# COMAR Title 20 — Public Service Commission

## Subtitle 79 — Applications Concerning the Construction or Modification of Generating Stations, Qualified Generator Lead Lines, and Overhead Transmission Lines

### Chapter 04 — Details of Filing Requirements — Transmission Lines

#### Regulation .01 Purpose and Justification.

*COMAR 20.79.04.01*

A. An application for a proposed transmission line or modification to an existing transmission line shall include:

  (1) An explanation of the need for the project in meeting demands for service;

  (2) A description of the effect of the project on system stability and reliability;

  (3) A description of the consequences if the project is delayed or not approved;

  (4) An explanation of the cost effectiveness of the project, including an estimate of capital cost and annual operating cost; and

  (5) A description of the impact of the project on the economies of the State.

B. If requested by the Commission, an application for a proposed transmission line shall include a plan as defined under COMAR 20.79.01.02.