<subtitle num="52" heading="Electric Standard Offer Service" title_num="20" title_heading="Public Service Commission">
  <chapter num="01" heading="General Regulations">
    <regulation prefix="Regulation" num=".01" heading="Scope.">
      <paragraph num="A.">
        <text>This subtitle applies to an investor-owned electric company or other entity directed or authorized by a Public Service Commission order to provide electricity supply and electricity supply service.</text>
      </paragraph>
      <paragraph num="B.">
        <text>This subtitle does not apply to electric cooperatives or municipal electric companies.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Definitions.">
      <paragraph num="A.">
        <text>In this subtitle, the following terms have the meanings indicated.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Terms Defined.</text>
        <paragraph num="(1)">
          <text>“Commission” means the Public Service Commission of Maryland.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>“Customer” has the meaning stated in Public Utilities Article, §7-501, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>“Electric company” has the meaning stated in Public Utilities Article, §1-101, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>“FERC” means the Federal Energy Regulatory Commission.</text>
        </paragraph>
        <paragraph num="(5)">
          <text>“HPS” means hourly priced nonresidential electricity service provided by an investor-owned electric company.</text>
        </paragraph>
        <paragraph num="(6)">
          <text>“LMP” means locational marginal price.</text>
        </paragraph>
        <paragraph num="(7)">
          <text>“PJM” means the PJM Interconnection, LLC.</text>
        </paragraph>
        <paragraph num="(8)">
          <text>“Standard offer service” or (SOS) has the meaning stated in Public Utilities Article, §7-501, Annotated Code of Maryland.</text>
        </paragraph>
        <paragraph num="(9)">
          <text>“Type I” means standard offer service provided by a utility under Public Utilities Article, §7-510(c), Annotated Code of Maryland, to certain commercial customers through a Commission-approved rate schedule.</text>
        </paragraph>
        <paragraph num="(10)">
          <text>Type II.</text>
          <paragraph num="(a)">
            <text>“Type II” means standard offer service offered by a utility to nonresidential customers ineligible for Type I service with a PJM capacity peak load contribution of less than 600 kilowatts (kW).</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Type II” does not include nonresidential electricity supply service provided to a customer ineligible for Type I service with a PJM capacity peak load contribution of less than 600 kilowatts (kW) receiving electric supply service under an existing special electric supply contract with a utility.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(11)">
          <text>Type III.</text>
          <paragraph num="(a)">
            <text>“Type III” means a large customer taking regulated electric supply service from a utility available to a nonresidential customer ineligible for Type I or Type II service.</text>
          </paragraph>
          <paragraph num="(b)">
            <text>“Type III” does not include a large customer with a special electric supply contract with a utility or excluded by a Commission order.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(12)">
          <text>“Utility” means an electric company that is investor owned.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Standard Offer Service Obligation.">
      <paragraph num="A.">
        <text>A utility or any other Commission-authorized entity shall provide SOS to any eligible customer choosing SOS, whose electric service has not been denied or terminated under COMAR 20.31, COMAR 20.50.04, or the utility's approved tariff.</text>
      </paragraph>
      <paragraph num="B.">
        <text>If a customer meets any of the criteria under the Public Utilities Article, §7-510(c)(2), Annotated Code of Maryland, the customer is considered to have chosen SOS.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, and 7-510, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: June 7, 2004 (31:11 Md. R. 857)</annotation>
    </annotations>
  </chapter>
  <chapter num="02" heading="Standard Offer Service">
    <regulation prefix="Regulation" num=".01" heading="Provision of Residential Standard Offer Service Required.">
      <paragraph num="A.">
        <text>This regulation does not apply to residential SOS before the service periods specified in §C of this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A utility may deny residential SOS under COMAR 20.50.04.01-2 or the utility's tariffs.</text>
      </paragraph>
      <paragraph num="C.">
        <text>A utility shall provide residential SOS for the following specified time periods:</text>
        <paragraph num="(1)">
          <text>Baltimore Gas and Electric Company from July 1, 2006 through May 31, 2010;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Delmarva Power &amp; Light Company from July 1, 2004 through May 31, 2008;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Potomac Electric Power Company from July 1, 2004 through May 31, 2008;</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The Potomac Edison Company doing business as (d/b/a) Allegheny Power from January 1, 2009 through December 31, 2012.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Extension of SOS. The Commission may extend a utility obligation to provide SOS under Public Utilities Article, §7-510(c)(3), Annotated Code of Maryland.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Standard Offer Service — Small Commercial Customers.">
      <paragraph num="A.">
        <text>This regulation does not apply to electric supply service provided by a utility prior to the service periods specified in §§B and C of this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Type I—Small Commercial Customer.</text>
        <paragraph num="(1)">
          <text>A utility shall provide Type I SOS to a customer for the following specified time periods:</text>
          <paragraph num="(a)">
            <text>Baltimore Gas and Electric Company from July 1, 2004 through May 31, 2008;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Delmarva Power &amp; Light Company from June 1, 2004 through May 31, 2008;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Potomac Electric Power Company from July 1, 2004 through May 31, 2008; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The Potomac Edison Company doing business as (d/b/a) Allegheny Power from January 1, 2005 through December 31, 2008.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>A utility shall offer Type I SOS as ordered by the Commission to all small commercial customer classes.</text>
        </paragraph>
      </paragraph>
      <paragraph num="C.">
        <text>Type II—Commercial Customer.</text>
        <paragraph num="(1)">
          <text>A utility shall offer Type II SOS to a commercial customer as defined under COMAR 20.52.01.02B(11).</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A utility shall provide Type II SOS to customers for the following specified time periods:</text>
          <paragraph num="(a)">
            <text>Baltimore Gas and Electric Company from July 1, 2004 through May 31, 2006;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Delmarva Power &amp; Light Company from June 1, 2004 through May 31, 2006;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Potomac Electric Power Company from July 1, 2004 through May 31, 2006; and</text>
          </paragraph>
          <paragraph num="(d)">
            <text>The Potomac Edison Company doing business as (d/b/a) Allegheny Power from January 1, 2005 through December 31, 2006.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>Extension of SOS. The Commission may extend a utility obligation to provide SOS under Public Utilities Article, §7-510(c)(3), Annotated Code of Maryland.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Large Customer — Electric Supply Service.">
      <paragraph num="A.">
        <text>This regulation does not apply to electric supply service provided by a utility before the service periods stated in §B of this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A utility shall provide Type III large customer service to customers for the following specified time periods:</text>
        <paragraph num="(1)">
          <text>Baltimore Gas and Electric Company from July 1, 2004 through May 31, 2005;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Delmarva Power &amp; Light Company from June 1, 2004 through May 31, 2005;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>Potomac Electric Power Company from July 1, 2004 through May 31, 2005; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>The Potomac Edison Company doing business as (d/b/a) Allegheny Power from January 1, 2005 through December 31, 2005.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Hourly Priced Electric Supply Service.">
      <paragraph num="A.">
        <text>A utility shall offer hourly priced nonresidential electric supply service to all nonresidential customers ineligible for Type I or Type II SOS, excluding special generation contract customers.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A utility shall provide hourly priced service beginning with the time periods provided for Type III service in Regulation .03 of this chapter.</text>
      </paragraph>
      <paragraph num="C.">
        <text>A utility may not change or alter tariff rules, terms, and conditions for HPS under §B of this regulation for a period of at least 2 years.</text>
      </paragraph>
      <paragraph num="D.">
        <text>The rate for HPS shall include:</text>
        <paragraph num="(1)">
          <text>One of the following:</text>
          <paragraph num="(a)">
            <text>The PJM hourly LMP for energy; or</text>
          </paragraph>
          <paragraph num="(b)">
            <text>If PJM alters its pricing methods, the nearest equivalent to LMP;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(2)">
          <text>Charges associated with PJM capacity obligation;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>FERC-approved:</text>
          <paragraph num="(a)">
            <text>Transmission rates;</text>
          </paragraph>
          <paragraph num="(b)">
            <text>Ancillary services;</text>
          </paragraph>
          <paragraph num="(c)">
            <text>Energy losses;</text>
          </paragraph>
          <paragraph num="(d)">
            <text>Administrative costs;</text>
          </paragraph>
          <paragraph num="(e)">
            <text>Any other FERC approved or PJM charges and costs directly related to the utilities' hourly priced service;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(4)">
          <text>Costs required to meet statutory renewable requirements;</text>
        </paragraph>
        <paragraph num="(5)">
          <text>Any other price elements directly related to the service as approved by the Commission;</text>
        </paragraph>
        <paragraph num="(6)">
          <text>Taxes;</text>
        </paragraph>
        <paragraph num="(7)">
          <text>An applicable administrative charge intended to recover the utility's verifiable and prudently incurred costs; and</text>
        </paragraph>
        <paragraph num="(8)">
          <text>A Commission-approved reasonable return.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Other Periods of Electric Service.">
      <text>For periods other than those identified in Regulations .01—.03 of this chapter, the Commission may authorize the provision of SOS, default service, Type II service, Type III service, or electric supply provider of last resort service to the customer classes described in this chapter.</text>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, and 7-510, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: June 7, 2004 (31:11 Md. R. 857)</annotation>
    </annotations>
  </chapter>
  <chapter num="03" heading="Transfers Of Service">
    <regulation prefix="Regulation" num=".01" heading="Customer Changes of Service Providers.">
      <paragraph num="A.">
        <text>A customer may move between SOS or HPS and competitive electricity supply service.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A customer may not be charged a fee for switching between SOS or HPS and competitive electricity supply.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Except as provided by an order of the Commission, a utility may not impose a minimum contract term for the provision of electricity supply service under this subtitle.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Notice of Transfer to Standard Offer Service.">
      <paragraph num="A.">
        <text>Existing Customers. If an existing utility customer does not select a competitive electricity supplier to provide electricity supply service, the customer shall receive standard offer service under this subtitle until that choice is made in accordance with §C of this regulation.</text>
      </paragraph>
      <paragraph num="B.">
        <text>New Customer. A customer establishing a new service, after the service periods specified in COMAR 20.52.02, shall receive SOS until the customer affirmatively selects a competitive electricity supplier.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Transfer Rules.</text>
        <paragraph num="(1)">
          <text>If a customer or the customer’s competitive supplier requests SOS, 12 or more days before the customer's next regularly scheduled meter read date, the utility shall place the customer on SOS on the customer's next regularly scheduled meter read date.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If a customer or the customer’s competitive supplier requests SOS, less than 12 days before the customer’s next regularly scheduled meter read date, the utility shall transfer the customer to SOS on the subsequent scheduled meter read date after the date of the request.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>If a customer is subject to an involuntary transfer to SOS, the customer shall receive SOS effective on the date on which PJM transfers responsibility for supplying that customer's electricity to the utility.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Notice of Transfer From Standard Offer Service.">
      <paragraph num="A.">
        <text>When a customer receiving SOS chooses electricity from a competitive electricity supplier, the competitive electricity supplier shall notify the utility.</text>
      </paragraph>
      <paragraph num="B.">
        <text>The notice required under §A of this regulation shall comply with the requirements of COMAR 20.53 and the utility's approved supplier coordination tariffs.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Transfer Rules.</text>
        <paragraph num="(1)">
          <text>When a competitive electricity supplier provides the transfer notice required under §A of this regulation, 12 or more days before a customer's next regularly scheduled meter read date, the utility shall transfer the customer to the competitive electricity supplier on the next regularly scheduled meter read date after the notice.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>When a competitive electricity supplier provides the transfer notice, required under §A of this regulation, less than 12 days before a customer's next regularly scheduled meter read date, the utility shall transfer the customer to the competitive electricity supplier on the subsequent scheduled meter read date after the notice.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".04" heading="Hourly Priced or Competitive Service — Selection or Transfer.">
      <paragraph num="A.">
        <text>Utility Fixed Price or Variable Price Service Customers.</text>
        <paragraph num="(1)">
          <text>If a customer eligible for does not select or have a competitive electricity supplier, a utility shall provide HPS service to the customer.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If a customer eligible for HPS selects a competitive electricity supplier, the competitive electricity supplier shall provide the utility notice of the selection in a manner conforming to the requirements of the applicable utility’s supplier coordination tariff and COMAR 20.53.06.05.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>Failure of Competitive Electricity Supplier to Deliver.</text>
        <paragraph num="(1)">
          <text>If a competitive electricity service customer is eligible for HPS and the competitive electricity service supplier fails to deliver power as defined by PJM due to default, bankruptcy, or Commission action, the customer shall receive HPS.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A customer eligible for HPS and affected by §B(1) of this regulation may elect at any time to switch to another competitive electricity supplier.</text>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".05" heading="Denial or Termination of SOS.">
      <paragraph num="A.">
        <text>A utility or other Commission-authorized entity providing SOS may terminate SOS only if the termination process complies with COMAR 20.31.</text>
      </paragraph>
      <paragraph num="B.">
        <text>A utility or other Commission-authorized entity providing SOS may deny SOS only if the denial complies with COMAR 20.50.04.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, and 7-510, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: June 7, 2004 (31:11 Md. R. 857)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .01 amended effective February 4, 2013 (40:2 Md. R. 73)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .02 amended effective February 4, 2013 (40:2 Md. R. 73)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .03B, C amended effective February 4, 2013 (40:2 Md. R. 73)</annotation>
      <annotation type="History" subtype="Administrative History">Regulation .04 amended effective February 4, 2013 (40:2 Md. R. 73)</annotation>
    </annotations>
  </chapter>
  <chapter num="04" heading="Electric Supply Service Procurement">
    <regulation prefix="Regulation" num=".01" heading="Procurement by Investor-Owned Utilities.">
      <paragraph num="A.">
        <text>Except for HPS or under Regulation .02D and E of this chapter, a utility shall procure the electricity needed to provide service under this subtitle during the service periods stated in COMAR 20.52.02 only through a competitive wholesale bidding process approved by the Commission.</text>
      </paragraph>
      <paragraph num="B.">
        <text>Model Request for Proposals and Utility Bid Plan.</text>
        <paragraph num="(1)">
          <text>A utility shall base the competitive bidding process required by this regulation on the model request for proposals and a utility bid plan approved by the Commission.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The model request for proposals shall include a provision designed to eliminate a bid proposal for residential standard offer service that contains a price anomaly.</text>
        </paragraph>
        <paragraph num="(3)">
          <text>The model request for proposals may be altered by a utility bid plan only if it is necessary to conform to utility specific conditions.</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Utility Bid Plan.</text>
          <paragraph num="(a)">
            <text>A utility bid plan shall include:</text>
            <paragraph num="(i)">
              <text>A bidding schedule;</text>
            </paragraph>
            <paragraph num="(ii)">
              <text>A description of the power supply blocks on which potential suppliers shall bid;</text>
            </paragraph>
            <paragraph num="(iii)">
              <text>Bid price formats;</text>
            </paragraph>
            <paragraph num="(iv)">
              <text>The time period during which the power will need to be supplied for each power supply block;</text>
            </paragraph>
            <paragraph num="(v)">
              <text>Bid submission instructions and format; and</text>
            </paragraph>
            <paragraph num="(vi)">
              <text>Bid evaluation criteria.</text>
            </paragraph>
          </paragraph>
          <paragraph num="(b)">
            <text>A utility may include in its bid plan reasonable credit requirements, cash collateral, or other assurance of the bidder's ability to perform, as approved by the Commission.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Evaluation and Selection of Qualified Bids.">
      <paragraph num="A.">
        <text>A utility shall evaluate a qualified bid in a nondiscriminatory manner based on:</text>
        <paragraph num="(1)">
          <text>The contents of the bid submissions as specified in the model request for proposal; and</text>
        </paragraph>
        <paragraph num="(2)">
          <text>The utility bid plan.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>A utility shall select qualified bidders based on the criteria established in the model request for proposals and the utility bid plan.</text>
      </paragraph>
      <paragraph num="C.">
        <text>Commission Review.</text>
        <paragraph num="(1)">
          <text>As provided by Commission order, the Commission shall review all utility-selected bid proposals as a condition of any final contract.</text>
        </paragraph>
        <paragraph num="(2)">
          <text>If the Commission uses a consultant for this purpose, the consultant is subject to strict confidentiality requirements established by the Commission in consultation with the utility.</text>
        </paragraph>
      </paragraph>
      <paragraph num="D.">
        <text>If a utility's competitive bid process under this regulation does not provide sufficient electric supply to meet the utility's full load requirements, the Commission by order may provide a process to ensure that a utility obtains all the electricity supply needed to serve the unmet electric load requirements.</text>
      </paragraph>
      <paragraph num="E.">
        <text>The processes established under §D of this regulation may include:</text>
        <paragraph num="(1)">
          <text>A requirement that the utility file with the Commission a proposed alternate means of supplying the otherwise unserved load within 20 days of the utility determining that the load is unserved; or</text>
        </paragraph>
        <paragraph num="(2)">
          <text>A requirement that the utility purchase the necessary electricity and other required services through the PJM market until the Commission approves another means for procuring supply to serve all of its electric load requirements.</text>
        </paragraph>
      </paragraph>
      <paragraph num="F.">
        <text>The result of the competitive bidding process under this regulation is confidential and subject to the confidentiality requirement established by the Commission in consultation with the utility.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".03" heading="Electric Supply Contract.">
      <paragraph num="A.">
        <text>The utility and selected bidders shall enter into a full requirements service contract for each power supply block contained in the utility bid plan.</text>
      </paragraph>
      <paragraph num="B.">
        <text>The Commission shall approve the terms and conditions of the full service contract required under §A of this regulation.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, and 7-510, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: June 7, 2004 (31:11 Md. R. 857)</annotation>
    </annotations>
  </chapter>
  <chapter num="05" heading="Price">
    <regulation prefix="Regulation" num=".01" heading="Public Notice of Price.">
      <text>Upon completion of the electric supply procurement process under COMAR 20.52.04, a utility shall:</text>
      <paragraph num="A.">
        <text>Explain the methodology used to calculate the price for electric service under this subtitle;</text>
      </paragraph>
      <paragraph num="B.">
        <text>Calculate the price for each type of electric service offered to a customer under this subtitle;</text>
      </paragraph>
      <paragraph num="C.">
        <text>File tariffs with the Commission containing the methods of calculating the price for each service authorized by this subtitle at least 30 days, and if possible 2 months, before the effective date of the tariffs;</text>
      </paragraph>
      <paragraph num="D.">
        <text>Provide affected customers at least 30 days notice, and if possible 2 months notice, of new prices for electric service under this subtitle; and</text>
      </paragraph>
      <paragraph num="E.">
        <text>Post on the utility's internet website, the actual price payable each month for each service offered under this subtitle.</text>
      </paragraph>
    </regulation>
    <regulation prefix="Regulation" num=".02" heading="Calculation of Prices.">
      <paragraph num="A.">
        <text>For service periods stated in COMAR 20.52.02, retail prices for each service other than HPS under this subtitle shall consist of the sum of the following components:</text>
        <paragraph num="(1)">
          <text>The seasonally differentiated and, if applicable, the time-of-use differentiated load weighted average of all awarded electric supply prices for specific services in each year;</text>
        </paragraph>
        <paragraph num="(2)">
          <text>Retail charges designed to recover, on an aggregate basis, FERC-approved transmission charges and any other PJM charges and costs incurred by the utility;</text>
        </paragraph>
        <paragraph num="(3)">
          <text>An administrative charge, including other costs and return or profit; and</text>
        </paragraph>
        <paragraph num="(4)">
          <text>Applicable taxes.</text>
        </paragraph>
      </paragraph>
      <paragraph num="B.">
        <text>The Commission may approve adjustments or reconciliation of a price component under §A of this regulation.</text>
      </paragraph>
    </regulation>
    <annotations>
      <annotation type="Authority">Public Utilities Article, §§2-113, 2-121, 5-101, and 7-510, Annotated Code of Maryland</annotation>
      <annotation type="History" subtype="Administrative History">Effective date: June 7, 2004 (31:11 Md. R. 857)</annotation>
    </annotations>
  </chapter>
</subtitle>