# COMAR Title 21 — State Procurement Regulations

## Subtitle 05 — Procurement Methods and Project Delivery Methods

### Chapter 08 — Mandatory Written Solicitation Requirements

#### Regulation .02 Bid Bond Notice.

*COMAR 21.05.08.02*

A. Solicitations for construction contracts reasonably expected by the procurement officer to exceed $100,000 shall contain notice of bid security requirements (See COMAR 21.06.07).

B. Solicitations for all other contracts reasonably expected by the procurement officer to exceed $50,000 and for which the procurement officer wishes to require bid security shall contain notice of the bid security requirements.

C. Notwithstanding §§A and B of this regulation, notice of bid security is required if a federal law or a condition of federal assistance for the contract requires it.