<regulation prefix="Regulation" num=".12" citation="COMAR 20.50.09.12" title_num="20" subtitle_num="50" chapter_num="09" heading="Level 4 Study Review.">
  <paragraph num="A.">
    <text>A utility shall use the Level 4 study review procedure for an interconnection request that meets the Level 4 criteria in Regulation .08 of this chapter.</text>
  </paragraph>
  <paragraph num="B.">
    <text>Interconnection Request.</text>
    <paragraph num="(1)">
      <text>Within 5 business days from receipt of an interconnection request, the utility shall notify the applicant whether the request is</text>
      <paragraph num="(a)">
        <text>Complete; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Incomplete.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>If the interconnection request is not complete:</text>
      <paragraph num="(a)">
        <text>The utility shall provide the applicant a written list detailing information that shall be provided to complete the interconnection request;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The applicant shall have 10 business days, which may be extended at the request of the applicant and not unreasonably denied by the utility, to provide appropriate data in order to complete the interconnection request, or the interconnection request shall be considered withdrawn; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The interconnection request shall be considered complete:</text>
        <paragraph num="(i)">
          <text>If the required information has been provided by the applicant; or</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>The utility and applicant have agreed that the applicant may provide additional information at a later time.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Queue Position.</text>
    <paragraph num="(1)">
      <text>When an interconnection request is complete, the utility shall assign a queue position.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The utility shall use the queue position of an interconnection request to determine the cost responsibility necessary for the facilities to accommodate the interconnection.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>The utility shall notify the applicant of other higher-queued applicants on the same line section of the new interconnection request.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Any required interconnection studies may not begin until the utility has completed its review of all other interconnection requests that have a higher queue position.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Queue position is not forfeited or otherwise impacted by any pending dispute submitted under the provisions of Regulation .13 of this chapter.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Scoping Meeting.</text>
    <paragraph num="(1)">
      <text>By mutual agreement of the utility and applicant, the scoping meeting may be waived and the interconnection feasibility study, interconnection impact study, or interconnection facilities studies provided for in a Level 4 review and discussed in this section may be waived or combined.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>If agreed to by the utility and applicant, a scoping meeting shall be held within 10 business days, or other mutually agreed to time, after the utility has notified the applicant that the interconnection request is considered complete, or the applicant has requested that its interconnection request proceed after failing the requirements of a Level 2 review or Level 3 review.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>The purpose of the meeting is to review the interconnection request, existing studies relevant to the interconnection request, and the results of the Level 1, Level 2, or Level 3 screening criteria.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>If the utility and applicant agree at a scoping meeting that an interconnection feasibility study shall be performed, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
      <paragraph num="(a)">
        <text>An interconnection feasibility study agreement;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>An outline of the scope of the study; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(5)">
      <text>If the applicant and utility agree at a scoping meeting that an interconnection feasibility study is not required, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
      <paragraph num="(a)">
        <text>An interconnection system impact study agreement;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>An outline of the scope of the study; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(6)">
      <text>If the utility and applicant agree at the scoping meeting that an interconnection feasibility study and system impact study are not required, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
      <paragraph num="(a)">
        <text>An interconnection facilities study agreement;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>An outline of the scope of the study; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Interconnection Feasibility, Interconnection System Impact, and Interconnection Facilities Studies.</text>
    <paragraph num="(1)">
      <text>Interconnection Feasibility Study.</text>
      <paragraph num="(a)">
        <text>An interconnection feasibility study shall include any necessary analyses for the purpose of identifying a potential adverse system impact to the utility's electric distribution system that would result from the interconnection from among the following:</text>
        <paragraph num="(i)">
          <text>Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Initial identification of any thermal overload or voltage limit violations resulting from the interconnection;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>Initial review of grounding requirements and system protection; and</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>Description and nonbinding estimated cost of facilities required to interconnect the small generator facility to the utility's electric distribution system in a safe and reliable manner.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>If an applicant requests that the interconnection feasibility study evaluate multiple potential points of interconnection, additional evaluations may be required. Additional evaluations shall be conducted at the expense of the applicant.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>An interconnection system impact study is not required if the interconnection feasibility study concludes there is no adverse system impact, or if the study identifies an adverse system impact and the utility is able to identify a remedy without the need for an interconnection system impact study.</text>
      </paragraph>
      <paragraph num="(d)">
        <text>The utility and applicant shall use an interconnection feasibility study agreement form.</text>
      </paragraph>
      <paragraph num="(e)">
        <text>The utility shall avoid duplicating previously conducted interconnection studies to the extent possible.</text>
      </paragraph>
      <paragraph num="(f)">
        <text>The utility may require a study deposit of the lesser of 100 percent of estimated nonbinding good faith study costs or $1,000.</text>
      </paragraph>
      <paragraph num="(g)">
        <text>The interconnection feasibility study shall be completed and the results shall be transmitted to the interconnection customer within 30 calendar days after the interconnection feasibility study agreement is signed by the parties.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Interconnection System Impact Study.</text>
      <paragraph num="(a)">
        <text>A distribution interconnection system impact study shall be performed when a potential distribution system adverse system impact is identified in the interconnection feasibility study.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Scope of Interconnection System Impact Study.</text>
        <paragraph num="(i)">
          <text>An interconnection system impact study shall evaluate the impact of the proposed interconnection on both the safety and reliability of the utility's electric distribution system.</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>The interconnection system impact study shall identify and detail the system impacts that result when a small generator facility is interconnected without project or system modifications, focusing on the adverse system impacts identified in the interconnection feasibility study, or potential impacts including those identified in the scoping meeting.</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>The interconnection system impact study shall consider all small generator facilities that, on the date the interconnection system impact study is commenced, are directly interconnected with the utility's electric distribution system, have a pending higher queue position to interconnect to the system, or have signed an interconnection agreement.</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>As part of its impact study, the utility shall agree to evaluate and consider any separate studies prepared by the applicant that evaluate alternatives for interconnecting the small generator facility, including the applicant's assessment of potential impacts of the small generator facility on the electric distribution system.</text>
        </paragraph>
        <paragraph num="(v)">
          <text>The utility shall provide the applicant with the utility's final impact study evaluation, including a comparison of the results of its own analyses with those provided by the applicant.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(c)">
        <text>Within 5 business days of transmittal of the interconnection feasibility study report, the utility shall send the applicant:</text>
        <paragraph num="(i)">
          <text>An interconnection system impact study agreement using a form;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>An outline of the scope of the interconnection system impact study; and</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>A good faith estimate of the cost to perform the study.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(d)">
        <text>The interconnection system impact study shall include any necessary elements from among the following:</text>
        <paragraph num="(i)">
          <text>A load flow study;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Identification of affected systems;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>An analysis of equipment interrupting ratings;</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>A protection coordination study;</text>
        </paragraph>
        <paragraph num="(v)">
          <text>Voltage drop and flicker studies;</text>
        </paragraph>
        <paragraph num="(vi)">
          <text>Protection and set point coordination studies;</text>
        </paragraph>
        <paragraph num="(vii)">
          <text>Grounding reviews; and</text>
        </paragraph>
        <paragraph num="(viii)">
          <text>Impact on system operation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(e)">
        <text>An interconnection system impact study shall consider any necessary criteria from among the following:</text>
        <paragraph num="(i)">
          <text>A short circuit analysis;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>A stability analysis;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>Alternatives for mitigating adverse system impacts on affected systems;</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>Voltage drop and flicker studies;</text>
        </paragraph>
        <paragraph num="(v)">
          <text>Protection and set point coordination studies; and</text>
        </paragraph>
        <paragraph num="(vi)">
          <text>Grounding reviews.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(f)">
        <text>The final interconnection system impact study shall provide the following:</text>
        <paragraph num="(i)">
          <text>The underlying assumptions of the study;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>The results of the analyses;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>A list of any potential impediments to providing the requested interconnection service;</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>Required distribution upgrades; and</text>
        </paragraph>
        <paragraph num="(v)">
          <text>A nonbinding good faith estimate of cost and time to construct any required distribution upgrades.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(g)">
        <text>The utility may require a study deposit of the lesser of 50 percent of estimated nonbinding good faith study costs or $3,000.</text>
      </paragraph>
      <paragraph num="(h)">
        <text>The interconnection system impact study, if required, shall be completed and the results transmitted to the interconnection customer within 45 calendar days after the interconnection system impact study agreement is signed by the parties.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>Interconnection Facilities Study.</text>
      <paragraph num="(a)">
        <text>Within 5 business days of completion of the interconnection system impact study, the utility shall provide to the applicant:</text>
        <paragraph num="(i)">
          <text>A report of the interconnection system impact study;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>An interconnection facilities study agreement;</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>An outline of the scope of the interconnection facilities study; and</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>A nonbinding good faith estimate of the cost to perform the facilities study.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>The interconnection facilities study shall identify:</text>
        <paragraph num="(i)">
          <text>The electrical switching configuration of the equipment, including transformer, switchgear, meters, and other station equipment;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>The nature and estimated cost of the utility's interconnection facilities and distribution upgrades necessary to accomplish the interconnection, including engineering, procurement, construction, and overhead; and</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>An estimate of the time required to complete the construction and installation of the facilities.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(c)">
        <text>Third-Party Design or Construction of Interconnection Facilities.</text>
        <paragraph num="(i)">
          <text>The applicant and utility may agree to permit an applicant to separately arrange for a third party to design and construct the required interconnection facilities.</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>The utility may review and approve the design of the facilities under the interconnection facilities study agreement.</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>If the applicant and utility agree to separately arrange for design and construction, the utility, consistent with security and confidentiality requirements, shall make all relevant information and required specifications available to the applicant to permit the applicant to obtain an independent design and cost estimate for the interconnection facilities.</text>
        </paragraph>
        <paragraph num="(iv)">
          <text>The interconnection facilities shall be built in accordance with the specifications in the interconnection facilities study.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(d)">
        <text>Upon completion of the interconnection facilities study, and with the agreement of the applicant to pay for the interconnection facilities and distribution upgrades identified in the interconnection facilities study, the utility shall provide the applicant with an interconnection agreement within 5 business days.</text>
      </paragraph>
      <paragraph num="(e)">
        <text>The utility may require a study deposit of the lesser of 50 percent of estimated nonbinding good faith study costs or $10,000.</text>
      </paragraph>
      <paragraph num="(f)">
        <text>In cases where no interconnection upgrades are required, the interconnection facilities study shall be completed and the results shall be transmitted to the interconnection customer within 30 calendar days after the agreement is signed by the parties.</text>
      </paragraph>
      <paragraph num="(g)">
        <text>In cases where interconnection upgrades are required, the interconnection facilities study shall be completed and the results shall be transmitted to the interconnection customer within 45 calendar days after the agreement is signed by the parties.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>Interconnection Agreement.</text>
    <paragraph num="(1)">
      <text>When a utility determines, as a result of the interconnection studies conducted under a Level 4 review, that it is appropriate to interconnect the small generator facility, the utility shall provide the applicant with an interconnection agreement.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The applicant shall have either 30 calendar days, or another mutually agreeable time frame after receipt of the interconnection agreement, to sign and return the interconnection agreement.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>If the applicant does not sign the interconnection agreement within 30 calendar days, the request shall be considered withdrawn unless the applicant and utility mutually agree to extend the time period for executing the interconnection agreement prior to the expiration of the 30-calendar-day period. A request for extension may not be unreasonably denied by the utility.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>After the interconnection agreement is signed by the applicant and utility, interconnection of the small generator facility shall proceed according to any milestones agreed to by the applicant and utility in the interconnection agreement.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>The utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
      <paragraph num="(a)">
        <text>All milestones agreed to in the interconnection agreement are satisfied;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The small generator facility is approved by electric code officials with jurisdiction over the interconnection;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The applicant provides a certificate of completion to the utility;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Upon request of the utility, the applicant provides one or more photographs of the small generator facility site location, components, metering equipment, and other related facilities and equipment; and</text>
      </paragraph>
      <paragraph num="(e)">
        <text>There is a successful completion of the witness test, if conducted by the utility.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="G.">
    <text>Level 4 Review Failure. If the interconnection request is denied, the utility shall provide the applicant a letter explaining the reasons for denying the interconnection request.</text>
  </paragraph>