  <text>Before the solicitation is issued, the procurement officer shall prepare a written determination justifying the use of the design-build method which addresses some or all of the following criteria:</text>
  <paragraph num="A.">
    <text>The extent to which the unit can adequately define the project requirements;</text>
  </paragraph>
  <paragraph num="B.">
    <text>Time constraints for delivery of the project;</text>
  </paragraph>
  <paragraph num="C.">
    <text>Capability and experience of prospective contractors with the design-build method or similar experience;</text>
  </paragraph>
  <paragraph num="D.">
    <text>Suitability of the project for use of the design-build method of project delivery with respect to time, schedule, costs, and quality factors; and</text>
  </paragraph>
  <paragraph num="E.">
    <text>Capability of the agency to manage the project.</text>