<chapter num="03" heading="Renewable Energy Credit" title_num="20" subtitle_num="61">
  <regulation prefix="Regulation" num=".01" heading="RPS Eligible REC.">
    <paragraph num="A.">
      <text>Except as provided under Regulation .03 of this chapter, a Maryland-eligible REC shall be recorded with GATS.</text>
    </paragraph>
    <paragraph num="B.">
      <text>If not required by GATS, the REC recordation under §A of this regulation shall include:</text>
      <paragraph num="(1)">
        <text>The name of the Maryland certified renewable energy facility;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A description of the renewable source of generation for the REC;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The month and year of the generation of the energy represented by the REC; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Tier 1 renewable source or Tier 2 renewable source associated with the REC.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>A Maryland eligible REC issued to a renewable on-site generator under this regulation is valid for compliance for the calendar year of generation and the following 2 calendar years.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="REC Creation from Renewable On-Site Generation.">
    <paragraph num="A.">
      <text>Except under §C of this regulation, a renewable on-site generator may receive a Maryland-eligible REC associated with on-site generation if:</text>
      <paragraph num="(1)">
        <text>The renewable on-site generator is certified as a renewable energy facility under COMAR 20.61.02;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>An authorized representative of the renewable on-site generator enters its generation data at least annually in a GATS account maintained in good standing; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>An authorized representative of the non-solar renewable on-site generator files a non-solar renewable on-site generator report with the Commission under §B of this regulation within 1 week of each recording with GATS.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The non-solar renewable on-site generator report required under §A of this regulation shall be on a form provided by the Commission.</text>
    </paragraph>
    <paragraph num="C.">
      <text>A Level 1 solar renewable energy facility may receive a Maryland-eligible REC associated with on-site generation based on the schedule established by the Commission derived from Commission certified engineering estimates under COMAR 20.61.02 if:</text>
      <paragraph num="(1)">
        <text>The Level 1 solar facility is certified as a renewable energy facility under COMAR 20.61.02; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Level 1 solar facility or its authorized representative enters generation data into a GATS.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>A Maryland-eligible REC issued to a renewable on-site generator under this regulation is considered issued only upon its recording with GATS.</text>
    </paragraph>
    <paragraph num="E.">
      <text>A Maryland-eligible REC issued to a renewable on-site generator under this regulation is valid for compliance for the calendar year of generation and the following 2 calendar years.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Creation of RECs Based on Generation Not Delivered Into the PJM Region.">
    <text>A supplier may request recognition of a REC associated with a Tier 1 renewable source or Tier 2 renewable source not delivered into the PJM region under the following conditions:</text>
    <paragraph num="A.">
      <text>The electricity is generated at a facility that has been certified by the Commission under COMAR 20.61.02;</text>
    </paragraph>
    <paragraph num="B.">
      <text>One of the following:</text>
      <paragraph num="(1)">
        <text>Certification by the operator of the control area in which the facility is located of the total number of megawatt-hours (MWhs) generated at the facility by month and calendar year; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If the operator of the control area is unable to make the certification under §B(2)(a) of this regulation:</text>
        <paragraph num="(a)">
          <text>An affidavit from the operator of the control area attesting that the operator is unable to certify the total number of megawatt-hours generated by the named applicant facility for the specific year in question; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A certification by the applicant of the total number of megawatt-hours generated at the facility for each calendar year;</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Certification by the authorized representative of the facility that the RECs associated with the electricity have not expired or been retired, transferred, or redeemed; and</text>
    </paragraph>
    <paragraph num="D.">
      <text>The electricity is generated within the PJM Region or in a state adjacent to the PJM control area.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="GATS — Maryland REC Designation.">
    <text>If a renewable energy facility is approved by the Commission under COMAR 20.61.02 and the facility's GATS account continues to be maintained in good standing, the renewable energy facility may achieve a Maryland designation for a Tier 1 renewable source or Tier 2 renewable source REC recorded with GATS before the Commission's approval of the facility only during the calendar year of the Commission's approval.</text>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Decertified Renewable Energy Facility.">
    <text>Any REC transferred or sold to a supplier, including a Level 1 solar REC transferred under COMAR 20.61.01.05C(1), before the date of decertification of the renewable energy facility where the REC was created shall remain Maryland-eligible.</text>
  </regulation>
  <annotations>
    <annotation type="Authority">Public Utilities Article, §§2-121, 5-101, and 7-701—7-713, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date:</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .01—.06 adopted as an emergency provision effective July 1, 2005 (32:18 Md. R. 1517); adopted permanently effective November 24, 2005 (32:23 Md. R. 1829)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01 amended as an emergency provision effective April 1, 2008 (35:9 Md. R. 895); amended permanently effective May 5, 2008 (35:9 Md. R. 899)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02 amended as an emergency provision effective April 1, 2008 (35:9 Md. R. 895); amended permanently effective May 5, 2008 (35:9 Md. R. 899)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02B amended effective January 1, 2007 (33:26 Md. R. 1998)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03 amended as an emergency provision effective April 1, 2008 (35:9 Md. R. 895); amended permanently effective May 5, 2008 (35:9 Md. R. 899)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04 amended as an emergency provision effective April 1, 2008 (35:9 Md. R. 895); amended permanently effective May 5, 2008 (35:9 Md. R. 899)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04A amended effective January 1, 2007 (33:26 Md. R. 1998)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05 amended as an emergency provision effective April 1, 2008 (35:9 Md. R. 895); amended permanently effective May 5, 2008 (35:9 Md. R. 899)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06 amended effective December 1, 2008 (35:24 Md. R. 2079); August 10, 2009 (36:16 Md. R. 1251)</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised effective September 20, 2010 (37:19 Md. R. 1285)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02A, B amended effective March 18, 2013 (40:5 Md. R. 412)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02B amended effective July 8, 2013 (40:13 Md. R. 1076)</annotation>
  </annotations>