<regulation prefix="Regulation" num=".05" citation="COMAR 20.50.09.05" title_num="20" subtitle_num="50" chapter_num="09" heading="Interconnection Request Processing Fees.">
  <paragraph num="A.">
    <text>A utility may only charge a small generator interconnection request fee for a Level 2, Level 3, or Level 4 interconnection request.</text>
  </paragraph>
  <paragraph num="B.">
    <text>A utility may not charge interconnection request fees for interconnection requests determined to be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of this chapter.</text>
  </paragraph>
  <paragraph num="C.">
    <text>The utility shall specify the interconnection [processing] request fees charged under this regulation in its tariff.</text>
  </paragraph>
</regulation>