  <text>Mandatory provision for all construction contracts:</text>
  <included-document>
    <text>"Changes</text>
    <text>"(1) The procurement officer unilaterally may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make any change in the work within the general scope of the contract, including but not limited to changes:</text>
  </included-document>