<regulation prefix="Regulation" num=".03" citation="COMAR 20.79.01.03" title_num="20" subtitle_num="79" chapter_num="01" heading="Exemption.">
  <paragraph num="A.">
    <text>A person may file an application for an exemption from the requirement to obtain a Certificate of Public Convenience and Necessity for the construction of a generating station if the person intends to construct a generating station which meets the requirements under Public Utilities Article, §7-207.1(a), Annotated Code of Maryland.</text>
  </paragraph>
  <paragraph num="B.">
    <text>An application for an exemption from the requirement to obtain a Certificate of Public Convenience and Necessity for the construction of a generating station under §A of this regulation shall be on a form provided by the Commission.</text>
  </paragraph>
  <paragraph num="C.">
    <text>Unless otherwise directed by the Commission, a decision on an application for an exemption from the requirement to obtain a Certificate of Public Convenience and Necessity for the construction of a generating station shall be rendered not later than 90 days from the date a complete application is filed.</text>
  </paragraph>