#### Regulation .05 Interconnection Request Processing Fees.

*COMAR 20.50.09.05*

A. A utility may only charge a small generator interconnection request fee for a Level 2, Level 3, or Level 4 interconnection request.

B. A utility may not charge interconnection request fees for interconnection requests determined to be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of this chapter.

C. The utility shall specify the interconnection [processing] request fees charged under this regulation in its tariff.