)">
              <text>A statement or finding whether the proposed energy storage device is consistent with the current comprehensive plan of the county or municipal corporation;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>A statement or finding whether the proposed energy storage device is consistent with the current zoning ordinance of the county or municipal corporation; and</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Suggestions for improving or modifying the application prior to submission of the application to the initiative administrator.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(d)">
            <text>If the applicant or electric company, for a utility-owned energy storage device, makes any material changes to the energy storage device as submitted to the administrator under this regulation, the applicant shall provide notice of the changes to the county or municipal corporation in which any portion of the energy storage device is proposed to be located.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>The applicant shall submit to the Department of Natural Resources Power Plant Research Program any report or other information received on their energy storage device from the county or municipal corporation in which any portion of the energy storage device is proposed to be located before filing an application for enrollment in an initiative or submits an application for Commission Energy Storage Construction Approvals and Waivers for energy storage devices not seeking to enroll in an initiative.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>The applicant or electric company, for a utility-owned energy storage device, shall, a minimum of 60 days prior to filing an application for enrollment, submitting an application for Commission Energy Storage Construction Approvals and Waivers for energy storage devices not seeking to enroll in an initiative, or prior to filing for a zoning variance or permits, whichever is earlier, meet with affected communities for the purposes of public engagement and participation. The applicant or electric company, for a utility-owned energy storage device, shall provide 14 days’ notice to affected communities and:</text>
          <paragraph num="(a)">
            <text>If the proposed location of the front-of-the-meter energy storage device is in an area considered to be an overburdened community or underserved community, the applicant or electric company, for a utility-owned energy storage device, shall hold at least two public meetings in the affected community; and</text>
          </paragraph>
          <paragraph num="(b)">
            <text>An owner of a proposed front-of-the-meter energy storage device that is located within the boundaries of an existing electricity generating station shall be exempt from meeting the requirements of §B(3)(a) of this regulation.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>The applicant or electric company, for a utility-owned energy storage device, shall submit to the Commission any report received on their energy storage device from the affected communities in which any portion of the energy storage device is proposed to be located including the following information:</text>
          <paragraph num="(a)">
            <text>A description of the time, place, and manner in which the applicant held the public meeting with members of the affected communities;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>A description of the manner in which the applicant provided notice to the affected communities of the proposed public meeting with members of the affected communities;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>A copy of any meeting sign-in sheet voluntarily indicating persons of interest; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>A description of any terms, incentives, or resolutions reached between the applicant and the affected communities.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(5)">
          <text>Affected communities including residential individuals, organizations, affected county or municipal corporations may also file information with the Commission on their position supporting, opposing, or requesting modifications to a front-of-the-meter energy storage device.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>The applicant or electric company, for a utility-owned energy storage device, may respond within 30 days of the Commission’s receipt of such information from affected communities, residential individuals, organizations, affected counties or municipal corporations.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".10" heading="Safety, Siting, and Environmental Requirements for Front-Of-The-Meter Energy Storage Devices.">
      <paragraph num="A.">
        <text>Applicability.  This regulation applies to all front-of-the meter energy storage devices unless exempted pursuant to Regulation .08 of this chapter.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Minimum Safety, Siting, and Environmental Requirements.</text>
        <paragraph num="(1)">
          <text>An energy storage device that will not be constructed at an electricity generating station, electric substation, or commercial or industrial location shall meet the site requirements of Public Utilities Article, §7-219(e), Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An energy storage device shall adhere to the design, construction, operation, and maintenance standards in NFPA 855, if applicable, which is incorporated by reference in this chapter. The scope of NFPA 855 applies only to the technologies and energy storage devices of certain size thresholds whether owned and operated by an applicant or registrant.</text>
          <paragraph num="(a)">
            <text>The applicant or registrant shall include an attestation from a professional engineer licensed in Maryland that its proposed energy storage device shall comply with the standards in NFPA 855, if applicable.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If an applicant or registrant states that NFPA 855 is not applicable to the energy storage device technology utilized, the applicant or registrant shall include an attestation that the energy storage device shall be designed, constructed, installed, operated, and maintained in accordance with any applicable standards, regulations, and codes, in addition to complying with all state and local building, fire, and zoning requirements, and shall include a copy of the applicable standards, regulations, and codes with its application.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>In cases where the adherence with NFPA 855 or other applicable standards, regulations, and codes are not applicable, the applicant or registrant may seek a waiver pursuant to Regulation .08 of this chapter.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(3)">
          <text>An energy storage device shall have hazard mitigation and firefighting preparedness plans that include hazard mitigation, firefighting water needs, and fire tests.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>An energy storage device shall have emergency preparedness plans and procedures including pre-incident plans, emergency procedures, periodic safety inspections, first responder response, and training.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>An energy storage device shall comply with all applicable codes and standards.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".11" heading="Department of Natural Resources Power Plant Research Program Review on Behalf of the State Agencies for Front-Of-The-Meter Energy Storage Devices.">
      <paragraph num="A.">
        <text>State Agency Application Review Coordinated by the Power Plant Research Program.</text>
        <paragraph num="(1)">
          <text>An applicant with proposed energy storage devices 20 megawatt-hours storage capacity or greater total sited per parcel, regardless of energy storage device technology, shall no later than 45 days prior to filing an application for enrollment in an initiative, submitting an application for Commission Energy Storage Construction Approvals and Waivers for energy storage devices not seeking to enroll in an initiative, or prior to filing for a zoning variance or permits, whichever is earlier, consult with the staff of the Department of Natural Resources Power Plant Research Program to provide an overview of the proposed energy storage device.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The Department of Natural Resources Power Plant Research Program review shall include the minimum safety, siting, and environmental requirements in Regulation .10 of this chapter.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Other potential factors for which the Department of Natural Resources Power Plant Research Program may request information include the following.</text>
          <paragraph num="(a)">
            <text>Environmental information required under COMAR 20.79.03.02.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Natural Resources information required under COMAR 20.79.03.03.</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Socioeconomic information required under COMAR 20.79.03.04.</text>
          </paragraph>
          <paragraph num="(d)">
            <text>EJSCREEN Reports pursuant to COMAR 20.79.03.05.</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Plans for compliance which are subject to COMAR 26.02.03.02 noise assessment regulations.</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Plans for compliance with all state and local building, fire, and zoning requirements.</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Information on grid reliability impacts.</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Decommissioning plans, if applicable, to ensure there is an appropriate financial surety instrument to cover the projected cost of decommissioning less projected salvage value at the end of projected project life. Electric companies are exempt from decommissioning requirements.</text>
          </paragraph>
          <paragraph num="(i)">
            <text>Any additional information required by the Department of Natural Resources Power Plant Research Program for state agency review which shall not be unreasonably denied.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>State Agency Application Recommendations.</text>
        <paragraph num="(1)">
          <text>The State agencies shall consider in its recommendation to the Commission, the information received from the applicant regarding stakeholder engagement and participation of counties, municipal corporations, or an affected community. The Department of Natural Resources Power Plant Research Program shall upon request, provide the Maryland Office of People’s Counsel the information it collected from the applicant.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>An energy storage device owner may respond within 30 days of the Commission’s receipt of such information from the State agencies.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The State agencies shall file with the Commission within 4 months of receipt of all required information, a recommendation on whether the energy storage device enrollment in the Maryland Energy Storage Program or an application for Commission Energy Storage Construction Approvals and Waivers for energy storage devices not seeking to enroll in an initiative should be approved, approved with modifications, or denied.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The State agencies shall also include any recommended conditions.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>An applicant shall have 10 days to agree or disagree with these State agency recommended conditions in a filing to the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>State Agency Waiver Reviews. The State agencies shall also consider waiver requests for front-of-the-meter energy storage devices equal to or greater than 20 megawatt-hours per parcel pursuant to Regulation .08 of this chapter and make recommendations to the Commission within 4 months of receipt of all required information to approve, approve with modifications, or deny the waiver request.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".12" heading="Commission Approvals for Front-Of-The-Meter Energy Storage Devices.">
      <paragraph num="A.">
        <text>Pursuant to Public Utilities Article, §7–219(B), Annotated Code of Maryland, a person may not begin construction of a front-of-the-meter energy storage device unless the construction has been approved by the Commission.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Hearings and Approvals.</text>
        <paragraph num="(1)">
          <text>State agency recommendations coordinated by the Department of Natural Resources Power Plant Research Program pursuant to Regulation .11 of this chapter may be considered by the Commission in its Administrative Docket within 60 days of filing of the state agency recommendations unless there is a filing by any other state agency, county, municipal corporation, an affected community, or any other stakeholder opposing the state agency recommendations that necessitates an evidentiary hearing.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The Commission may approve, deny, or approve modifications to an application or a waiver request within 30 days of a hearing in either the Commission’s Administrative Docket or at an evidentiary hearing as determined by the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Compliance and Revocation of Approval.  If an energy storage device enrolled in an initiative is found to be in violation of any conditions approved for its inclusion, its approval may be revoked by the administrator and the energy storage device removed from enrollment in the initiative pursuant to a Commission determination.</text>
      </paragraph>
      <paragraph num="D.">
        <text>Appeals. Within 30 days of the filing of an appeal, the Commission may consider any motions to appeal any decisions. No change in an energy storage device’s application status, enrollment status, or registration status shall be made until the appeal is adjudicated by the Commission.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".13" heading="Annual Reporting.">
      <paragraph num="A.">
        <text>Starting September 1 of the year after the Commission approves the first administrator’s initiative, an administrator shall file the following information for the prior delivery year with the Commission segregated by market segment, ownership, and operating model, technology type, and SDES, LDES, Multi-day ES durations:</text>
        <paragraph num="(1)">
          <text>The following information regarding applications, enrollments, registrations, awards, and removals from initiatives:</text>
          <paragraph num="(a)">
            <text>Total number of energy storage device initiative applications;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Total kilowatts of energy storage device applications;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Total kilowatt-hours of energy storage device applications;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Total number of energy storage devices enrolled for each delivery year;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Total kilowatts of energy storage devices enrolled for each delivery year;</text>
          </paragraph>
          <paragraph num="(f)">
            <text>Total kilowatt-hours of energy storage devices enrolled for each delivery year;</text>
          </paragraph>
          <paragraph num="(g)">
            <text>Total number of energy storage devices registered;</text>
          </paragraph>
          <paragraph num="(h)">
            <text>Total kilowatts of energy storage devices registered;</text>
          </paragraph>
          <paragraph num="(i)">
            <text>Total kilowatt-hours of energy storage devices registered;</text>
          </paragraph>
          <paragraph num="(j)">
            <text>Total number of denied energy storage device applications;</text>
          </paragraph>
          <paragraph num="(k)">
            <text>Total kilowatts of denied energy storage applications;</text>
          </paragraph>
          <paragraph num="(l)">
            <text>Total kilowatt-hours of denied energy storage applications;</text>
          </paragraph>
          <paragraph num="(m)">
            <text>Total number of energy storage devices removed from initiative enrollment or registration by delivery year for any reason;</text>
          </paragraph>
          <paragraph num="(n)">
            <text>Total kilowatts of energy storage devices removed from an initiative enrollment or registration by delivery year for any reason;</text>
          </paragraph>
          <paragraph num="(o)">
            <text>Total kilowatt-hours of energy storage devices removed from an initiative enrollment or registration by delivery year for any reason;</text>
          </paragraph>
          <paragraph num="(p)">
            <text>Total kilowatts of energy storage device deployment incentives awarded in the prior delivery year;</text>
          </paragraph>
          <paragraph num="(q)">
            <text>Total kilowatt-hours of energy storage device deployment incentives awarded in the prior delivery year;</text>
          </paragraph>
          <paragraph num="(r)">
            <text>Total dollars for energy storage device deployment incentives awarded in the prior delivery year;</text>
          </paragraph>
          <paragraph num="(s)">
            <text>Total kilowatts for energy storage device procurement mechanisms awarded in the prior delivery year;</text>
          </paragraph>
          <paragraph num="(t)">
            <text>Total kilowatt-hours for energy storage device procurement mechanisms awarded in the prior delivery year; and</text>
          </paragraph>
          <paragraph num="(u)">
            <text>Total dollars for energy storage device procurement mechanisms awarded in the prior delivery year;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>The following information regarding pre-existing energy storage devices:</text>
          <paragraph num="(a)">
            <text>Total number of pre-existing energy storage devices discovered in the prior delivery year;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Total kilowatts of pre-existing energy storage devices discovered in the prior delivery year; and</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Total kilowatt-hours of pre-existing energy storage devices discovered in the prior delivery</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <text>year;</text>
      <paragraph num="(3)">
        <text>Initiative administrative costs in the prior delivery year;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Cumulative totals that include data from previous annual reports for the information in §§A(1), (2), and (3) of this regulation;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Initiative assessments containing the following information:</text>
        <paragraph num="(a)">
          <text>Initiative assessment regarding evaluation, measurement and verification benefit/costs expected and benefit/costs received in the prior delivery year; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Initiative assessment regarding equity impacts of the initiative in the prior delivery year, including:</text>
          <paragraph num="(i)">
            <text>Total number, total kilowatts and kilowatt-hours of energy storage devices providing benefits to underserved communities;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Percentage of number, total kilowatts and kilowatt-hours of energy storage devices providing benefits to underserved communities; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A description of actions taken to promote or incentivize initiative participation in underserved communities and any metrics used for monitoring underserved community participation; and</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>Cumulative totals that include data from previous annual reports for the information in §A(2)(a) and (b) of this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Maryland Energy Storage Program Annual Report. The Maryland Energy Storage Program Manager shall annually each October 1 file a report with the Commission that summarizes the information in §§A(1) and (2) of this regulation.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§1-101, 2-113, 2-121, 7-207, 7-216, 7-216.1, 7-219, 7–1001, and 7-1005, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: March 30, 2026 (52:6 Md. R. 292)</annotation>
    </annotations>
  </chapter>
</subtitle>