# COMAR Title 21 — State Procurement Regulations

## Subtitle 05 — Procurement Methods and Project Delivery Methods

### Chapter 10 — Construction Management at Risk

#### Regulation .03 Selection of the Construction Manager.

*COMAR 21.05.10.03*

A. Procurement agencies shall use the competitive sealed proposals procurement method under COMAR 21.05.03 to select the construction manager.

B. Procurement agencies shall obtain separate Board of Public Works approval for preconstruction services, regardless of dollar value, and each GMP that exceeds the Board delegations of procurement and contracting authority in COMAR 21.02.01.04.