<regulation prefix="Regulation" num=".03" citation="COMAR 20.56.02.03" title_num="20" subtitle_num="56" chapter_num="02" heading="Required Tests.">
  <paragraph num="A.">
    <text>General. Any meter test required by this regulation shall be made at both check flow and full rated flow.</text>
  </paragraph>
  <paragraph num="B.">
    <text>Preinstallation Test.</text>
    <paragraph num="(1)">
      <text>Meter Accuracy.</text>
      <paragraph num="(a)">
        <text>Except as provided in §B(3) of this regulation, the owner shall test a meter for accuracy before the meter is placed in service.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The date of the accuracy test shall be within 2 years of the date the meter is placed in service.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Leak Test. An owner shall test a meter for leaks before the meter is placed in service.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Sample Testing New Meters. An owner may sample test new meters for accuracy in accordance with a sample plan approved by the Commission.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Request Test.</text>
    <paragraph num="(1)">
      <text>Request for Test. Upon request by a customer and at no charge, the owner shall test the accuracy of the meter and associated metering device, if installed, serving the customer. A test under this subsection need not be made more often than once in 18 months.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Customer May Observe. The customer, or the customer's representative, may be present when the test is performed.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Report to Customer. A report of the results of the test shall be made to the customer within a reasonable time after the completion of the test, and a record of the report, together with a complete record of the test, shall be kept on file at the office of the owner for at least 3 years.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Referee Test.</text>
    <paragraph num="(1)">
      <text>Application for Test. Upon written application to the Commission by a customer or an owner, an accuracy test shall be made of the customer's meter and associated metering device, if installed, as soon as practicable by a representative of the Commission. A test under this subsection need not be made more often than once in 18 months.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Deposit for Test. The application under §D(1) of this regulation shall be accompanied by a $10 deposit.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Notice to Owner. On receipt of a request from a customer, the Commission shall notify the owner and the owner may not knowingly remove or adjust the meter and associated metering device, if installed, unless instructed by the Commission. The owner shall furnish to the Commission's representative reasonable assistance if required to make the test.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Customer May Observe. The customer, or the customer's representative, may be present when the test is performed.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Report to Customer. A written report of the results of the test shall be sent to the customer and to the owner.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>Disposition of Deposit. If the accuracy test shows an over-registration of more than 2 percent at check flow, a deposit shall be refunded by the Commission and the owner billed the amount of the deposit. If the accuracy test shows an under-registration or an over-registration of 2 percent or less at check flow, the Commission shall retain the deposit.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>In-Service Performance Test.</text>
    <paragraph num="(1)">
      <text>An owner shall prepare and submit to the Commission an in-service performance plan.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The Commission shall approve an owner's in-service performance plan before its implementation.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>An owner shall perform an in-service accuracy test of meters and associated metering devices, if installed, on a periodic interval or variable interval basis.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Report.</text>
      <paragraph num="(a)">
        <text>An owner shall prepare a report showing all in-service performance tests conducted during a calendar year.</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The owner shall submit the report to the commission by April 1 of the following year.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>As Found Test. An owner shall test a meter before adjustment, repair, or retirement.</text>
  </paragraph>
  <paragraph num="G.">
    <text>As Left Test. If a meter does not meet the accuracy requirements of Regulation .04A of this chapter, an owner shall adjust, repair, or both, and test the meter for accuracy before returning it to service.</text>
  </paragraph>
</regulation>