# COMAR Title 20 — Public Service Commission

## Subtitle 79 — Applications Concerning the Construction or Modification of Generating Stations, Qualified Generator Lead Lines, and Overhead Transmission Lines

### Chapter 01 — General

#### Regulation .07 Deadlines.

*COMAR 20.79.01.07*

A. Unless otherwise directed by the Commission, a decision on an application for a Certificate of Public Convenience and Necessity for the construction of an electric generating station shall be rendered not later than 365 days from the date a complete application is filed.

B. Unless otherwise directed by the Commission, a decision on an application for modification of an electric generating station shall be rendered not later than 150 days from the date a complete application is filed.