# COMAR Title 21 — State Procurement Regulations

## Subtitle 03 — State Procurement Regulations and Contracts

### Chapter 01 — General Regulations

#### Regulation .02 Contracts Void for Noncompliance.

*COMAR 21.03.01.02*

A. Except as provided in Regulation .03 or elsewhere in this title, if a procurement violates this title, the procurement contract is void.

B. If a procurement contract is void under this regulation, the contractor shall be awarded compensation for actual expenses reasonably incurred under the contract, plus a reasonable profit if the contractor:

  (1) Has acted in good faith;

  (2) Did not directly contribute to a violation of this title; and

  (3) Had no knowledge of the violation before the procurement contract was awarded.