# COMAR Title 20 — Public Service Commission

## Subtitle 63 — Community Choice Aggregation

### Chapter 20 — CCA Coordination Tariff

#### Regulation .02 Tariffs.

*COMAR 20.63.20.02*

A. Introduction of a CCA Coordination Tariff.

  (1) An electric company serving customers within Montgomery County shall, within 60 days after the Commission adopts the regulations for final publication, file with the Commission proposed tariff language to address the electric company’s interactions with a CCA for the duration of the Pilot.

  (2) An electric company may incorporate the tariff provisions required by this chapter in the company’s existing Electricity Supplier Coordination Tariff.

  (3) Each electric company serving accounts in Montgomery County shall coordinate with the other electric companies serving accounts in Montgomery County to propose consistent tariff provisions.

B. An electric company shall include at least the following terms and conditions in its tariff for CCA interactions:

  (1) Billing and payment collection;

  (2) Dispute resolution;

  (3) Financial settlement;

  (4) Losses;

  (5) Metering services;

  (6) PJM interconnection requirements;

  (7) Scheduling; and

  (8) Utility charges.