<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".03" citation="COMAR 20.79.02.03" title_num="20" subtitle_num="79" chapter_num="02" heading="Proceedings on the Application.">
  <paragraph num="A.">
    <text>The Commission may hold hearings with any other state or local agency having jurisdiction to issue any permit, authority, or certificate that is required before construction or operation of a project can begin.</text>
  </paragraph>
  <paragraph num="B.">
    <text>In order to ensure timely completion of the proceedings, the Commission may impose a schedule of procedural dates which is subject to change only for good cause shown.</text>
  </paragraph>
  <paragraph num="C.">
    <text>Phased Proceeding Requests.</text>
    <paragraph num="(1)">
      <text>The applicant may request that the construction of a generating station be reviewed by the Commission in phases.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>If a phased proceeding is requested and the request is granted by the Commission:</text>
      <paragraph num="(a)">
        <text>An applicant may file a partial application; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The Commission may render separate findings of fact on any phase or issue within a phase.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>Findings of fact rendered by the Commission under this section are not subject to further litigation unless warranted by new substantive issues or changed circumstances.</text>
    </paragraph>
  </paragraph>
</regulation>