  <regulation prefix="Regulation" num=".01" heading="Scope.">
    <text>These regulations apply to LPG systems located in Maryland and to owners of these systems.</text>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Definition of Terms.">
    <paragraph num="A.">
      <text>In this subtitle, the following terms have the meanings indicated.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Terms Defined.</text>
      <paragraph num="(1)">
        <text>“Accident” has the meaning stated in Public Utility Companies Article, §5-304, Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>“Accuracy” means the degree of conformity of a measure to a standard or true value.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>“Associated metering device” means an instrument used to adjust the quantity of gas measured by a meter, based on the measurement of the:</text>
        <paragraph num="(a)">
          <text>Temperature of the gas passing through the meter;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Pressure of the gas passing through the meter; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Temperature and pressure of the gas passing through the meter.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>“Check flow” means a flow of gas at 20—50 percent of the rated capacity of a meter.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>“Commission” means the Public Service Commission of Maryland.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>“Full rated flow” means a flow of gas at approximately 100 percent of the rated capacity of a meter.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>“Gas” means LPG in the vapor state.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>“LPG” means liquified petroleum gas which includes propane, or butane, or other combustible gases, or mixtures thereof.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>“LPG system” means an LPG service installation located in Maryland that provides service to:</text>
        <paragraph num="(a)">
          <text>Ten or more customers by underground pipes from a LPG storage tank; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>At least two but fewer than ten customers by underground pipes from a LPG storage tank, if a portion of the LPG system is located in a public place.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(10)">
        <text>“Meter” means a device used by an owner to measure a quantity of gas.</text>
      </paragraph>
      <paragraph num="(11)">
        <text>“Owner” means the person, as defined in Public Utilities Article, §1-101, Annotated Code of Maryland, owning the LPG system.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="General Requirements.">
    <paragraph num="A.">
      <text>Each owner shall provide the Commission with the following information in writing:</text>
      <paragraph num="(1)">
        <text>The location of each LPG system;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The number of customers or dwelling units provided service by each LPG system; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The name, address, and telephone number of the office of the person responsible for each LPG system.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The information required by §A of this regulation shall be filed with the Public Service Commission under COMAR 20.07.01.01.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Incorporation by Reference.">
    <paragraph num="A.">
      <text>In this chapter, the following documents are incorporated by reference:</text>
      <paragraph num="(1)">
        <text>49 CFR Part 191 Transportation of Natural Gas and Other Gas by Pipeline; Annual Reports, Incident Reports, and Safety Related Condition Reports, as amended;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>49 CFR Part 192 Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety Standards, as amended; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The applicable provisions in the GPTC Guide for Gas Transmission and Distribution Piping Systems, which is incorporated by reference under COMAR 20.55.02.02.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Each owner shall use as acceptable good engineering practice applicable provisions under §A(3) of this regulation.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Enforcement.">
    <paragraph num="A.">
      <text>Public Utilities Article, §§2-117(a), 5-101, 5-304, 12-101—12-113, and 13-203, Annotated Code of Maryland, shall apply to the owners of LPG systems to the extent ordered by the Commission.</text>
    </paragraph>
    <paragraph num="B.">
      <text>The Commission is an authorized agent of the United States Department of Transportation for the administration and enforcement of these regulations and those federal regulations that apply to LPG systems in this State.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Inspections and Tests.">
    <paragraph num="A.">
      <text>Upon reasonable notice, a representative of the Commission shall be given access to each LPG system in order to conduct tests or inspections to assure compliance with these regulations.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Routine inspections of the LPG systems shall be made during regular business hours and may be inspected at any time in the event of an emergency or incident.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Gas Leak Surveys.">
    <paragraph num="A.">
      <text>Frequency of Leak Surveys. Each owner shall conduct a gas leak survey of a LPG pipeline system in accordance with the following schedule:</text>
      <paragraph num="(1)">
        <text>At least once each calendar year, at intervals not exceeding 15 months, for a pipeline located in a business district or place of public assembly;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>At least once every 3 calendar years, at intervals not exceeding 39 months, for a pipeline made of cast iron, ductile iron, and cathodically unprotected steel; or</text>
      </paragraph>
      <paragraph num="(3)">
        <text>At least once every 5 calendar years, at intervals not exceeding 63 months, for all other types of pipelines.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Testing Methods.</text>
      <paragraph num="(1)">
        <text>Each owner shall establish written procedures for conducting gas leak surveys as specified in this chapter.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Acceptable methods for owners conducting gas leak surveys, as described in the GPTC Guide for Gas Transmission and Distribution Piping Systems, include:</text>
        <paragraph num="(a)">
          <text>Subsurface gas detector survey, including bar hole surveys;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Bubble leakage test for pipelines exposed to the atmosphere; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Pressure drop test.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>In addition to the acceptable methods listed in §B(2) of this regulation, other survey and test methods that have been tested and proven to be at least equal to the methods listed in §B(2) of this regulation and approved by the Commission may be used to meet the requirements of §B(1) of this regulation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>A leak or leaks discovered by a gas leak survey conducted pursuant to this regulation shall be classified, and the appropriate action taken as described in the GPTC Guide For Gas Transmission and Distribution Piping Systems.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Field Operations.</text>
      <paragraph num="(1)">
        <text>An owner shall conduct a leakage survey on each new or replaced service line before the line is placed in service, but after backfilling and a reasonable period of gas pressurizing.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>After a leak repair, an owner shall conduct a gas leakage survey in accordance with §B of this regulation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Records of Leak Surveys.</text>
      <paragraph num="(1)">
        <text>An owner shall maintain a record of each leak survey listing by location and date for the following:</text>
        <paragraph num="(a)">
          <text>Number of leaks detected;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Severity of each leak; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Action taken to repair each leak.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>An owner shall maintain the records required under §E(1) of this regulation as long as the segment of pipeline involved remains in service.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Pipeline Location.">
    <paragraph num="A.">
      <text>Identification.</text>
      <paragraph num="(1)">
        <text>An owner shall install tracer wire on all newly installed plastic pipes.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>When the open trenching method of pipeline construction is used, an owner shall install suitable identification tape at least 12 inches above the top of the pipe.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Location of Residential Service Lines and Meters.</text>
      <paragraph num="(1)">
        <text>Residential customer meters shall be placed as close to the exterior building wall as possible.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Gas service may not be provided to new or renewed service lines if there is any underground pipeline after the meter, unless the pipeline carries gas only to gas utilization equipment located outdoors.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If it is not possible to comply with §B(1) or (2) of this regulation, written permission shall be obtained from the Commission before placing the meter and activating the service.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>If a residential service line is replaced, the new service line shall be installed as provided in §B(1)—(3) of this regulation.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".09" heading="Records and Reports.">
    <paragraph num="A.">
      <text>Each owner of a LPG system shall maintain records and provide reports to the Commission as required by this regulation.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Fatal Accidents.</text>
      <paragraph num="(1)">
        <text>In the event of a fatal accident, an owner shall promptly notify the Commission of the fatal accident by telephone.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A written report shall be submitted to the Commission within 20 days of the date of the incident resulting in the fatal accident reported under §B(1) of this regulation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Leaks in pipes or tanks that are hazardous to the public shall be reported immediately to the local central fire department communications center and to the Commission.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Each owner shall submit to the Commission, on a quarterly basis, reports summarizing the leaks discovered, leak calls made pursuant to §C of this regulation, and the owner's responses to these events.</text>
    </paragraph>
    <paragraph num="E.">
      <text>All reports required to be filed with the United States Department of Transportation by 49 CFR 191 and 192 shall also be filed with the Commission.</text>
    </paragraph>
    <paragraph num="F.">
      <text>The Commission may require additional reports to be submitted to it by owners of LPG systems.</text>
    </paragraph>
    <paragraph num="G.">
      <text>Construction Notices.</text>
      <paragraph num="(1)">
        <text>An owner shall notify the Commission in writing at least 10 days before the estimated start date of a major construction project.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A major construction project includes:</text>
        <paragraph num="(a)">
          <text>A new pressure-regulating station;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A significant modification to gas supply equipment at an existing pressure-regulating station;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A new propane plant;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A significant modification to process equipment at an existing propane plant; or</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A new pipeline installation of 500 or more feet.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The notification required by this regulation shall be on a form provided by the Commission.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Public Utilities Article, §§2-113, 2-117(a), 2-121, 5-101, 5-304, 7-301—7-302, 11-102, 12-101—12-113, and 13-203, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: September 13, 1982 (9:18 Md. R. 1801)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02 amended effective March 31, 2003 (30:6 Md. R. 422)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04 amended effective November 2, 1987 (14:22 Md. R. 2340)</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .07 and .08 adopted effective October 11, 1982 (9:20 Md. R. 1982)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .07C amended effective January 15, 1996 (23:1 Md. R. 36)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08E amended effective November 2, 1987 (14:22 Md. R. 2340)</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised effective April 21, 2008 (35:8 Md. R. 809)</annotation>
  </annotations>
</chapter>