# COMAR Title 20 — Public Service Commission

## Subtitle 62 — Community Solar Energy Generation Systems

### Chapter 03 — Program Administration

#### Regulation .08 Project Location.

*COMAR 20.62.03.08*

A. Except as provided in §B of this regulation, a community solar energy generating system may not be located on the same or an adjacent parcel of land as an existing or proposed community solar energy generating system if the total installed capacity of all community solar energy generating systems on the same or adjacent parcel would exceed 5 megawatts.

B. The prohibition under §A of this regulation does not apply to projects constructed:

  (1) On the rooftops of buildings;

  (2) In areas that are zoned for industrial use;

  (3) On brownfields locations and clean fill sites;

  (4) Over parking lots or roadways;

  (5) On multilevel parking structures;

  (6) On or over transportation or public rights-of -way;

  (7) At airports;

  (8) On land that:

    (a) Was previously zoned for industrial use or is ecologically compromised; and

    (b) Is not targeted for mitigation or restoration; or

  (9) In any location if the combined capacity of all community solar energy generating systems on the same or adjacent parcel does not exceed 10 megawatts and:

    (a) At least 75% of the aggregate capacity of the co-located community solar energy generating system serves LMI subscribers;

    (b) For a site without a community solar energy generating system installed before the start of the Program, all of the community solar energy generating systems installed after the start of the Program are used for agrivoltaics; or

    (c) For a site with a community solar energy generating system installed before the start of the Program, each new community solar energy generating system installed after the start of the Program is used for agrivoltaics.