Regulation .01 Scope.

Regulation .01 Scope.Copy Citation

The regulations in this subtitle apply to:
A.
A person applying for a Certificate of Public Convenience and Necessity for the construction of a generating station, qualified generator lead line, or overhead transmission line, or modification to an existing electric generating station, or an overhead transmission line;
B.
A person requesting an exemption from the requirement to obtain a Certificate of Public Convenience and Necessity for the construction of a generating station under Regulation .03 of this chapter; or
C.
A person making a modification under Public Utilities Article, §7-205, Annotated Code of Maryland.