# COMAR Title 20 — Public Service Commission

## Subtitle 79 — Applications Concerning the Construction or Modification of Generating Stations, Qualified Generator Lead Lines, and Overhead Transmission Lines

### Chapter 01 — General

#### Regulation .11 Availability of Applications and Related Materials.

*COMAR 20.79.01.11*

The following documents shall be made available for public inspection at the offices of the Commission and on the Commission’s website:

A. A copy of the application for a Certificate of Public Convenience and Necessity for the construction of a generating station or transmission line, or an application for modification to an existing electric generating station or transmission line;

B. All written public comments received by the Commission concerning the application; and

C. Any comments and recommendations filed by a State agency or other parties concerning the application and received by the Commission.