  <paragraph num="A.">
    <text>Authorization by Commission. A meter may be installed for use for revenue-billing purposes if it meets the following conditions:</text>
    <paragraph num="(1)">
      <text>Approved Type. Its type and design meet the requirements of COMAR 20.50.02.02.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Accuracy. The registration of the meter is within the tolerances specified in Regulation .03 of this chapter. A representative of the Commission will check the condition of meters in the meter shop of the utility from time to time by testing random samples of meters ready for installation.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Test Required. Each meter and associated metering device shall be inspected and tested in the meter shop of the utility, or sample tested by the utility if 100 percent tested by the manufacturer, before being placed in service, except for instrument transformers tested in accordance with Regulation .03E(3) of this chapter.</text>
  </paragraph>
  <paragraph num="C.">
    <text>Reinstallation. When a meter is removed from service, it shall be adjusted if necessary in order to conform to the accuracy tolerances specified in Regulation .03 of this chapter before being placed in service again. However, it may be retired without test or returned to service without being tested if it is covered by an in-service sample or periodic test plan.</text>
  </paragraph>