<regulation prefix="Regulation" num=".17" citation="COMAR 20.61.06.17" title_num="20" subtitle_num="61" chapter_num="06" heading="Extension of OREC Price Schedule Beyond the Term.">
  <paragraph num="A.">
    <text>Each qualified offshore wind project shall report all of the following information to the Commission within 2 years before the expiration of the term of an OREC price schedule:</text>
    <paragraph num="(1)">
      <text>Anticipated PJM revenues for the project for the 5-year period immediately following expiration of the term of the OREC price schedule; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Anticipated project operating costs for the project for the 5-year period immediately following expiration of the term of the OREC price schedule.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Each qualified offshore wind project shall report all of the following information to the Commission within 2 years of expiration of an additional 5-year term extended under Public Utilities Article, §7-704.2(d), Annotated Code of Maryland:</text>
    <paragraph num="(1)">
      <text>Anticipated PJM revenues for the project for the 5-year period immediately following expiration of the 5-year term extended under Public Utilities Article, §7-704.2(d), Annotated Code of Maryland; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Anticipated project operating costs for the project for the 5-year period immediately following expiration of the 5-year term extended under Public Utilities Article, §7-704.2(d), Annotated Code of Maryland.</text>
    </paragraph>
  </paragraph>