A.
Net Energy Metering. An electric company shall provide net metering of electric service to eligible customer-generators using a meter capable of net energy metering until the rated generating capacity of all eligible customer-generators in the State reaches 1,500 megawatts.
B.
Maximum Size of Electric Generating System — Net Metering. An electric company may not provide net energy metering to an eligible customer-generator operating an electric generating system that has a rated capacity of more than 2 megawatts.
C.
Micro Combined Heat and Power Electric Generating System. An electric company may not provide net energy metering to an eligible customer-generator operating a micro combined heat and power electric generating system that has a rated capacity of more than 30 kilowatts.
D.
Qualifying for Net Energy Metering.
(1)
In order to initially qualify for net energy metering:
(a)
An eligible customer-generator shall comply with the provisions of COMAR 20.50.09; and
(b)
The eligible customer-generator’s proposed electric generating system may not exceed 200 percent of the eligible customer-generator’s baseline annual usage.
(2)
Upgraded Electric Generating Systems.
(a)
When an eligible customer-generator receiving net energy metering proposes an upgrade to an existing electric generating system, an electric company shall re-evaluate the baseline annual usage to determine whether the electric generating system continues to meet the requirements of §D(1)(b) of this regulation.
(b)
If the eligible customer-generator’s upgraded electric generating system does not meet the requirements of §D(1)(b) of this regulation, an electric company may discontinue net energy metering.