A. The description of each alternative route considered for the transmission line shall include:

  (1) An estimate of the capital and annual operating cost of each alternative route; and

  (2) A statement of the reason why each alternative route was rejected.

B. For modifications to existing transmission lines, alternative routes need not be evaluated.