<regulation prefix="Regulation" num=".03" citation="COMAR 20.50.15.03" title_num="20" subtitle_num="50" chapter_num="15" heading="Electric System Planning Process.">
  <paragraph num="A.">
    <text>An electric system planning process shall align with the following components for each planning cycle and scenario and related requirements specified in this chapter:</text>
    <paragraph num="(1)">
      <text>Considerations feeding into types of projections;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Goals/ objectives;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>DER forecast;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Load forecast;</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Hosting capacity assessment;</text>
    </paragraph>
    <paragraph num="(6)">
      <text>Grid needs and locational value assessment;</text>
    </paragraph>
    <paragraph num="(7)">
      <text>Identify possible solutions to grid needs;</text>
    </paragraph>
    <paragraph num="(8)">
      <text>Screen and evaluate possible solutions;</text>
    </paragraph>
    <paragraph num="(9)">
      <text>Choose solutions and publish plan;</text>
    </paragraph>
    <paragraph num="(10)">
      <text>Program and project design; and</text>
    </paragraph>
    <paragraph num="(11)">
      <text>Assess results.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Considerations Feeding into Types of Projections.</text>
    <paragraph num="(1)">
      <text>Time Horizons for DER and Load Forecasting.</text>
      <paragraph num="(a)">
        <text>DER and load forecasting processes for electric companies other than electric cooperatives and municipal electric companies shall include at least three planning time horizons:</text>
        <paragraph num="(i)">
          <text>1 to 3 years;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>4 to 6 years; and</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>7 to 10  years.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>DER and load forecasting processes for electric cooperatives and municipal electric companies shall include at least two planning time horizons:</text>
        <paragraph num="(i)">
          <text>1 to 3 years; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>4 years up to 20 years.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Level of Granularity. The granularity of information in an electric system plan may vary as described in other sections of this regulation.</text>
      <paragraph num="(a)">
        <text>As a near-term objective:</text>
        <paragraph num="(i)">
          <text>Information shall be provided in an Electric System Plan at the substation level; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Feeder-level information shall be provided as part of the planning process for feeders where there are identified system constraints;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>As a longer-term objective, electric companies shall report on progress regarding incorporating more granular electric system and customer information and data into forecasting and planning processes in their electric system plan or annual electric system plan update.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>Scenarios/Projections to be Analyzed. An electric system plan shall include a minimum of two scenarios to provide a range of outcomes to inform planning analysis and the determination of the scale and pace of grid needs:</text>
      <paragraph num="(a)">
        <text>A baseline scenario; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>A goal scenario.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The Commission may request an electric company to analyze scenarios in addition to a baseline scenario and goal scenario.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>Data Sources, Scope, and Access. Electric companies shall provide for data collection and access that:</text>
      <paragraph num="(a)">
        <text>Allows stakeholders the opportunity to provide data inputs at pre-identified time periods defined by the electric company;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Provides collected data in a format that can be easily accessed by stakeholders; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Provides stakeholders transparency into data sources, data and assumptions used to develop electric system plans and annual electric system plan updates.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(5)">
      <text>Already-Approved Resource Retirements and Additions. Electric companies shall consider in their electric system plans whether distribution-level electric system planning can be used to mitigate potential gaps caused by generation retirements.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>PJM Wholesale Markets. Electric companies shall consider DERs and VPPs that participate in the PJM wholesale markets in electric distribution planning as applicable.</text>
    </paragraph>
    <paragraph num="(7)">
      <text>Resource Costs and Capabilities. Electric companies contracting decisions to implement electric system plans and annual electric system plan updates shall be left to electric company discretion.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Goals/Objectives. An electric system plan shall promote applicable State policy goals pursuant to Public Utilities Article, §§7-801—7-804, et seq., Annotated Code of Maryland, and other applicable goals and targets as directed by the Commission.</text>
  </paragraph>
  <paragraph num="D.">
    <text>DER Forecast. An electric system plan shall account for the following considerations for each electric system planning cycle and scenario.</text>
    <paragraph num="(1)">
      <text>Electric companies shall develop separate forecasts for each relevant DER type, including energy efficiency, demand response, distributed generation, energy storage devices, VPPs and managed EV charging-discharging.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Electric Companies shall develop hourly DER forecasts.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Load Forecast. Load forecasts shall account for the following considerations for each planning cycle and scenario as follows:</text>
    <paragraph num="(1)">
      <text>Electric companies shall incorporate load impacts of current and future transportation and building electrification based on known information and assumptions; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Electric company distribution-level forecasts in aggregate shall be aligned to a reasonable extent with available electric company developed transmission-level forecasts and with PJM-developed system-level forecasts with an explanation provided in electric system plans for any differences and the associated factors, including differences in assumptions.</text>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>Hosting Capacity Assessment. An electric system plan shall account for the following considerations for each planning cycle and scenario.</text>
    <paragraph num="(1)">
      <text>Hosting capacity calculations shall be determined using a circuit-specific calculation including installed and forecasted DER interconnections.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>DER forecasting shall be incorporated into reserve hosting capacity determinations and the rightsizing of hosting capacity upgrades.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Electric companies shall establish methodologies for calculating available hosting capacity and, in the annual electric system plan update and electric system plan, discuss planned hosting capacity capability improvements.</text>
    </paragraph>
  </paragraph>
  <paragraph num="G.">
    <text>Grid Needs and Locational Value Assessment.</text>
    <paragraph num="(1)">
      <text>Grid Needs Assessment.</text>
      <paragraph num="(a)">
        <text>An electric company’s grid needs assessment shall include current and forecast distribution substation and feeder constraints identified as part of each planning cycle, including the timing, magnitude and other relevant characteristics for each identified system constraint.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The annual electric system plan update shall discuss changes to an electric company’s grid needs assessment that may occur between planning cycles.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Electric companies shall cost-effectively pursue industry best practice methods and analytical tools to improve their planning analysis and processes, the choice of which to adopt shall be at the discretion of the electric companies.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Locational Value Assessment.</text>
      <paragraph num="(a)">
        <text>An electric system plan shall provide locational value for each identified electric system constraint.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Locational value shall include the potential deferral or avoided value of a traditional wires solution.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Electric companies shall develop a locational value assessment using the Commission's uniform benefit cost analysis framework.</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Electric companies shall report on the progress towards implementation of locational value assessments at annual technical conferences.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="H.">
    <text>Identify Possible Solutions to Grid Needs. An electric system plan shall account for the following considerations for each planning cycle and scenario:</text>
    <paragraph num="(1)">
      <text>Near-Term Objective.</text>
      <paragraph num="(a)">
        <text>An electric system plan shall identify solutions for identified grid needs.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Electric companies shall identify non-wires solutions considered to address system constraints.</text>
      </paragraph>
      <paragraph num="(c)">
        <text>For any proposed upgrade projects resulting from Regulations .03H and .03I of this chapter, future hosting capacity constraints that incorporate DER forecasts shall be considered.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>As A Longer-Term Objective.</text>
      <paragraph num="(a)">
        <text>Electric companies shall assess the feasibility of utilizing new cost-effective technologies and methodologies for solutions to grid needs.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Electric companies shall report on the progress towards utilizing new cost-effective technologies and methodologies at annual technical conferences.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>Pursuant to Public Utilities Article, §7-804, Annotated Code of Maryland, electric companies shall consider investment in, or procurement of cost-effective demand-side methods and technology to improve reliability and efficiency, including VPPs.</text>
    </paragraph>
  </paragraph>
  <paragraph num="I.">
    <text>Screen and Evaluate Possible Solutions.</text>
    <paragraph num="(1)">
      <text>An electric company shall screen and evaluate possible solutions for each planning cycle and scenario.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The electric system plan shall include the criteria used to evaluate possible solutions, including cost-effectiveness considerations.</text>
      <paragraph num="(a)">
        <text>Electric companies shall evaluate cost-effectiveness for alternatives considered, if applicable.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Electric companies shall utilize the Commission's Unified Benefit Cost Analysis framework for solutions involving DERs in determining cost-effectiveness.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="J.">
    <text>Choose Solutions and Publish Plan. An electric company shall choose a solution or solutions for each scenario and publish a plan for each planning cycle as described in Regulation .04 of this chapter.</text>
    <paragraph num="(1)">
      <text>Electric companies shall present their rationale for solution selection in electric system plans, including why alternative solutions were not selected.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Information and data shall be provided in an electric system plan at the substation level.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>When project solutions are proposed in response to system constraints, electric companies shall provide feeder-level information, where applicable.</text>
    </paragraph>
  </paragraph>
  <paragraph num="K.">
    <text>Program and Project Design.</text>
    <paragraph num="(1)">
      <text>Program and project design including construction, procurement, and electric company contracting are factors in the electric companies’ mandate to provide safe and reliable service and a consideration in overall cost which shall be estimated in electric system plans.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Program and project design including construction, procurement, and electric company contracting decisions shall be left to electric company discretion in executing an electric system plan although these factors will remain subject to review in rate cases.</text>
    </paragraph>
  </paragraph>
  <paragraph num="L.">
    <text>Assess Results. An electric company shall account for the following considerations for each planning cycle:</text>
    <paragraph num="(1)">
      <text>An electric company shall assess the results of their electric system plans to determine lessons learned and changes to future planning assumptions.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Rate case filings shall provide explanations for projects that do not reconcile with electric system plans.</text>
    </paragraph>
  </paragraph>