<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".01" citation="COMAR 20.79.04.01" title_num="20" subtitle_num="79" chapter_num="04" heading="Purpose and Justification.">
  <paragraph num="A.">
    <text>An application for a proposed transmission line or modification to an existing transmission line shall include:</text>
    <paragraph num="(1)">
      <text>An explanation of the need for the project in meeting demands for service;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>A description of the effect of the project on system stability and reliability;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>A description of the consequences if the project is delayed or not approved;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>An explanation of the cost effectiveness of the project, including an estimate of capital cost and annual operating cost; and</text>
    </paragraph>
    <paragraph num="(5)">
      <text>A description of the impact of the project on the economies of the State.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>If requested by the Commission, an application for a proposed transmission line shall include a plan as defined under COMAR 20.79.01.02.</text>
  </paragraph>
</regulation>