Regulation .02 Determination on Use of the Design-Build Method.
Regulation .02 Determination on Use of the Design-Build Method.LinkCopy Citation
Before the solicitation is issued, the procurement officer shall prepare a written determination justifying the use of the design-build method which addresses some or all of the following criteria:
A.
The extent to which the unit can adequately define the project requirements;
B.
Time constraints for delivery of the project;
C.
Capability and experience of prospective contractors with the design-build method or similar experience;
D.
Suitability of the project for use of the design-build method of project delivery with respect to time, schedule, costs, and quality factors; and
E.
Capability of the agency to manage the project.