  <text>If the applicant is requesting authority to exercise a right of condemnation in connection with the construction of a generating station, a statement of the reasons the generating capacity is necessary to ensure a sufficient supply of electricity to customers in the State as required under Public Utilities Article, §7-207(b)(2), Annotated Code of Maryland.</text>