<chapter num="09" heading="Small Generator Facility Interconnection Standards" title_num="20" subtitle_num="50">
  <regulation prefix="Regulation" num=".01" heading="Scope.">
    <paragraph num="A.">
      <text>This chapter applies to a small generator facility seeking to interconnect and operate in parallel with the electric distribution system. All small generator facilities shall interconnect under requirements in this chapter or under the physical interconnection requirements of the PJM Interconnection, LLC under the authority of FERC.</text>
    </paragraph>
    <paragraph num="B.">
      <text>A small generator facility seeking to interconnect and operate in parallel with the electric distribution system under this chapter shall meet one of the following criteria:</text>
      <paragraph num="(1)">
        <text>The small generator facility is a qualifying facility pursuant to the Public Utility Regulatory Policies Act that intends to make sales at a rate approved by the Maryland Commission;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The small generator facility is not a qualifying facility pursuant to the Public Utility Regulatory Policies Act and does not intend to make sales of wholesale electric energy through the PJM Interconnection, LLC;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The small generator facility intends to make sales of wholesale electric energy through the PJM Interconnection, LLC at an electric distribution interconnection facility where there has been no prior FERC jurisdictional service;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The small generator facility intends to make sales of wholesale electric energy through the PJM Interconnection, LLC only at an electric distribution interconnection facility through participation in a distributed energy resource aggregation; or</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The small generator facility will be interconnected to an electric distribution circuit and its energy will not be transmitted across state lines for a wholesale customer other than the electric distribution owner.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Market processes under FERC jurisdiction that are administered by the PJM Interconnection, LLC may not impede the interconnection timeline requirements in this chapter unless the utility has good cause to believe that equipment upgrades exceeding minor equipment modifications and related modifications to the interconnection agreement will be needed to facilitate these market processes. In these cases, the utility shall notify the interconnection customer in writing of their rationale to delay approval of the interconnection request until the conclusion of the PJM Interconnection, LLC's market process study.</text>
    </paragraph>
    <paragraph num="D.">
      <text>In situations where an interconnected small generator facility project intends to change their energy sales strategy from market processes under FERC jurisdiction to retail processes under this chapter, the small generator facility shall submit an interconnection request.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Definitions.">
    <paragraph num="A.">
      <text>In this chapter, the following terms have the meanings indicated.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Terms Defined.</text>
      <paragraph num="(1)">
        <text>“AC EVSE” means supply equipment that passes alternating current to the EV with conversion between AC and DC accomplished onboard the EV.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>“Adverse system impact” means a negative effect, due to technical or operational limits on conductors or equipment being exceeded, that may compromise the safety or reliability of the electric distribution system.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>“Affected system” means a utility electric system that is affected by the interconnection of a small generator facility to another utility’s electric distribution system.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>“Aggregate generation” means the aggregated net system capacities of all small generator facilities across multiple points of common coupling.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>“Applicant” means a person who has submitted an interconnection request to interconnect a small generator facility to a utility's electric distribution system.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>“Area network” means a type of electric distribution system served by multiple transformers interconnected in an electrical network circuit, often used in large, densely populated metropolitan areas.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>“Bidirectional electric vehicle” has the meaning stated in Public Utilities Article, §7-1001(c), Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>“Certificate of completion” means a certificate provided by a utility to an applicant containing information about the interconnection equipment used, its installation, and local inspections.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>“Closed circuit” means an electric distribution system circuit with no available hosting capacity.</text>
      </paragraph>
      <paragraph num="(10)">
        <text>“Commissioning test” means one of several tests applied to a small generator facility by the applicant after construction is completed to verify that the small generator facility does not create adverse system impacts, including the test specified in Section 5.4 of IEEE Standard 1547.</text>
      </paragraph>
      <paragraph num="(11)">
        <text>“DC EVSE” means supply equipment that passes direct current to or from the EV, with the EVSE accomplishing conversion between AC and DC.</text>
      </paragraph>
      <paragraph num="(12)">
        <text>“Default utility required inverter settings profile” means a utility set of default smart inverter settings optimized for use across a utility’s service territory.</text>
      </paragraph>
      <paragraph num="(13)">
        <text>“Distributed energy resource” means any geographically dispersed energy resource located on an electric distribution system that produces electricity or offsets electrical demand including small generator facilities, energy storage devices, energy efficiency devices, and demand response devices.</text>
      </paragraph>
      <paragraph num="(14)">
        <text>“Distribution upgrade” means a required addition or modification to the utility electric distribution system, excluding the interconnection facilities, necessary to accommodate the interconnection of a small generator facility.</text>
      </paragraph>
      <paragraph num="(15)">
        <text>“Draw-out type circuit breaker” means a molded case switching device that:</text>
        <paragraph num="(a)">
          <text>Can be inserted into or removed from its enclosure during no-load conditions; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Is capable of making, carrying, and breaking currents under normal and abnormal circuit conditions.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(16)">
        <text>Electric Distribution System.</text>
        <paragraph num="(a)">
          <text>“Electric distribution system” means the facilities and equipment used to transmit electricity generally at less than 69 kV to ultimate usage points such as homes and industries from interchanges with higher voltage transmission networks that transport bulk power over longer distances.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Electric distribution system” has the same meaning as the term Area EPS as defined in Section 3.1.6.1 of IEEE Standard 1547.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(17)">
        <text>“Electric vehicle” or “EV” means a vehicle that employs electrical energy as a primary or secondary mode of propulsion and is capable of charging the onboard battery from an external supply of electricity.</text>
      </paragraph>
      <paragraph num="(18)">
        <text>“Electric vehicle supply equipment” or “EVSE” means a device or system designed and used specifically to transfer electrical energy between an electric vehicle and the electric grid.</text>
      </paragraph>
      <paragraph num="(19)">
        <text>“Energy Storage Device” means a piece of equipment that captures energy produced at one time, stores that energy for a period of time, and delivers that energy as electricity at a future time.</text>
      </paragraph>
      <paragraph num="(20)">
        <text>“Fault current” means the electrical current that flows through a circuit during an electrical fault condition, such as when one or more electrical conductors contact ground or each other.</text>
      </paragraph>
      <paragraph num="(21)">
        <text>“Grid support services” means compensated or uncompensated services unrelated to wholesale markets provided by a small generator facility that support the safety, stability, reliability, or economics of the electric grid.</text>
      </paragraph>
      <paragraph num="(22)">
        <text>“Hosting capacity” means the amount of aggregate generation that can be accommodated on an electric distribution system or area, or a system component, without requiring infrastructure upgrades.</text>
      </paragraph>
      <paragraph num="(23)">
        <text>“Hosting capacity reporting system” means the information available on a utility website providing reports, tabular data, or maps of hosting capacity available on the electric distribution system.</text>
      </paragraph>
      <paragraph num="(24)">
        <text>“Hosting capacity upgrade plan” means a utility plan to promote clean energy interconnection for a particular area or a proposal to open multiple restricted and closed circuits or areas on an electric system in the aggregate through proactive distribution system investments that includes a cost allocation and recovery proposal, under conditions that are approved by the Commission.</text>
      </paragraph>
      <paragraph num="(25)">
        <text>“IEEE Standard 1547” means the standard incorporated by reference in COMAR 20.50.02.02.</text>
      </paragraph>
      <paragraph num="(26)">
        <text>“IEEE Standard 1547.1” means the standard incorporated by reference in COMAR 20.50.02.02.</text>
      </paragraph>
      <paragraph num="(27)">
        <text>“Inadvertent export” means the unscheduled export of power from a small generator facility, beyond a specified magnitude and for a limited duration, generally due to fluctuations in load-following behavior.</text>
      </paragraph>
      <paragraph num="(28)">
        <text>“Interconnection agreement” means an agreement that contains details regarding the proposed interconnection equipment and its operation to ensure the reliability and safety of the grid, including schedules, rights, obligations, and terms and conditions that become effective on the date the agreement is executed by the utility and the interconnection customer.</text>
      </paragraph>
      <paragraph num="(29)">
        <text>“Interconnection customer” means an entity that proposes to interconnect or has interconnected a small generator facility to an electric distribution system.</text>
      </paragraph>
      <paragraph num="(30)">
        <text>Interconnection Equipment.</text>
        <paragraph num="(a)">
          <text>“Interconnection equipment” means a group of components or an integrated system connecting an electric generator with a local electric power system, or an electric distribution system.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Interconnection equipment” means all interface equipment including switchgear, protective devices, inverters, or other interface devices.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>“Interconnection equipment” includes equipment installed as part of an integrated equipment package that includes a generator or other electric source.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(31)">
        <text>Interconnection Facilities.</text>
        <paragraph num="(a)">
          <text>“Interconnection facilities” means facilities and equipment required by the utility to accommodate the interconnection of a small generator facility.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Interconnection facilities” includes all facilities and equipment between the small generator facility and the point of interconnection, and modifications, additions, or upgrades that are necessary to physically and electrically interconnect the small generator facility to the electric distribution system.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>“Interconnection facilities” includes any distribution upgrade.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(32)">
        <text>“Interconnection facility cost sharing” means the allocation of distribution interconnection facility upgrade costs among multiple small generator facility projects that utilize the hosting capacity created by an interconnection facility upgrade.</text>
      </paragraph>
      <paragraph num="(33)">
        <text>“Interconnection request” means an applicant's request for the interconnection of a small generator facility, or to increase the capacity or operating characteristics of a small generator facility that is already interconnected with the utility's electric distribution system.</text>
      </paragraph>
      <paragraph num="(34)">
        <text>“Interconnection study” means an interconnection feasibility study, interconnection system impact study, or interconnection facilities study as described in Regulation .12 of this chapter.</text>
      </paragraph>
      <paragraph num="(35)">
        <text>“Limited export agreement” means an agreement for energy supplied to the grid by an interconnection customer that may be managed to specified ramp rates and generation levels for operating conditions, as specified in the interconnection agreement or in a separate limited export agreement.</text>
      </paragraph>
      <paragraph num="(36)">
        <text>“Line section” means that portion of a utility electric distribution system connected to an interconnection customer, bounded by automatic sectionalizing devices, or the end of the distribution line.</text>
      </paragraph>
      <paragraph num="(37)">
        <text>Local Electric Power System.</text>
        <paragraph num="(a)">
          <text>“Local electric power system” means those facilities that deliver electric power to a load that are contained entirely within a single premises or group of premises.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Local electric power system” has the same meaning as the term local electric power system as defined in Section 3.1.6.2 of IEEE Standard 1547.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(38)">
        <text>“Meter collar adapter” means an electronic device that is installed between a residential electric meter and the meter socket, for the purpose of facilitating the deployment of customer-owned or customer-leased technology.</text>
      </paragraph>
      <paragraph num="(39)">
        <text>“Minor equipment modification” means a change to the proposed small generator facility that does not have a significant impact on safety or reliability of the electric distribution system.</text>
      </paragraph>
      <paragraph num="(40)">
        <text>“Minor system modification” means a change to the distribution system:</text>
        <paragraph num="(a)">
          <text>Located between the service tap on the distribution circuit and the meter serving the applicant; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>That the utility estimates will entail less than 4 hours of work and less than $1,500 in materials.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(41)">
        <text>“Nameplate capacity” means the maximum rated output of a generator at a point of common coupling of all electric power production equipment or energy storage devices under specific conditions designated by the manufacturer that is usually listed on a nameplate physically attached to the equipment.</text>
      </paragraph>
      <paragraph num="(42)">
        <text>“Nationally recognized testing laboratory (NRTL)” means a qualified private organization recognized by the Occupational Safety and Health Administration to perform independent safety testing and product certification.</text>
      </paragraph>
      <paragraph num="(43)">
        <text>“Net system capacity” means the total export capacity at a point of common coupling of a small generator facility as measured by the nameplate capacities of all power production units and energy storage devices minus their consumption of electrical power, if applicable, as limited through the use of a control system, power relays, or other similar device settings or adjustments.</text>
      </paragraph>
      <paragraph num="(44)">
        <text>“Parallel operation” means the sustained state of operation over 100 milliseconds which occurs when a small generator facility is connected electrically to the electric distribution system, and thus has the ability for electricity to flow from the small generator facility to the electric distribution system.</text>
      </paragraph>
      <paragraph num="(45)">
        <text>“Permission to operate notice” means the written permission provided by a utility in the form of an email or letter authorizing an interconnection customer to interconnect and operate its small generator interconnection facility.</text>
      </paragraph>
      <paragraph num="(46)">
        <text>“Point of common coupling” means the point of interconnection where the small generator facility is electrically connected to the electric distribution system.</text>
      </paragraph>
      <paragraph num="(47)">
        <text>“Point of interconnection” has the same meaning as the term “point of common coupling”.</text>
      </paragraph>
      <paragraph num="(48)">
        <text>“Primary line” means a distribution line rated at greater than 600 volts.</text>
      </paragraph>
      <paragraph num="(49)">
        <text>“Primary voltage hosting capacity upgrade cost” means the equipment upgrade costs of all interconnection equipment, interconnection facilities, protective devices and associated communications systems, and other upgrades that directly increase hosting capacity for multiple primary voltage and secondary voltage interconnection customers while excluding equipment upgrade costs that solely benefit a single interconnection customer, to the extent practicable and material.</text>
      </paragraph>
      <paragraph num="(50)">
        <text>“Primary voltage interconnection customer” means an interconnection customer with a point of interconnection at greater than 600 nominal volts.</text>
      </paragraph>
      <paragraph num="(51)">
        <text>Proposed Use.</text>
        <paragraph num="(a)">
          <text>“Proposed use” means the operational control modes of a small generator facility upon which the applicant’s technical review is based and under which the small generator facility is bound to operate upon the execution of the interconnection agreement.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Proposed use” for a small generator facility includes a combination of electric generators and energy storage devices operating in specified operational control modes during specified time periods.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(52)">
        <text>“Queue position” means the order of a completed interconnection request, relative to all other pending completed interconnection requests, that is established based upon the date and time of receipt of the completed interconnection request by the utility.</text>
      </paragraph>
      <paragraph num="(53)">
        <text>“Radial distribution circuit” means a circuit configuration in which independent feeders branch out radially from a common source of supply.</text>
      </paragraph>
      <paragraph num="(54)">
        <text>“Reserve hosting capacity” means the amount of hosting capacity reserved for small generator facilities on an electric distribution system circuit.</text>
      </paragraph>
      <paragraph num="(55)">
        <text>“Restricted circuit” means an electric system distribution circuit with reserve hosting capacity.</text>
      </paragraph>
      <paragraph num="(56)">
        <text>“Rightsizing” means to increase the size, scope, and cost of an electric utility hosting capacity upgrade project, following a distributed energy resource interconnection request, to account for both the immediate interconnection customer’s needs and future hosting capacity needs that are identified by the electric utility through a distributed energy resource forecast.</text>
      </paragraph>
      <paragraph num="(57)">
        <text>“Scoping meeting” means a meeting between the applicant and utility conducted for the purpose of discussing alternative interconnection options, exchanging information, including any electric distribution system data and earlier study evaluations that would be reasonably expected to impact interconnection options, analyzing information, and determining the potential feasible points of interconnection.</text>
      </paragraph>
      <paragraph num="(58)">
        <text>“Secondary line” means a service line subsequent to the primary line that is rated for 600 volts or less, also referred to as the customer's service line.</text>
      </paragraph>
      <paragraph num="(59)">
        <text>“Secondary voltage hosting capacity upgrade cost” means the costs of all primary voltage and secondary voltage interconnection equipment upgrades that directly increase secondary voltage hosting capacity available to multiple secondary voltage interconnection customers while excluding all primary voltage and secondary voltage interconnection equipment upgrade costs that solely benefit a single interconnection customer, to the extent practicable and material.</text>
      </paragraph>
      <paragraph num="(60)">
        <text>“Secondary voltage interconnection customer” means an interconnection customer with a point of interconnection at less than or equal to 600 nominal volts.</text>
      </paragraph>
      <paragraph num="(61)">
        <text>“Shared transformer" means a transformer that supplies secondary source voltage to more than one customer.</text>
      </paragraph>
      <paragraph num="(62)">
        <text>“Site-specific utility required inverter settings profile” means a set of smart inverter settings optimized for use at a specific site on a utility’s electric system.</text>
      </paragraph>
      <paragraph num="(63)">
        <text>Small Generator Facility.</text>
        <paragraph num="(a)">
          <text>“Small generator facility” means the equipment used to generate or store electricity that operates in parallel with the electric distribution system.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Small generator facility” includes an electric generator, a prime mover, energy storage device, and the interconnection equipment required to safely interconnect with the electric distribution system or local electric power system.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(64)">
        <text>“Smart Inverter” means any inverter hardware system certified to be compliant with IEEE 1547-2018 or subsequent revisions to these standards.</text>
      </paragraph>
      <paragraph num="(65)">
        <text>Spot Network.</text>
        <paragraph num="(a)">
          <text>“Spot network” means a type of electric distribution system that uses two or more inter-tied transformers to supply an electrical network circuit.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Spot network” is generally used to supply power to a single customer or a small group of customers.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>“Spot network” has the same meaning as the term is defined in 4.1.4 of IEEE Standard 1547.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(66)">
        <text>“Statewide utility required inverter settings profile” or “grid code” means a set of smart inverter settings optimized for use Statewide that can be used by utilities and manufacturers in establishing defaults.</text>
      </paragraph>
      <paragraph num="(67)">
        <text>“Technical interconnection requirement” or “TIR” means a public-facing document available on an electric company's website that specifies interconnection technical review criteria and distributed energy resource functional settings.</text>
      </paragraph>
      <paragraph num="(68)">
        <text>“Utility monitoring and control plan” means a plan to monitor and control, in the aggregate, a set of small generator facilities in multiple locations that includes a cost recovery method, under conditions that are approved by the Commission.</text>
      </paragraph>
      <paragraph num="(69)">
        <text>“Utility required inverter settings profile” means smart inverter settings for a small generator facility that are established by a utility.</text>
      </paragraph>
      <paragraph num="(70)">
        <text>“V1G or managed charging” means a range of approaches from utility programs and rate design to incentivize ratepayers for varying the time or rate at which an electric vehicle is charged.</text>
      </paragraph>
      <paragraph num="(71)">
        <text>“V1G Ready EVSE” is an EVSE that is capable of controlled charging rate operation but is either not certified for or is certified for but not programmed or configured for bidirectional operation.</text>
      </paragraph>
      <paragraph num="(72)">
        <text>“V2G or vehicle-to-grid” means the ability for an EVSE connected to a bidirectional electric vehicle to operate in parallel to the grid and both receive and feed power to the point of interconnection between the EVSE and the grid.</text>
      </paragraph>
      <paragraph num="(73)">
        <text>“V2G Ready EVSE” is an AC EVSE or DC EVSE, is certified for and programmed or configured for bidirectional operation as part of a V2G system in parallel with the electric grid.</text>
      </paragraph>
      <paragraph num="(74)">
        <text>“V2G System” is a combination of hardware and software in or around the EVSE and EV for the purposes of communication with and programmed flow of energy into and out of the vehicle battery in support of electrical loads or systems offboard the EV, including the electric grid.</text>
      </paragraph>
      <paragraph num="(75)">
        <text>“Witness test” means, for lab-certified or field-approved equipment, verification either by an on-site observation or review of documents by the utility that the interconnection installation evaluation required by Section 5.3 of IEEE Standard 1547 and the commissioning test required by Section 5.4 of IEEE Standard 1547 have been adequately performed.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Acceptable Standards.">
    <text>The technical standard to be used in evaluating all interconnection requests under Level 1, Level 2, Level 3, and Level 4 reviews, unless otherwise provided for in this chapter, is IEEE Standard 1547.</text>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Interconnection Requests.">
    <paragraph num="A.">
      <text>Applicants seeking to interconnect a small generator facility shall submit an interconnection request to the utility that owns the electric distribution system to which interconnection is sought.</text>
    </paragraph>
    <paragraph num="B.">
      <text>An interconnection request shall be in the form and format specified by the utility that owns the electric distribution system to which interconnection is sought and shall include the following information and any additional information that may be reasonably requested by the utility:</text>
      <paragraph num="(1)">
        <text>Contact information for the interconnection customer;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Existing utility account information;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Location information for the small generator facility;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Contact information for the interconnection customer’s equipment and electrical contractors;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Information on the manner in which the interconnection customer intends to use the small generator facility;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Requested review level for interconnection request;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Technical information regarding the generator and prime mover;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Technical information regarding the interconnection components and system or systems;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Location and other information regarding disconnect switch for small generator facility;</text>
      </paragraph>
      <paragraph num="(10)">
        <text>Details regarding any plans to export power to the electric distribution system; and</text>
      </paragraph>
      <paragraph num="(11)">
        <text>Any other item specified by the Commission.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Each utility shall make reasonable efforts to align the content of its interconnection request form with those forms provided by other utilities in Maryland.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Each utility shall establish a process that allows an applicant and an applicant’s authorized designee to:</text>
      <paragraph num="(1)">
        <text>Sign and submit an interconnection request electronically on the utility’s website;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Track the status of the interconnection request electronically; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Conduct electronically any other process that can reasonably occur in that manner.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Interconnection Request Processing Fees.">
    <paragraph num="A.">
      <text>A utility may only charge a small generator interconnection request fee for a Level 2, Level 3, or Level 4 interconnection request.</text>
    </paragraph>
    <paragraph num="B.">
      <text>A utility may not charge interconnection request fees for interconnection requests determined to be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of this chapter.</text>
    </paragraph>
    <paragraph num="C.">
      <text>The utility shall specify the interconnection [processing] request fees charged under this regulation in its tariff.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="General Requirements.">
    <paragraph num="A.">
      <text>For small generator facilities at a site for which the applicant seeks a single point of interconnection, the interconnection request shall be evaluated for total exports on the basis of the net system capacity.</text>
    </paragraph>
    <paragraph num="B.">
      <text>An interconnection request is required for the interconnection of a new small generator facility, or to increase the total exports, change the energy sales strategy pursuant to Regulation .01C of this chapter, or change the proposed use of an existing small generator facility. Any time a new interconnection request is processed for an existing small generator facility, the utility will apply any standards in effect at the time of the interconnection request and, if approved, a new interconnection agreement will be required. The interconnection request shall be evaluated on the basis of the total net system capacity of the small generator facility.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Utility Provided Information.</text>
      <paragraph num="(1)">
        <text>A utility shall designate a contact person, and provide contact information on its website and for the Commission's website for submission of all interconnection requests, and from whom information on the interconnection request process and the utility's electric distribution system can be obtained.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The information provided by the utility on its website shall include studies and other materials useful to an understanding of the feasibility of interconnecting a small generator facility on the utility electric distribution system, except to the extent providing the materials would violate security requirements or confidentiality agreements, or be contrary to law.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>For projects with a nameplate capacity over 20kW, the utility shall:</text>
        <paragraph num="(a)">
          <text>Provide the applicant an opportunity to request a pre-application report, which may require payment of a fee listed in the utility’s tariff;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Publicly post the fee amount on the utility’s website; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Provide the pre-application report within 20 business days, once the fee is paid.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The pre-application report shall rely largely on pre-existing utility data and shall, at a minimum, include the following items:</text>
        <paragraph num="(a)">
          <text>Initial proposed point of interconnection of the small generator facility, including address or GIS coordinates;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Closest electrical facilities to the initial proposed point of interconnection of the small generator facility, including voltage level, feeder identification, substation, and including distance to that substation;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Amount of generation hosting capacity available on the closest feeder, if this information is in possession of or easily obtainable by the utility; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Any other items specified by the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>In appropriate circumstances, the utility may require an applicant to execute an appropriate confidentiality agreement prior to release or access to confidential or restricted information.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>If an interconnection request is determined to be complete, any material modification, other than a minor equipment modification, that is not agreed to in writing by the utility, shall require submission of a new interconnection request.</text>
    </paragraph>
    <paragraph num="E.">
      <text>If an applicant is not currently a customer of the utility at the location for the proposed small generator facility, upon request from the utility, the applicant shall provide proof of site control evidenced by a property tax bill, deed, lease agreement, contract, or other acceptable document.</text>
    </paragraph>
    <paragraph num="F.">
      <text>Connection of Multiple Small Generator Facilities by Single Interconnection.</text>
      <paragraph num="(1)">
        <text>To minimize the cost of interconnecting multiple small generator facilities, the utility or the applicant may propose a single point of interconnection for multiple small generator facilities located at a single site.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If an applicant rejects a utility proposal for a single point of interconnection, the applicant shall pay any additional cost of providing separate points of interconnection for each small generator facility.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If a utility unreasonably rejects a customer proposal for a single point of interconnection without providing a written technical explanation, the utility shall pay any additional cost of providing separate points of interconnection for each small generator facility.</text>
      </paragraph>
    </paragraph>
    <paragraph num="G.">
      <text>Electrical Isolation of a Small Generator Facility.</text>
      <paragraph num="(1)">
        <text>A small generator facility shall be capable of being isolated from the utility electric distribution system.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>For a small generator facility interconnecting to a primary or secondary line, the isolation shall be by means of a lockable, visible-break isolation device accessible by the utility.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The isolation device shall be installed, owned, and maintained by the interconnection customer for the small generator facility, and located electrically between the small generator facility and the point of interconnection.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>A draw-out type circuit breaker with a provision for padlocking at the draw-out position satisfies the requirement for an isolation device.</text>
      </paragraph>
    </paragraph>
    <paragraph num="H.">
      <text>Use of Lockbox for Access to Isolation Device.</text>
      <paragraph num="(1)">
        <text>An interconnection customer may elect to provide the utility access to an isolation device that is contained in a building or area that may be unoccupied and locked or not otherwise readily accessible to the utility, by installing a lockbox provided by the utility that shall allow ready access to the isolation device.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The lockbox shall be in a location that is readily accessible by the utility, and the interconnection customer shall permit the utility to affix a placard in a location of its choosing that provides clear instructions to utility operating personnel on access to the isolation device.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>In the event the interconnection customer fails to comply with the terms of this section and the utility needs to gain access to the isolation device, the utility may not be held liable for any damages resulting from any necessary utility action to isolate the small generator facility.</text>
      </paragraph>
    </paragraph>
    <paragraph num="I.">
      <text>Metering.</text>
      <paragraph num="(1)">
        <text>Any metering necessitated by a small generator facility interconnection shall be installed, operated, and maintained in accordance with the applicable utility tariff.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Any small generator facility metering requirements shall be clearly identified as part of the interconnection agreement executed by the interconnection customer and the utility.</text>
      </paragraph>
    </paragraph>
    <paragraph num="J.">
      <text>Utility Monitoring and Control of Small Generator Facility.</text>
      <paragraph num="(1)">
        <text>Utility monitoring or control of a small generator facility shall be permitted subject to the conditions in §J of this regulation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Any utility monitoring or control requirements shall be:</text>
        <paragraph num="(a)">
          <text>Consistent with the utility published requirements, as available on the utility’s website; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Clearly identified in an interconnection agreement executed by the interconnection customer and the utility.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>For a small generator facility under a nameplate capacity of 2 MW, utility monitoring or control is not permitted unless:</text>
        <paragraph num="(a)">
          <text>The Commission approves a utility monitoring and control plan addressing such facilities in the aggregate; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The interconnection customer consents to utility monitoring or control.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Equipment certified under the latest published editions of IEEE 1547, IEEE 1547.1, and UL 1741 shall be permitted to be used for monitoring or control upon mutual agreement of the utility and the interconnection customer.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>A utility monitoring and control plan submitted to the Commission pursuant to §J(3)(a) of this regulation shall include:</text>
        <paragraph num="(a)">
          <text>Technical requirements;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Cost;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Benefits;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Comparison to IEEE 1547-2018 compliant monitoring and control alternatives, if applicable;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Customer permissions plan; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Project management plan.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="K.">
      <text>Good Small Generator Facility Cybersecurity Practice. A small generator facility’s cybersecurity shall be:</text>
      <paragraph num="(1)">
        <text>Designed;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Installed;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Maintained; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Operated to the extent reasonable and practical, in accordance with accepted industry standards and meet utility cybersecurity requirements</text>
      </paragraph>
    </paragraph>
    <paragraph num="L.">
      <text>Witness Test of Small Generator Facility.</text>
      <paragraph num="(1)">
        <text>The utility shall have the option of performing a witness test after construction of the small generator facility is completed.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The applicant shall provide the utility at least 5 business days notice of the planned commissioning test for the small generator facility.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If the utility elects to perform a witness test, the utility shall contact the applicant to schedule the witness test at a mutually agreeable time within 10 business days of the scheduled commissioning test.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>If the utility does not perform the witness test within 10 business days of the commissioning test, the witness test is considered waived unless the utility and applicant agree to extend the time for conducting the witness test.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>If the results of the witness test are not acceptable to the utility, the applicant shall address and resolve any deficiencies within 30 calendar days, which may be extended upon the request of the applicant prior to the expiration of the 30-calendar-day period. A request for extension may not be unreasonably denied by the utility.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>If the applicant fails to address and resolve the deficiencies to the satisfaction of the utility, the interconnection request shall be considered withdrawn.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>If a witness test is not performed by the utility or an entity approved by the utility, the applicant shall satisfy the interconnection test specifications and requirements specified in Section 8 of IEEE Standard 1547.1-2020.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>For interconnection equipment that has not been certified or approved under Regulation .07 of this chapter, the witness test may also include the verification by the utility specified in Section 8 of IEEE Standard 1547.1-2020.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>All tests verified by the utility shall be performed in accordance with the test procedures specified in Section 8 of IEEE Standard 1547.1-2020.</text>
      </paragraph>
      <paragraph num="(10)">
        <text>The applicant shall, if requested by the utility, provide a copy of all documentation in its possession regarding testing conducted under  Section 8 of IEEE Standard 1547.1-2020.</text>
      </paragraph>
      <paragraph num="(11)">
        <text>The applicant shall demonstrate that it meets the smart inverter requirements of §O of this regulation, if applicable.</text>
      </paragraph>
    </paragraph>
    <paragraph num="M.">
      <text>Interconnection Studies and Applicant Information.</text>
      <paragraph num="(1)">
        <text>If requested by the applicant, the utility shall provide the applicant copies of any interconnection studies performed in analyzing an interconnection request.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An applicant may provide any other prospective applicant copies of interconnection studies to aid in streamlining a future utility review.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Queue position for all small generator facilities shall be prioritized based on the date the interconnection request is submitted.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Each utility shall publicly and electronically provide an interconnection queue, updated monthly, that includes the following information about each interconnection request for any small generator facility with a nameplate capacity greater than 500 kW:</text>
        <paragraph num="(a)">
          <text>Size (MW or kW);</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Proposed circuit number and substation;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>County and zip code;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Interconnection request received date;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Queue position on the system’s proposed circuit number and substation;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Review status;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Interconnection request approved date; and</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Any other information requested by the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>A small generator facility shall remain on the list for at least 3 years after the interconnection request was approved by the utility, unless subsequently cancelled or removed from the interconnection queue pursuant to §N of this regulation.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>A utility may provide any additional information to a prospective applicant if the utility determines that doing so would streamline the utility’s review of an interconnection request.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>A utility has no obligation to provide any prospective applicant any information regarding prior interconnection requests, including a prior applicant's name, copies of prior interconnection studies performed by the utility, or any other information regarding a prior applicant or request.</text>
      </paragraph>
    </paragraph>
    <paragraph num="N.">
      <text>Validity of Conditional Approval.</text>
      <paragraph num="(1)">
        <text>A project participating as a community solar energy generating system under COMAR 20.62 is not subject to this section.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The notice of conditional approval shall clearly identify the applicable deadline and the consequences of failing to either deliver the certification of completion or request an extension by the deadline.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Once the utility delivers notice of conditional approval to the applicant, the applicant shall deliver the certification of completion within the following time frames:</text>
        <paragraph num="(a)">
          <text>For an application for a small generator facility with a nameplate capacity smaller than or equal to 100 kW, the applicant:</text>
          <paragraph num="(i)">
            <text>Shall deliver the certification of completion within 6 months;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Shall receive a 6-month extension of the specified deadline, upon request; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>May receive one or more additional extensions of at least 6 months upon good cause shown after an initial 6-month extension; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>For an application for a small generator facility with a nameplate capacity larger than 100 kW, the applicant:</text>
          <paragraph num="(i)">
            <text>Shall deliver the certification of completion within 12 months;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Shall receive a 6-month extension of the specified deadline, upon request; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>May receive one or more additional extensions of at least 6 months upon good cause shown after an initial 6-month extension.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>A project participating in the Community Solar pilot program under COMAR 20.62 is not subject to this section.</text>
      </paragraph>
    </paragraph>
    <paragraph num="O.">
      <text>Smart Inverters.</text>
      <paragraph num="(1)">
        <text>After January 1, 2024, any small generator facility requiring an inverter that submits an interconnection request shall use a smart inverter with either a default or a site-specific utility required inverter settings profile, as determined by a utility.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Any small generator facility may replace an existing inverter with a similar spare inverter that was purchased prior to January 1, 2024, for use at the small generator facility. This requirement does not apply to inverter replacements conducted under manufacturer warranty.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Prior to January 1, 2024, all utilities will establish default utility required inverter settings profiles for smart inverters pursuant to §O(5) of this regulation. A utility with a total number of less than 150,000 customers served in Maryland may use a Statewide utility required inverter settings profile as their default utility required inverter settings profile.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>To the extent reasonable, pursuant to any modifications required by §O(5) of this regulation, all utility required inverter setting profiles shall be consistent with applicable smart inverter recommendations from PJM Interconnection, LLC that are applicable.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>A default utility required inverter settings profile shall be established by a utility to optimize the safe and reliable operation of the electric distribution system, and shall serve the following objectives:</text>
        <paragraph num="(a)">
          <text>The primary objective is to incur no involuntary real power inverter curtailments incurred during normal operating conditions and minimal real power involuntary curtailments during abnormal operating conditions.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The secondary objective is to enhance electric distribution system hosting capacity and to optimize the provision of grid support services.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>A site-specific utility required inverter settings profile may be established by a utility as necessary to optimally meet the objectives established in §O(5) of this regulation.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>All default and site-specific utility required inverter settings profiles shall be documented in interconnection agreements.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>A default utility required inverter settings profile shall be published on the utility’s website.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>A utility with a total number of 150,000 or more customers served in Maryland shall:</text>
        <paragraph num="(a)">
          <text>File an initial default utility required inverter settings profile with the Commission for approval by October 1, 2023 to be effective by January 1, 2024.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>File any changes to its established default utility required inverter settings profile with the Commission for approval.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(10)">
        <text>Commission Staff shall file any changes to the established statewide utility required inverter settings profile with the Commission for approval.</text>
      </paragraph>
      <paragraph num="(11)">
        <text>A utility required inverter settings profile or statewide utility required inverter settings profile shall be deemed approved within 90 days upon filing, unless directed otherwise by the Commission.</text>
      </paragraph>
    </paragraph>
    <paragraph num="P.">
      <text>Flexible Interconnection Options.</text>
      <paragraph num="(1)">
        <text>Utilities shall approve interconnection requests while considering flexible interconnection options under a limited export agreement or, for inadvertent export, net system capacity and a proposed use subject to the requirements of this section.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Inadvertent Export for Energy Storage Devices.</text>
        <paragraph num="(a)">
          <text>Small generator facilities using Level 3 interconnection requests are non-exporting systems and are not allowed to utilize inadvertent exports.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A utility may not approve an inadvertent export option if the interconnection customer lacks the appropriate standardized controls to ensure that the small generator facility operates as agreed upon in interconnection agreements.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Small generator facilities may inadvertently export power of a magnitude and duration as evaluated and allowed by the utility and as specified in their interconnection agreement. Thirty seconds shall be used as a default inadvertent export duration unless the utility determines that this level duration violates utility evaluation criteria.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>There are no limits on the number of times inadvertent exports occur in any given customer billing cycle.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Small generator facilities may not have total inadvertent exports greater than the generating facility nameplate capacity multiplied by 1 hour per customer in each billing cycle.</text>
        </paragraph>
        <paragraph num="(f)">
          <text>In the event that a small generator facility exceeds approved inadvertent export magnitude or duration limits, the small generator facility shall immediately cease to export power to the grid until acceptable output control has been reestablished.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Net System Capacity and Proposed Use.</text>
        <paragraph num="(a)">
          <text>An interconnection customer may request that its interconnection request be based on the proposed use of the small generator facility and the impact of its proposed use on net system capacity.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A utility may not approve a proposed use if the interconnection customer lacks the appropriate standardized controls to ensure that the small generator facility operates as agreed upon in interconnection agreements.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>In the event that a small generator facility exceeds the approved net system capacity for the proposed use, the small generator facility shall immediately cease to export power to the grid until acceptable output control has been reestablished.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Limited Export Agreements.</text>
        <paragraph num="(a)">
          <text>By January 1, 2025, a utility shall publish on its interconnection website a description of their limited export agreement policies and provide a process for interconnection customers to request these agreements to avoid the need for a hosting capacity upgrade project to accommodate an interconnection request, including the following:</text>
          <paragraph num="(i)">
            <text>Limited export agreements shall be made available upon request only to Level 2 and Level 4 interconnection customers;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Limited export agreement terms shall be mutually agreed upon between a utility and an interconnection customer for operating conditions as specified in the interconnection agreement or in a separate limited export interconnection customer agreement; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The method of implementation and control of the limited export agreement terms shall be mutually agreed upon between a utility and the interconnection customer and specified in the interconnection agreement or in a separate limited export interconnection customer agreement.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>A utility may not approve a limited export agreement if the interconnection customer lacks the appropriate standardized controls to ensure that the small generator facility operates as agreed upon in interconnection agreements.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>In the event that a small generator facility does not curtail and exceeds the approved limited export parameters stated in the interconnection agreement or a separate limited export interconnection customer agreement, the small generator facility shall immediately cease to export real power to the grid until acceptable output control has been reestablished.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>If required by the utility, the small generator facility shall be subject to a verification reporting plan to monitor the small generator facility’s compliance with any flexible interconnection option limits involving net system capacity, inadvertent export, proposed use, and limited export agreement requirements as documented in the interconnection agreement. A verification reporting plan may include periodic reports, online monitoring, or other verification methods, or it may be waived as agreed upon by the utility and interconnection customer.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Utilities may include a recurring administrative fee in utility tariffs as a term in flexible interconnection option agreements to reimburse the utility for estimated additional costs to administer these agreements and the stated limiting conditions.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Failure of a small generator facility to demonstrate compliance with the facility’s verification reporting plan may result in the suspension of utility approvals in this section until the small generator facility agrees and implements an acceptable corrective action plan with the utility within 30 calendar days of notification by the utility.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>A small generator facility shall cease to export power if it fails to provide an acceptable corrective action plan to the utility, pursuant to §P(7) of this regulation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="Q.">
      <text>Hosting Capacity.</text>
      <paragraph num="(1)">
        <text>Utilities shall establish hosting capacity policies subject to the following requirements:</text>
        <paragraph num="(a)">
          <text>A utility shall designate a circuit a closed circuit if there is no remaining hosting capacity.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A utility shall designate a circuit a restricted circuit if only reserve hosting capacity is available.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A utility shall determine the amount of reserve hosting capacity on a restricted circuit based on a circuit-specific assessment of distributed energy resource forecasts or other factors, including customer density, type of area served, and customer demographics of the circuit.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A utility may determine the aggregate generation of a small generator facility permitted to use an electric distribution circuit’s reserve hosting capacity and publish this information on their website.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A utility shall report their closed circuits, restricted circuits, and reserve hosting capacity in their hosting capacity reporting system.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>A utility may submit for the Commission’s review and approval a hosting capacity upgrade plan or multiple plans to address or otherwise increase the utility’s existing distribution aggregate circuit hosting capacity limits across the system, or in a specific area of an electric utility’s system, that are forecasted to be congested in the future if the utility’s forecast of distributed energy resource growth exceeds existing hosting capacity. These plans may be considered by the Commission if primary voltage hosting capacity upgrade fees, pursuant to §R of this regulation, exceed a threshold of the utility’s average cost per kilowatt for their aggregate customer funded hosting capacity upgrade projects completed in the previous year, unless good cause exists for a utility to request a waiver of this requirement.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Hosting capacity upgrade plans that are submitted by a utility shall include:</text>
        <paragraph num="(a)">
          <text>A description of the electric system areas to be included in the hosting capacity upgrade plan at the feeder and substation level;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A description of the assumptions used for establishing and prioritizing the area covered by the hosting capacity upgrade plan and associated forecasts and timeline for hosting capacity utilization;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A description of the assumptions used for modeling and establishing the cost of the hosting capacity upgrade plan;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>If the plan proposes that ratepayers bear any costs that would not be paid by future interconnection customers, a justification for the percentage cost allocation proposed between interconnection customers and ratepayers, including descriptions of:</text>
          <paragraph num="(i)">
            <text>How the proposed cost allocation was developed and what alternatives were considered, explaining and quantifying the benefits ratepayers are expected to receive from the upgrade; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>How the utility engaged with stakeholders, particularly the ratepayer advocate’s office, the Maryland Office of People’s Counsel, in the development of the utility’s cost allocation proposal;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>A description of the proposed cost allocation method in terms of dollars per kilowatt for a primary voltage hosting capacity fee for an interconnection customer;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>A description of the proposed cost allocation to ratepayers and the risks to ratepayers of unallocated hosting capacity upgrade costs if the hosting capacity upgrade does not become fully utilized; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>A proposal for utility cost recovery that describes how hosting capacity upgrade costs shall be offset by future utility revenues from interconnection customers.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>A utility shall have a procedure for calculating hosting capacity accounting for either gross peak or gross minimum loading based on good engineering practice.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The utility shall perform a representative sample of hosting capacity calculation validation checks at least annually, or more frequently in areas experiencing significant growth or distributed energy resource penetration. The hosting capacity calculation validation check frequency shall account for the utility's experience, good engineering practices, and judgment.</text>
      </paragraph>
    </paragraph>
    <paragraph num="R.">
      <text>Maryland Cost Allocation Method.</text>
      <paragraph num="(1)">
        <text>Within 1 year of the effective date of this regulation, electric utilities shall submit an electric utility service tariff for Commission approval for a primary voltage hosting capacity cost sharing and allocation methodology for interconnection customers, as follows:</text>
        <paragraph num="(a)">
          <text>The default hosting capacity cost sharing and allocation methodology for primary voltage interconnection customers shall be based on locational pricing to incentivize interconnection in areas with higher available hosting capacity and disincentivize interconnection in areas with lower available hosting capacity.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A utility may petition the Commission to implement a hosting capacity cost sharing and allocation methodology for primary voltage interconnection customers that is not locationally based for “good cause” in their tariff filing.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An interconnection request shall be eligible for hosting capacity cost sharing and allocation under this section unless they are exempted for the following reasons:</text>
          <paragraph num="(i)">
            <text>The interconnection request is subject to the PJM Interconnection, LLC Tariff;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The interconnection request is in an area with its cost allocation governed by a hosting capacity upgrade plan approved by the Commission;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The interconnection is on a dedicated primary voltage feeder that may not benefit any other interconnection customer;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>The interconnection is on a dedicated secondary voltage facility that may not benefit any other interconnection customer;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>The interconnection request is on an AC distribution grid or spot network; or</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>Other good cause as documented by the utility and reported, pursuant to Regulation .14 of this chapter.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(d)">
          <text>If an interconnection request is exempted, pursuant to §R(1)(c) of this regulation, the interconnection customer shall pay all interconnection costs as determined by the utility, unless the interconnection request is subject to the PJM Tariff or the interconnection request is in an area with its cost allocation governed by a hosting capacity upgrade plan approved by the Commission.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>If sufficient hosting capacity is not available at a point of interconnection for a primary voltage interconnection customer, an electric utility may propose a hosting capacity upgrade project to the interconnection customer or customers, as follows:</text>
          <paragraph num="(i)">
            <text>The utility shall charge the primary voltage interconnection customer a hosting capacity fee for its share of the primary voltage hosting capacity upgrade cost proportional to the interconnection customer’s utilization of hosting capacity.</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>If more than one interconnection request exists in the interconnection queue that shall benefit from the electric utility proposed hosting capacity upgrade project, these interconnection customers shall be clustered together for the purpose of calculating hosting capacity fees.</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Hosting capacity fees for clustered interconnection customers shall be calculated proportional to each interconnection customer’s utilization of the hosting capacity created by the hosting capacity upgrade project.</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>All hosting capacity upgrade costs in excess of hosting capacity fees collected shall be accumulated in a separate unallocated primary voltage hosting capacity upgrade cost account for future allocation to primary voltage interconnection customers.</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Unallocated hosting capacity upgrade costs for primary voltage interconnection customers shall be shared and allocated to other primary voltage interconnection customers using a primary voltage hosting capacity cost sharing and allocation methodology in an electric utility service tariff approved by the Commission.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Within 1 year of the effective date of this regulation, electric utilities shall submit an electric utility service tariff for Commission approval for a secondary voltage cost sharing and fee for both residential and commercial interconnection customers, as follows:</text>
        <paragraph num="(a)">
          <text>If sufficient hosting capacity is not available at a point of interconnection for a secondary voltage interconnection customer, an electric utility may construct a hosting capacity upgrade project for the interconnection customer or customers.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>All secondary voltage hosting capacity upgrade costs shall be accumulated in separate unallocated accounts for both residential and commercial secondary voltage interconnection customers for future allocation in hosting capacity fees.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Unallocated hosting capacity upgrade costs for both residential and commercial secondary voltage interconnection customers shall be shared and allocated to other secondary voltage interconnection customers using a hosting capacity cost sharing and allocation fee in an electric utility service tariff approved by the Commission.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Hosting capacity fees for primary voltage interconnection customers shall be reset using a cost sharing and allocation methodology approved by the Commission in an electric utility service tariff filing whenever a change in methodology is proposed, unless the fee is zero or the fee change is less than $1 per kilowatt.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Hosting capacity fees for secondary voltage interconnection customers shall be reset annually using a cost sharing and allocation methodology approved by the Commission unless the fee is zero or the fee change is less than $1 per kilowatt from the current fee in the electric utility’s service tariff.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>A utility may submit for Commission approval an administrative charge in its service tariff to recover its administrative costs for managing the cost sharing and allocation methodology for primary and secondary voltage interconnection customers.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>A utility shall describe all hosting capacity upgrade project rightsizing projects describing their forecasts, inputs, and assumptions in their next rate case to assist stakeholders in a prudency review.</text>
      </paragraph>
    </paragraph>
    <paragraph num="S.">
      <text>Vehicle to Grid Interconnection.</text>
      <paragraph num="(1)">
        <text>A V2G System shall meet the following requirements:</text>
        <paragraph num="(a)">
          <text>The interconnection customer for a V2G system shall submit an interconnection request pursuant to Regulation .04 of this chapter.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A V2G system interconnection shall be valid only at a single point of interconnection specified in the interconnection agreement. Additional locations shall require additional interconnection reviews and associated interconnection agreements.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An electric company shall consider a V2G system to be an energy storage device pursuant to Regulation .02B of this chapter for the purpose of evaluating the electrical performance requirements applicable to an interconnection request.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Characteristics of energy storage systems that do not and cannot apply to the use of EVs as connected energy storage units shall not be required of V2G systems operated as energy storage.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A V2G system shall not be authorized in bidirectional mode while in parallel operation with the local electric power system unless an interconnection agreement is in place between the interconnection customer and the relevant electric utility and the interconnection customer has received a permission to operate from the electric company.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>An electric company may delay interconnection of a V2G system to provide adequate time to ensure electric distribution system safety and reliability in advance of vehicle-to-grid interconnections pursuant to applicable requirements in Regulation .09 of this chapter for Level 1 Review, Regulation .10 of this chapter for a Level 2 Review, Regulation .11 of this chapter for a Level 3 Review, and Regulation .12 of this chapter for a Level 4 Review.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>To ensure safety, reliability and V2G functionality for DC EVSE V2G Systems, the interconnection agreement shall require adherence to UL 1741 incorporated by reference in COMAR 20.50.02.02(I).</text>
      </paragraph>
      <paragraph num="(4)">
        <text>To ensure safety, reliability and V2G functionality for AC EVSE V2G Systems there are two acceptable certification pathways for which only one certification pathway shall be required in an interconnection agreement:</text>
        <paragraph num="(a)">
          <text>Certification pathway 1 is as follows:</text>
          <paragraph num="(i)">
            <text>UL 1741 incorporated by reference in COMAR 20.50.02.02(I) and UL 2594 incorporated by reference in COMAR 20.50.02.02(N) for a V2G Ready EVSE; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>SAE J3072 incorporated by reference in COMAR 20.50.02.02(O) for a bidirectional electric vehicle.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>Certification pathway 2 is as follows:</text>
          <paragraph num="(i)">
            <text>UL 9741 incorporated by reference in COMAR 20.50.02.02(M) for V2G Ready EVSE; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>UL 1741 SB under the QIKP Grid Interconnection Performance Certification for a bidirectional electric vehicle and V2G Ready EVSE.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>If applicable, certifications pursuant to Regulation .06S(4) of this chapter are not available or safety, reliability, and V2G functionality cannot be ensured:</text>
        <paragraph num="(a)">
          <text>The utility may require reasonable alternative methods such as protective relaying equipment, a power control system, or other alternative methods in an interconnection agreement; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>If safety, reliability and V2G functionality cannot be ensured through certifications or reasonable alternative methods, an electric company shall deny the interconnection request.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>A V1G System shall meet the following requirements.</text>
        <paragraph num="(a)">
          <text>An interconnection request, interconnection agreement, and an electric company permission to operate is not required for a V1G Ready EVSE provided that the V1G Ready EVSE is configured to only allow V1G operation in compliance with relevant standards.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A V2G System that operates as a V1G Ready EVSE shall be accepted by an electric company using a method for notification form submittal as determined by the electric company. The notification form used by the electric company shall only require information required to attest to V1G operation and not duplicate an interconnection request.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A V1G Ready EVSE shall not be changed to a V2G Ready EVSE without first receiving an interconnection request and permission to operate from the utility.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Only the EVSE manufacturer or a manufacturer approved third party entity may reprogram or reconfigure an EVSE to bidirectional operation.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Certified and Approved Equipment.">
    <paragraph num="A.">
      <text>After January 1, 2024, any small generator facility inverter for which an interconnection request is submitted shall be deemed certified and approved if it meets the requirements of IEEE Standard 1547-2018 and UL Standard 1741-SB, except for inverters purchased pursuant to Regulation .06N(2) of this chapter.</text>
    </paragraph>
    <paragraph num="B.">
      <text>After January 1, 2024, any small generator facility shall be deemed approved if the interconnection equipment including interface components such as switchgear, multifunction relays, or other interface devices are compatible with the interconnection equipment, pursuant to witness test requirements pursuant to Regulation .06L of this chapter.</text>
    </paragraph>
    <paragraph num="C.">
      <text>An electric utility shall approve a meter collar adapter model for installation in its Maryland service area for specific compatible meter configurations and customer applications, provided that the meter collar adapter model meets the following criteria:</text>
      <paragraph num="(1)">
        <text>The meter collar adapter model is approved or listed by a nationally recognized testing laboratory;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The meter collar adapter model is approved for use in utility service areas, unless sufficient rational for disapproval is provided by an electric utility;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>All meter collar model installations, access, testing, inspections, servicing, and removals shall only be performed by a qualified person as agreed between the utility and the meter collar manufacturer;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The meter collar adapter model design does not impede access to the sealed meter socket compartment, or to the meter itself by a qualified person;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The meter collar adapter model is compatible with the National Electric Code; and</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The meter collar adapter model is compatible to the specific meter configurations and customer applications to ensure that the meter collar adapter is capable of being safely and reliably inserted into a meter socket to maintain a secure connection with both the meter socket and the utility meter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>An electric utility shall approve or disapprove a meter collar adapter model for installation in its service area no later than 90 days after a meter collar manufacturer submits a request for approval of the meter collar adapter, and a utility’s procedures shall be updated within 90 days of utility approval.</text>
    </paragraph>
    <paragraph num="E.">
      <text>An electric utility shall provide an explanation to the requesting meter collar manufacturer explaining the reasons any meter collar adapter model application was denied.</text>
    </paragraph>
    <paragraph num="F.">
      <text>A requesting meter collar adapter manufacturer may appeal the utility decision to the Commission using the dispute resolution process in Regulation .13 of this chapter.</text>
    </paragraph>
    <paragraph num="G.">
      <text>An electric utility shall provide public notice of all decisions approving a meter collar adapter model by posting the information on the utility’s website.</text>
    </paragraph>
    <paragraph num="H.">
      <text>An electric utility shall authorize the installation and operation of a utility-approved meter collar adapter for a customer installation, provided the meter collar adapter meets the following criteria:</text>
      <paragraph num="(1)">
        <text>The meter collar adapter is qualified to be connected to the supply side of the service disconnect, pursuant to the applicable provisions of the National Electric Code;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The meter collar adapter is rated for the meter socket into which it is intended to be installed;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The meter collar adapter does not exceed the weight bearing limits of a meter socket;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Multiple meter collar adapters are not stacked in a meter socket; and</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The meter collar adapter does not disable this excessive heating detection capability of AMI meters.</text>
      </paragraph>
    </paragraph>
    <paragraph num="I.">
      <text>A utility shall uninstall an approved meter collar adapter in the aggregate if any deficiencies are found after installation that result in safety or operational concerns, if these concerns cannot be remediated by a customer for a specific installation or by a meter collar adapter manufacturer, in the aggregate.</text>
    </paragraph>
    <paragraph num="J.">
      <text>The determination of violations in this regulation and the assessment of related civil penalties and corrective action plans shall be delegated to the Engineering Division.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Determination of Interconnection Jurisdiction and Level of Utility Review of Interconnection Request.">
    <paragraph num="A.">
      <text>A utility shall determine within 10 business days the interconnection jurisdiction pursuant to Regulation .01 of this chapter and the level of utility review required for an interconnection request based on nameplate capacity.</text>
    </paragraph>
    <paragraph num="B.">
      <text>A utility shall use a Level 1 procedure to evaluate an interconnection request to connect an inverter-based small generator facility when the small generator facility, or multiple small generator facilities interconnecting at a point of common coupling, has a nameplate capacity of 20kW or less.</text>
    </paragraph>
    <paragraph num="C.">
      <text>A utility shall use a Level 2 procedure to evaluate an interconnection request when:</text>
      <paragraph num="(1)">
        <text>The following criteria are met:</text>
        <paragraph num="(a)">
          <text>The small generation facility, or multiple small generator facilities interconnecting at a point of common coupling, has a nameplate capacity of 2 MW or less;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The interconnection equipment is lab-certified or field-approved; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The proposed interconnection is to a radial distribution circuit, or a spot network limited to serving one customer; or</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Alternatively, the small generator facility was reviewed under Level 1 review procedures but not approved, and the applicant has submitted a new interconnection request for consideration.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>A utility shall use a Level 3 procedure to evaluate an interconnection request to area networks and radial distribution circuits when electric power is not exported to the electric distribution system based on the following criteria:</text>
      <paragraph num="(1)">
        <text>For interconnection requests to the load side of an area network:</text>
        <paragraph num="(a)">
          <text>The nameplate capacity of the small generator facility, or multiple small generator facilities interconnecting at a point of common coupling, is less than or equal to 50 kW;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The proposed small generator facility utilizes a lab-certified inverter-based equipment package;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The small generator facility utilizes reverse power relays, other protection functions, or both, that prevent the export of power into the area network;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The aggregate generation on the area network does not exceed the smaller of 5 percent of an area network's maximum load or 50 kW; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Construction of facilities by the electric distribution company is not required to accommodate the small generator facility; or</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>For interconnection requests to a radial distribution circuit:</text>
        <paragraph num="(a)">
          <text>The small generator facility has a nameplate capacity of 10 MW or less;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The aggregate generation on the circuit, including the proposed small generator facility, is 10 MW or less;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The small generator facility will use reverse power relays or other protection functions that prevent power flow onto the electric distribution system;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The small generator facility is not served by a shared transformer; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Construction of facilities by the utility on its own electric distribution system is not required to accommodate the small generator facility.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>A utility shall use the Level 4 procedures for evaluating interconnection requests if:</text>
      <paragraph num="(1)">
        <text>The interconnection request cannot be approved under a Level 1, Level 2, or Level 3 review, and the applicant has submitted an interconnection request for consideration under a Level 4 study review; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The interconnection request does not meet the criteria for qualifying for a review under Level 1, Level 2, or Level 3 review procedures.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".09" heading="Level 1 Review.">
    <paragraph num="A.">
      <text>The utility shall evaluate a Level 1 small generator facility for the potential for adverse system impacts using net system capacity, pursuant to Regulation .06A and B of this chapter, unless nameplate capacity is specifically required using the following:</text>
      <paragraph num="(1)">
        <text>For interconnection of a proposed small generator facility:</text>
        <paragraph num="(a)">
          <text>To a radial distribution circuit, the aggregate generation on the circuit, including the proposed small generator facility, may not exceed 15 percent of the line section annual peak load as most recently measured at the substation or calculated for the line section; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>To a spot network:</text>
          <paragraph num="(i)">
            <text>On the load side of spot network protectors, the proposed small generator facility shall utilize an inverter-based equipment package;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The interconnection equipment proposed for the small generator facility is lab-certified; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The aggregate generation of all interconnected small generator facilities may not exceed 5 percent of the spot network's maximum load if the spot network serves more than one customer;</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>When a proposed small generator facility is to be interconnected on a single-phase shared secondary line, the aggregate generation on the shared secondary line, including the proposed small generator facility, may not exceed 20 kW;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>When a proposed small generator facility is single-phase and is to be interconnected on a center tap neutral of a 240 volt service, its addition may not create an imbalance between the two sides of the 240 volt service of more than 20 percent of the nameplate rating of the service transformer;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>As an alternative non-mandatory method to evaluate the adverse system impacts of a proposed Level 1 small generator facility on the distribution system, as described in §A(1)—(3) of this regulation, or as a mandatory next step prior to rejecting an interconnection request, pursuant to §E of this regulation, for Level 1 Review Failure, a utility may use a power-flow based analysis system with modeling of IEEE 1547-2018 inverter capabilities as follows, if its use may change the analysis result as determined by the utility:</text>
        <paragraph num="(a)">
          <text>For primary voltage systems, within 6 months of the effective date of this regulation; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>For secondary voltage systems, within 2 years of the effective date of this regulation;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Modification or construction of additional interconnection facilities by the utility on its distribution system, except for metering or a minor system modification, is not required to accommodate the small generator facility; and</text>
      </paragraph>
      <paragraph num="(6)">
        <text>If the proposed interconnection requires a minor system modification, the utility shall notify the applicant of that requirement when it provides the Level 1 evaluation result, as follows:</text>
        <paragraph num="(a)">
          <text>The applicant shall inform the utility within 10 business days if the applicant elects to continue the application;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>If the applicant makes such an election, the utility shall provide an interconnection agreement, along with a non-binding good faith cost estimate and construction schedule for those upgrades, to the applicant within 30 calendar days after the utility receives such an election; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The applicant shall have 30 calendar days, or other mutually agreeable time frame after receipt of the interconnection agreement, to sign and return such agreement.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The utility in conducting a Level 1 interconnection review shall:</text>
      <paragraph num="(1)">
        <text>Within 5 business days after receipt of the interconnection request, inform the applicant that the interconnection request is:</text>
        <paragraph num="(a)">
          <text>Complete; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Incomplete and what materials are missing; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Within 15 business days after the utility notifies the applicant that the application is complete under §B(1) of this regulation, verify that the small generator facility can be interconnected safely and reliably under §A of this regulation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Unless the utility determines and demonstrates that a small generator facility cannot be interconnected safely or reliably to its electric distribution system, the utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
      <paragraph num="(1)">
        <text>The small generator facility has been approved by local or municipal electric code officials with jurisdiction over the interconnection;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A certificate of completion has been returned to the utility;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The witness test has been successfully completed or waived by the utility; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The applicant has signed an interconnection agreement.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>If an applicant does not sign the interconnection agreement within 30 calendar days after receipt from the utility, the interconnection request is considered withdrawn unless the applicant requests to have the deadline extended. A request for extension may not be unreasonably denied by the utility.</text>
    </paragraph>
    <paragraph num="E.">
      <text>Level 1 Review Failure.</text>
      <paragraph num="(1)">
        <text>If the small generator facility is not approved under a Level 1 review, the utility shall provide the applicant a letter explaining its reasons for denying the interconnection request.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If a small generator facility fails a Level 1 review, the utility may approve the interconnection request if the small generator facility can be interconnected safely and reliably to the utility’s electric distribution system.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>When a small generator facility is not approved under a Level 1 review, the applicant may submit a new interconnection request for consideration under Level 2, Level 3, or Level 4 procedures.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".10" heading="Level 2 Review.">
    <paragraph num="A.">
      <text>The utility shall evaluate a Level 2 small generator facility for the potential for adverse system impacts using net system capacity, pursuant to Regulation .06A and B of this chapter, unless nameplate capacity is specifically required using the following:</text>
      <paragraph num="(1)">
        <text>For interconnection of a proposed small generator facility:</text>
        <paragraph num="(a)">
          <text>To a radial distribution circuit, the aggregate generation on the circuit, including the proposed small generator facility, may not exceed 15 percent of the line section annual peak load most recently measured at the substation or calculated for the line section; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>To a spot network:</text>
          <paragraph num="(i)">
            <text>When the interconnection of a proposed small generator facility is to the load side of spot network protectors, the proposed small generator facility shall utilize an inverter-based equipment package;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The applicant's interconnection equipment proposed for the small generator facility shall be lab-certified or field-approved; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A small generator facility, when aggregated with other generation, the aggregate generation on the spot network, may not exceed 5 percent of a spot network's maximum load if the spot network serves more than one customer;</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>For fault current limitations:</text>
        <paragraph num="(a)">
          <text>The nameplate capacity of the proposed small generator facility, in aggregation with other generation and energy storage devices on the distribution circuit, may not contribute more than 10 percent to the electric distribution circuit's maximum fault current at the point on the primary line nearest the point of interconnection;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The nameplate capacity of the proposed small generator facility, in aggregation with other generation and energy storage devices on the distribution circuit, may not cause any distribution protective devices and equipment including substation breakers, fuse cutouts, and line reclosers, or other customer equipment on the electric distribution system to be exposed to fault currents exceeding 90 percent of the short circuit interrupting capability; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The interconnection request may not request interconnection on a circuit that already exceeds 90 percent of the short circuit interrupting capability;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The proposed small generator facility's point of interconnection may not be on a transmission line;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>When a small generator facility is to be connected to 3-phase, 3-wire primary utility distribution lines, a 3-phase or single-phase generator shall be connected phase-to-phase;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>When a small generator facility is to be connected to 3-phase, 4-wire primary utility distribution lines, a 3-phase or single-phase generator will be connected line-to-neutral and will be effectively grounded;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>When the proposed small generator facility is to be interconnected on single-phase shared secondary line, the aggregate generation on the shared secondary line, including the proposed small generator facility, may not exceed 20 kW;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>When a proposed small generator facility is single-phase and is to be interconnected on a center tap neutral of a 240 volt service, its addition may not create an imbalance between the two sides of the 240 volt service of more than 20 percent of the nameplate rating of the service transformer;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>A small generator facility, in aggregate with other generation and energy storage devices interconnected to the distribution side of a substation transformer feeding the circuit where the small generator facility proposes to interconnect, the aggregate generation may not exceed 10 MW in an area where there are known or posted transient stability limitations to generating units located in the general electrical vicinity;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>As an alternative non-mandatory method to evaluate the adverse system impacts of a proposed Level 2 small generator facility on the distribution system, as described in §A(1)—(8) of this regulation, or as a mandatory next step prior to rejecting an interconnection request, pursuant to §F of this regulation, for Level 2 Review Failure, a utility may use a power-flow based analysis system with modeling of IEEE 1547-2018 inverter capabilities as follows, if its use may change the analysis result as determined by the utility:</text>
        <paragraph num="(a)">
          <text>For primary voltage systems, within 6 months of the effective date of this regulation; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>For secondary voltage systems, within 2 years of the effective date of this regulation;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(10)">
        <text>Except as permitted by an additional review in §G of this regulation, no modification or construction of additional facilities by a utility of its distribution system, with the exception of metering or a minor system modification, shall be required to accommodate the small generator facility; and</text>
      </paragraph>
      <paragraph num="(11)">
        <text>If the proposed interconnection facility requires a site-specific utility required inverter settings profile review or a minor system modification without further study review needed, the utility shall notify the applicant of that requirement when it provides the Level 2 evaluation result, as follows:</text>
        <paragraph num="(a)">
          <text>The applicant must inform the utility within 10 business days if the applicant elects to continue the application;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>If the applicant makes such an election, the utility shall provide an interconnection agreement, along with a non-binding good faith cost estimate and construction schedule for any minor system modifications to the applicant within 30 calendar days after the utility receives such an election; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The applicant shall have 30 calendar days, or other mutually agreeable time frame after receipt of the interconnection agreement, to sign and return such agreement.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>A utility shall, within 5 business days after receipt of the interconnection request, inform the applicant that the interconnection request is:</text>
      <paragraph num="(1)">
        <text>Complete; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Incomplete and what materials are missing;</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Queue Position.</text>
      <paragraph num="(1)">
        <text>When an interconnection request is complete, the utility shall assign a queue position.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The queue position of the interconnection request shall be used to determine the potential adverse system impact of the small generator facility based on the relevant screening criteria.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The utility shall notify the applicant of any other higher queue position applicants on the same line section or spot network for which interconnection is sought.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Queue position may not be forfeited or otherwise impacted by the submission of a dispute under the provisions of Regulation .13 of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>When a utility determines additional information is required to complete an evaluation:</text>
      <paragraph num="(1)">
        <text>The utility shall request the information;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The time necessary to complete the evaluation may be extended, but only to the extent of the delay required for receipt of the additional information; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>When additional information is required, the utility may not revert to the start of the review process or alter the applicant's queue position.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Within 20 business days after the utility notifies the applicant it has received a completed interconnection request, the utility shall:</text>
      <paragraph num="(1)">
        <text>Evaluate the interconnection request using the Level 2 screening criteria;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Review the applicant's analysis, if provided by applicant, using the same criteria;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Provide the applicant with the utility's evaluation, including a comparison of the results of its own analyses with those of applicant, if applicable; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>When a utility does not have a record of receipt of the interconnection request and the applicant can demonstrate that the original interconnection request was delivered, expedite its review to complete the evaluation of the interconnection request within 20 business days.</text>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Failure to Meet Level 2 Criteria.</text>
      <paragraph num="(1)">
        <text>Additional review may be appropriate when a small generator facility has failed to meet one or more of the Level 2 criteria of §A of this regulation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A utility shall:</text>
        <paragraph num="(a)">
          <text>Within 30 calendar days, offer to perform additional review to determine whether minor system modifications or a site-specific utility required inverter settings profile would enable the interconnection to be made consistent with safety, reliability, and power quality criteria;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Provide the applicant with a nonbinding, good faith estimate of the costs of the additional review and minor system modifications; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Advise the applicant if a limited export customer agreement could be used to facilitate reliable and safe interconnection to the electric distribution system.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The utility shall undertake the additional review only if the applicant agrees within 10 business days to pay for the cost of the review, which may be extended at the request of the applicant. A request for extension may not be unreasonably denied by the utility.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>If the review identifies the need for modifications to the distribution system, the utility shall make the necessary modifications only if the interconnection customer agrees to pay for the cost of the modifications.</text>
      </paragraph>
    </paragraph>
    <paragraph num="G.">
      <text>Interconnection Agreement.</text>
      <paragraph num="(1)">
        <text>When a utility determines that the interconnection request passes the Level 2 screening criteria, or fails one or more of the Level 2 screening criteria but determines that the small generator facility can be interconnected safely and reliably, the utility shall provide the applicant an interconnection agreement within 5 business days after the determination.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The applicant shall have either 30 calendar days, or another mutually agreeable time frame after receipt of the interconnection agreement, to sign and return the interconnection agreement.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If the applicant does not sign the interconnection agreement within 30 calendar days, the request shall be considered withdrawn unless the applicant and utility mutually agree to extend the time period for executing the interconnection agreement prior to the expiration of the 30-calendar-day calendar period. A request for extension may not be unreasonably denied by the utility.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>After the interconnection agreement is signed by the applicant and utility, interconnection of the small generator facility shall proceed according to any milestones agreed to by the applicant and utility in the interconnection agreement.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
        <paragraph num="(a)">
          <text>All milestones agreed to in the interconnection agreement are satisfied;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The small generator facility is approved by electric code officials with jurisdiction over the interconnection;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The applicant provides a certificate of completion to the utility;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Upon request of the utility, the applicant provides one or more photographs of the small generator facility site location, components, metering equipment, and other related facilities and equipment; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>There is a successful completion of the witness test, if conducted by the utility.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="H.">
      <text>Level 2 Review Failure.</text>
      <paragraph num="(1)">
        <text>If the small generator facility is not approved under a Level 2 review, the utility shall provide the applicant written notification explaining its reasons for denying the interconnection request.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The applicant may submit a new interconnection request for consideration under a Level 3 or Level 4 interconnection review; however, the queue position assigned to the Level 2 interconnection request shall be retained provided the request is made within 15 business days of notification that the current Level 2 interconnection request is denied.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".11" heading="Level 3 Review.">
    <paragraph num="A.">
      <text>The utility shall use the Level 3 review procedure for an interconnection request that meets the Level 3 criteria in Regulation .08 of this chapter.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Queue Position.</text>
      <paragraph num="(1)">
        <text>Once the interconnection request is considered complete by the utility, the utility shall assign a queue position based upon the date and time the interconnection request is determined to be complete.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The queue position of each interconnection request shall be used to determine the potential adverse system impact of the small generator facility based on the relevant screening criteria.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The utility shall notify the applicant of any other higher queue position applicants on the same radial line or area network that the applicant is seeking to interconnect to.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Queue position may not be forfeited or otherwise impacted by any pending dispute submitted under the provisions of Regulation .13 of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Interconnection requests meeting the requirements set forth in Regulation .08 of this chapter for nonexporting small generator facilities interconnecting to an area network shall be presumed by the utility to be appropriate for interconnection. The utility shall process the interconnection request to area networks using the following procedures:</text>
      <paragraph num="(1)">
        <text>The utility shall evaluate the interconnection request under Level 2 interconnection review procedures as set forth in Regulation .10 of this chapter, except that the utility shall have 25 business days to conduct an area network impact study to determine any potential adverse system impact of interconnecting to the utility's area network;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If the area network impact study identifies potential adverse system impacts, the utility may determine at its sole discretion that it is inappropriate for the small generator facility to interconnect to the area network, in which case the interconnection request shall be denied; however, the applicant may elect to submit a new interconnection request for consideration under Level 4 procedures, in which case the queue position assigned to the Level 3 interconnection request will be retained provided the request is made within 15 business days of notification that the current application is denied;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The utility shall conduct the area network impact study at its own expense; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>In the event the utility denies the interconnection request, the utility shall provide the applicant with a copy of its area network impact study and written justification for denying the interconnection request.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>When an interconnection request meets the requirements of Regulation .08 of this chapter for nonexporting small generator facilities interconnecting to a radial distribution circuit, the utility shall:</text>
      <paragraph num="(1)">
        <text>Evaluate the interconnection request using the Level 2 review in Regulation .10 of this chapter; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Approve the interconnection request if all of the applicable Level 2 screens are satisfied, except that the peak line section value indicated in Regulation .10A(1)(a) shall be 25 percent instead of 15 percent.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Interconnection Agreement.</text>
      <paragraph num="(1)">
        <text>If a small generator facility satisfies the criteria in §C or D of this regulation, the utility shall approve the interconnection request and provide an interconnection agreement for the applicant to sign.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The applicant shall have 30 calendar days, or other mutually agreeable time frame after receipt of the interconnection agreement, to sign and return the interconnection agreement.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If the applicant does not sign the interconnection agreement within 30 calendar days, the interconnection request shall be considered withdrawn unless the applicant and utility mutually agree to extend the time period for executing the interconnection agreement prior to the expiration of the 30-calendar-day period. A request for extension may not be unreasonably denied by the utility.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>After the interconnection agreement is signed by the applicant and utility, interconnection of the small generator facility shall proceed according to any milestones agreed to by the applicant and utility in the interconnection agreement.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
        <paragraph num="(a)">
          <text>All milestones agreed to in the interconnection agreement are satisfied;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The small generator facility is approved by electric code officials with jurisdiction over the interconnection;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The applicant provides a certificate of completion to the utility;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Upon request of the utility, the applicant provides one or more photographs of the small generator facility site location, components, metering equipment, and other related facilities and equipment; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>There is a successful completion of the witness test, if conducted by the utility.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Level 3 Review Failure.</text>
      <paragraph num="(1)">
        <text>If the small generator facility is not approved under a Level 3 review, the utility shall provide the applicant written notification explaining its reasons for denying the interconnection request.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If the small generator facility is not approved under a Level 3 review, the applicant may submit a new interconnection request for consideration under the Level 4 procedures; however, the queue position assigned to the Level 3 interconnection request shall be retained provided the request is submitted within 15 business days of the notice that the current Level 3 request was not approved.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".12" heading="Level 4 Study Review.">
    <paragraph num="A.">
      <text>A utility shall use the Level 4 study review procedure for an interconnection request that meets the Level 4 criteria in Regulation .08 of this chapter.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Interconnection Request.</text>
      <paragraph num="(1)">
        <text>Within 5 business days from receipt of an interconnection request, the utility shall notify the applicant whether the request is</text>
        <paragraph num="(a)">
          <text>Complete; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Incomplete.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>If the interconnection request is not complete:</text>
        <paragraph num="(a)">
          <text>The utility shall provide the applicant a written list detailing information that shall be provided to complete the interconnection request;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The applicant shall have 10 business days, which may be extended at the request of the applicant and not unreasonably denied by the utility, to provide appropriate data in order to complete the interconnection request, or the interconnection request shall be considered withdrawn; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The interconnection request shall be considered complete:</text>
          <paragraph num="(i)">
            <text>If the required information has been provided by the applicant; or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The utility and applicant have agreed that the applicant may provide additional information at a later time.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Queue Position.</text>
      <paragraph num="(1)">
        <text>When an interconnection request is complete, the utility shall assign a queue position.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The utility shall use the queue position of an interconnection request to determine the cost responsibility necessary for the facilities to accommodate the interconnection.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The utility shall notify the applicant of other higher-queued applicants on the same line section of the new interconnection request.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Any required interconnection studies may not begin until the utility has completed its review of all other interconnection requests that have a higher queue position.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Queue position is not forfeited or otherwise impacted by any pending dispute submitted under the provisions of Regulation .13 of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Scoping Meeting.</text>
      <paragraph num="(1)">
        <text>By mutual agreement of the utility and applicant, the scoping meeting may be waived and the interconnection feasibility study, interconnection impact study, or interconnection facilities studies provided for in a Level 4 review and discussed in this section may be waived or combined.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If agreed to by the utility and applicant, a scoping meeting shall be held within 10 business days, or other mutually agreed to time, after the utility has notified the applicant that the interconnection request is considered complete, or the applicant has requested that its interconnection request proceed after failing the requirements of a Level 2 review or Level 3 review.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The purpose of the meeting is to review the interconnection request, existing studies relevant to the interconnection request, and the results of the Level 1, Level 2, or Level 3 screening criteria.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>If the utility and applicant agree at a scoping meeting that an interconnection feasibility study shall be performed, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
        <paragraph num="(a)">
          <text>An interconnection feasibility study agreement;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An outline of the scope of the study; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>If the applicant and utility agree at a scoping meeting that an interconnection feasibility study is not required, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
        <paragraph num="(a)">
          <text>An interconnection system impact study agreement;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An outline of the scope of the study; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>If the utility and applicant agree at the scoping meeting that an interconnection feasibility study and system impact study are not required, the utility shall provide to the applicant, not later than 5 business days after the scoping meeting:</text>
        <paragraph num="(a)">
          <text>An interconnection facilities study agreement;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An outline of the scope of the study; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A nonbinding, good faith estimate of the cost to perform the study.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Interconnection Feasibility, Interconnection System Impact, and Interconnection Facilities Studies.</text>
      <paragraph num="(1)">
        <text>Interconnection Feasibility Study.</text>
        <paragraph num="(a)">
          <text>An interconnection feasibility study shall include any necessary analyses for the purpose of identifying a potential adverse system impact to the utility's electric distribution system that would result from the interconnection from among the following:</text>
          <paragraph num="(i)">
            <text>Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Initial identification of any thermal overload or voltage limit violations resulting from the interconnection;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Initial review of grounding requirements and system protection; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Description and nonbinding estimated cost of facilities required to interconnect the small generator facility to the utility's electric distribution system in a safe and reliable manner.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>If an applicant requests that the interconnection feasibility study evaluate multiple potential points of interconnection, additional evaluations may be required. Additional evaluations shall be conducted at the expense of the applicant.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>An interconnection system impact study is not required if the interconnection feasibility study concludes there is no adverse system impact, or if the study identifies an adverse system impact and the utility is able to identify a remedy without the need for an interconnection system impact study.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The utility and applicant shall use an interconnection feasibility study agreement form.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The utility shall avoid duplicating previously conducted interconnection studies to the extent possible.</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The utility may require a study deposit of the lesser of 100 percent of estimated nonbinding good faith study costs or $1,000.</text>
        </paragraph>
        <paragraph num="(g)">
          <text>The interconnection feasibility study shall be completed and the results shall be transmitted to the interconnection customer within 30 calendar days after the interconnection feasibility study agreement is signed by the parties.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Interconnection System Impact Study.</text>
        <paragraph num="(a)">
          <text>A distribution interconnection system impact study shall be performed when a potential distribution system adverse system impact is identified in the interconnection feasibility study.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Scope of Interconnection System Impact Study.</text>
          <paragraph num="(i)">
            <text>An interconnection system impact study shall evaluate the impact of the proposed interconnection on both the safety and reliability of the utility's electric distribution system.</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The interconnection system impact study shall identify and detail the system impacts that result when a small generator facility is interconnected without project or system modifications, focusing on the adverse system impacts identified in the interconnection feasibility study, or potential impacts including those identified in the scoping meeting.</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The interconnection system impact study shall consider all small generator facilities that, on the date the interconnection system impact study is commenced, are directly interconnected with the utility's electric distribution system, have a pending higher queue position to interconnect to the system, or have signed an interconnection agreement.</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>As part of its impact study, the utility shall agree to evaluate and consider any separate studies prepared by the applicant that evaluate alternatives for interconnecting the small generator facility, including the applicant's assessment of potential impacts of the small generator facility on the electric distribution system.</text>
          </paragraph>
          <paragraph num="(v)">
            <text>The utility shall provide the applicant with the utility's final impact study evaluation, including a comparison of the results of its own analyses with those provided by the applicant.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>Within 5 business days of transmittal of the interconnection feasibility study report, the utility shall send the applicant:</text>
          <paragraph num="(i)">
            <text>An interconnection system impact study agreement using a form;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>An outline of the scope of the interconnection system impact study; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A good faith estimate of the cost to perform the study.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(d)">
          <text>The interconnection system impact study shall include any necessary elements from among the following:</text>
          <paragraph num="(i)">
            <text>A load flow study;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Identification of affected systems;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>An analysis of equipment interrupting ratings;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>A protection coordination study;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Voltage drop and flicker studies;</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>Protection and set point coordination studies;</text>
          </paragraph>
          <paragraph num="(vii)">
            <text>Grounding reviews; and</text>
          </paragraph>
          <paragraph num="(viii)">
            <text>Impact on system operation.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>An interconnection system impact study shall consider any necessary criteria from among the following:</text>
          <paragraph num="(i)">
            <text>A short circuit analysis;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>A stability analysis;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Alternatives for mitigating adverse system impacts on affected systems;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Voltage drop and flicker studies;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Protection and set point coordination studies; and</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>Grounding reviews.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(f)">
          <text>The final interconnection system impact study shall provide the following:</text>
          <paragraph num="(i)">
            <text>The underlying assumptions of the study;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The results of the analyses;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A list of any potential impediments to providing the requested interconnection service;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Required distribution upgrades; and</text>
          </paragraph>
          <paragraph num="(v)">
            <text>A nonbinding good faith estimate of cost and time to construct any required distribution upgrades.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(g)">
          <text>The utility may require a study deposit of the lesser of 50 percent of estimated nonbinding good faith study costs or $3,000.</text>
        </paragraph>
        <paragraph num="(h)">
          <text>The interconnection system impact study, if required, shall be completed and the results transmitted to the interconnection customer within 45 calendar days after the interconnection system impact study agreement is signed by the parties.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Interconnection Facilities Study.</text>
        <paragraph num="(a)">
          <text>Within 5 business days of completion of the interconnection system impact study, the utility shall provide to the applicant:</text>
          <paragraph num="(i)">
            <text>A report of the interconnection system impact study;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>An interconnection facilities study agreement;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>An outline of the scope of the interconnection facilities study; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>A nonbinding good faith estimate of the cost to perform the facilities study.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>The interconnection facilities study shall identify:</text>
          <paragraph num="(i)">
            <text>The electrical switching configuration of the equipment, including transformer, switchgear, meters, and other station equipment;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The nature and estimated cost of the utility's interconnection facilities and distribution upgrades necessary to accomplish the interconnection, including engineering, procurement, construction, and overhead; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>An estimate of the time required to complete the construction and installation of the facilities.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>Third-Party Design or Construction of Interconnection Facilities.</text>
          <paragraph num="(i)">
            <text>The applicant and utility may agree to permit an applicant to separately arrange for a third party to design and construct the required interconnection facilities.</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The utility may review and approve the design of the facilities under the interconnection facilities study agreement.</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>If the applicant and utility agree to separately arrange for design and construction, the utility, consistent with security and confidentiality requirements, shall make all relevant information and required specifications available to the applicant to permit the applicant to obtain an independent design and cost estimate for the interconnection facilities.</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>The interconnection facilities shall be built in accordance with the specifications in the interconnection facilities study.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(d)">
          <text>Upon completion of the interconnection facilities study, and with the agreement of the applicant to pay for the interconnection facilities and distribution upgrades identified in the interconnection facilities study, the utility shall provide the applicant with an interconnection agreement within 5 business days.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The utility may require a study deposit of the lesser of 50 percent of estimated nonbinding good faith study costs or $10,000.</text>
        </paragraph>
        <paragraph num="(f)">
          <text>In cases where no interconnection upgrades are required, the interconnection facilities study shall be completed and the results shall be transmitted to the interconnection customer within 30 calendar days after the agreement is signed by the parties.</text>
        </paragraph>
        <paragraph num="(g)">
          <text>In cases where interconnection upgrades are required, the interconnection facilities study shall be completed and the results shall be transmitted to the interconnection customer within 45 calendar days after the agreement is signed by the parties.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Interconnection Agreement.</text>
      <paragraph num="(1)">
        <text>When a utility determines, as a result of the interconnection studies conducted under a Level 4 review, that it is appropriate to interconnect the small generator facility, the utility shall provide the applicant with an interconnection agreement.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The applicant shall have either 30 calendar days, or another mutually agreeable time frame after receipt of the interconnection agreement, to sign and return the interconnection agreement.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If the applicant does not sign the interconnection agreement within 30 calendar days, the request shall be considered withdrawn unless the applicant and utility mutually agree to extend the time period for executing the interconnection agreement prior to the expiration of the 30-calendar-day period. A request for extension may not be unreasonably denied by the utility.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>After the interconnection agreement is signed by the applicant and utility, interconnection of the small generator facility shall proceed according to any milestones agreed to by the applicant and utility in the interconnection agreement.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The utility shall approve the interconnection request and provide a permission to operate notice within 20 business days of receipt of acceptable documents, subject to the following conditions:</text>
        <paragraph num="(a)">
          <text>All milestones agreed to in the interconnection agreement are satisfied;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The small generator facility is approved by electric code officials with jurisdiction over the interconnection;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The applicant provides a certificate of completion to the utility;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Upon request of the utility, the applicant provides one or more photographs of the small generator facility site location, components, metering equipment, and other related facilities and equipment; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>There is a successful completion of the witness test, if conducted by the utility.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="G.">
      <text>Level 4 Review Failure. If the interconnection request is denied, the utility shall provide the applicant a letter explaining the reasons for denying the interconnection request.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".13" heading="Dispute Resolution.">
    <paragraph num="A.">
      <text>The applicant and utility shall attempt to resolve all disputes regarding interconnection as provided in this regulation promptly, equitably, and in a good faith manner.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Dispute Resolution Before the Commission.</text>
      <paragraph num="(1)">
        <text>If a dispute arises, the applicant or utility may seek immediate resolution through the procedures of COMAR 20.32.01.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Dispute resolution shall be conducted in an informal, expeditious manner to reach resolution with minimal costs and delay.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If a dispute arises involving technical matters regarding the interconnection process, dispute resolution shall be delegated to the Commission’s Engineering Division.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Pursuit of dispute resolution may not affect an applicant with regard to consideration of an interconnection request or an applicant's queue position.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Any deadline imposed by the regulations in this chapter, which is directly affected by any issue in dispute, shall be suspended until resolution of the dispute.</text>
    </paragraph>
    <paragraph num="E.">
      <text>If a satisfactory resolution is not achieved between the applicant and utility, the applicant or utility may request a hearing, pursuant to Public Utilities Article, §3-102, Annotated Code of Maryland.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".14" heading="Record Retention and Reporting Requirements.">
    <paragraph num="A.">
      <text>A utility shall retain records of the following for a minimum of 7 years:</text>
      <paragraph num="(1)">
        <text>The total number nameplate capacity and total fees charged for the interconnection requests received, approved, and denied under Level 1, Level 2, Level 3, and Level 4 reviews;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The number of evaluations of interconnections requests approved and denied using any alternate process under Level 1, Level 2, Level 3, and Level 4 reviews;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The fuel type, if appropriate, total number, and nameplate capacity of small generator facilities approved in each of the following categories:</text>
        <paragraph num="(a)">
          <text>Net metering;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Emergency standby capable of operating in parallel;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Behind the meter load offset;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Combined heat and power;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Energy storage devices; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Other;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The number of interconnection requests that were not processed within the deadlines established for Level 1, Level 2, Level 3, and Level 4 reviews in this chapter;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The number of scoping meetings held, the number of feasibility studies, impact studies, and facility studies performed, and the fees charged for these studies;</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The justifications for the actions taken to deny interconnection requests;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>The number of interconnection requests that were not processed within the deadlines established for Level 1, Level 2, Level 3, and Level 4 reviews in this chapter due to a PJM Interconnection, LLC market process study; and</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Any special operating requirements required in interconnection agreements, which are permitted only for generating facilities with a nameplate capacity greater than 2 MW, that are not part of the utility's standard operating procedures applicable to small generator facilities.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>A utility shall retain records of interconnection studies it performs to determine the feasibility, system impacts, and facilities required by the interconnection of any small generator facility for a minimum of 7 years.</text>
    </paragraph>
    <paragraph num="C.">
      <text>A utility shall file not later than April 1 of each year a report entitled “Annual Small Generator Interconnection Report” to the Commission containing the following information for the preceding calendar year:</text>
      <paragraph num="(1)">
        <text>The total number of interconnection requests received, approved, and denied under Level 1, Level 2, Level 3, and Level 4 reviews;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The fuel type, or energy storage type, total number, and total nameplate capacity of small generator facilities approved in each of the following categories:</text>
        <paragraph num="(a)">
          <text>Net metering;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Emergency standby capable of operating in parallel;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Behind the meter load offset;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Combined heat and power;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Energy storage devices;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>V2G Systems – DC EVSE;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>V2G Systems – AC EVSE; and</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Other;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The number of interconnection requests that were not processed within the deadlines established for Level 1, Level 2, Level 3, and Level 4 reviews and permission to operate notices in this chapter;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The total number of interconnection requests denied and the reason for each denial;</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Each interconnection request for a proposed small generator facility that received a cost estimate or incurred an actual cost of at least $10,000 for interconnection facilities or distribution upgrades and was completed during the reporting year, which shall include:</text>
        <paragraph num="(a)">
          <text>A list of the nameplate capacity of the proposed small generator facility;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Cost variance;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Variance percentage; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>If required, a summary explanation on why the actual cost of facilities or upgrades was at least 10 percent greater than the cost estimate provided;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>The number of scoping meetings held, the number of feasibility studies, impact studies, facility studies, and combined studies performed and the total fees charged for these studies;</text>
      </paragraph>
      <paragraph num="(7)">
        <text>For each interconnection request for a proposed small generator facility that failed to meet Level 2 criteria according to Regulation .10F of this chapter, a list of the queue number, reason for failure to meet Level 2 criteria, if the applicant requested additional review, whether the additional review was completed within 30 calendar days, or if the applicant decided to request interconnection under Level 4 criteria;</text>
      </paragraph>
      <paragraph num="(8)">
        <text>The current utility status and future plans and schedule for implementation of hosting capacity reporting systems or improvements to existing hosting capacity reporting systems;</text>
      </paragraph>
      <paragraph num="(9)">
        <text>Beginning April 1, 2021, a utility shall also report annually for the previous year:</text>
        <paragraph num="(a)">
          <text>The total number of restricted circuits and the total number of closed circuits;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The number of interconnection requests totaled for Level 1, Level 2, Level 3, and Level 4 that were denied due to restricted circuits and the total number that were denied due to closed circuits;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The number of interconnection requests for inadvertent export totaled for Level 1, Level 2, Level 3, and Level 4 that were approved, denied, or suspended due to non-compliance;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The number of interconnection requests for flexible interconnection options totaled for Level 1, Level 2, Level 3, and Level 4 that were approved, denied, or suspended due to non-compliance;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The number of cancelled small generator facility projects that result in interconnection costs to subsequent small generator facility projects in the same interconnection queue; and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The number of small generator facility projects that delay payment for a distribution system upgrade until the time a first higher small generator facility project in an interconnection queue is ready to interconnect;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(10)">
        <text>Beginning April 1, 2024, if Volt-Watt control is implemented in a utility’s default utility required inverter settings profile, a utility shall also report for the electric distribution system annually for the previous year:</text>
        <paragraph num="(a)">
          <text>Number of total interconnection customer complaints about smart inverter related curtailments;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Number of smart inverter related curtailment interconnection customer complaints resolved by utility;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Number of smart inverter related curtailment interconnection customer complaints resolved by customer; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Number of smart inverter related interconnection customer curtailment complaints unresolved; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(11)">
        <text>Beginning April 1, 2025, an electric utility shall report exemptions to Regulation .06R of this chapter annually for the previous year, including:</text>
        <paragraph num="(a)">
          <text>The number of interconnection requests subject to the PJM Interconnection, LLC Tariff;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The number of interconnection requests in an area governed by a hosting capacity upgrade plan approved by the Commission;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The number of interconnection requests on a dedicated primary voltage feeder that may not benefit any other interconnection customer;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The number of interconnection requests on a dedicated secondary voltage facility that may not benefit any other interconnection customer;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The number of interconnection requests on an AC distribution grid or spot network;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The number of interconnection requests exempted for other good cause; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>The reason for good cause for each interconnection request exempted from Regulation .06R of this chapter.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>The utility shall file a notice with the Commission describing any interconnection equipment the utility has considered field-approved for its distribution system within 90 days after granting approval for the interconnection of a small generator facility using the field-approved interconnection equipment.</text>
    </paragraph>
    <paragraph num="E.">
      <text>For any small generator facility receiving an interconnection impact study, the utility shall list and explain any study for which the cost of the actual upgrade exceeded the impact study’s estimate by at least 25 percent.</text>
    </paragraph>
    <paragraph num="F.">
      <text>For any small generator facility receiving an interconnection facilities study, the utility shall list and explain any study for which the cost of the actual upgrade exceeded the impact study’s estimate by at least 10 percent.</text>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, 5-303, 7-306, and 7-306.2, and 7-1004, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: June 9, 2008 (35:8 Md. R. 808)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01B amended effective March 20, 2023 (50:5 Md. R. 183)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02B amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04E repealed effective April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05 amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436); March 20, 2023 (50:5 Md. R. 183)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .07B amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09 amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09A, E amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .10 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .10A, G amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .11 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .11E amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .12 amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .12E, F amended effective April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .13C amended effective October 8, 2018 (45:20 Md. R. 920)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .14 amended effective October 8, 2018 (45:20 Md. R. 920); April 20, 2020 (47:8 Md. R. 436)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .14C amended effective March 20, 2023 (50:5 Md. R. 183)</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised effective December 12, 2024 (Md. R. 51:24 1082)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02B amended effective July 7, 2025 (52:13 Md. R. 657)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06N amended effective July 7, 2025 (52:13 Md. R. 657)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06S adopted effective July 7, 2025 (52:13 Md. R. 657)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .14C amended effective July 7, 2025 (52:13 Md. R. 657)</annotation>
  </annotations>
</chapter>