<?xml version='1.0' encoding='utf-8'?>
<chapter num="08" heading="Prompt Payment of Subcontractors" title_num="21" subtitle_num="10">
  <regulation prefix="Regulation" num=".01" heading="Definitions.">
    <paragraph num="A.">
      <text>In this chapter, the following terms have the meanings indicated.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Terms Defined.</text>
      <paragraph num="(1)">
        <text>Undisputed Amount.</text>
        <paragraph num="(a)">
          <text>“Undisputed amount” means an amount owed by a contractor to a subcontractor or supplier for which there is no good faith dispute, including any retainage withheld.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Undisputed amount” includes an amount withheld because of a dispute arising out of an agreement or occurrence unrelated to the agreement under which the amount is withheld.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>“Prime contractor” means a person or firm that has a State procurement contract with a unit.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Contractor.</text>
        <paragraph num="(a)">
          <text>“Contractor” means a person or firm that:</text>
          <paragraph num="(i)">
            <text>Has an agreement to perform all or some of the work required under a State contract; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Subcontracts with another person or firm for performance of all or some of the work required under the contract.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>“Contractor” includes a prime contractor and a subcontractor at any tier.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>“Subcontractor” means a person or firm that has an agreement with a contractor to perform all or some of the contractor's work under a State contract.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>“Supplier” has the same definition set forth in State Finance and Procurement Article. §15–226, Annotated Code of Maryland, and COMAR 21.01.02.01.B.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Policy.">
    <text>It is the policy of the State that a contractor shall promptly pay to a subcontractor or supplier any undisputed amount to which the subcontractor or supplier is entitled for work under a State procurement contract.</text>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Responsibilities.">
    <paragraph num="A.">
      <text>A contractor who receives a progress payment or a final payment shall pay a subcontractor or supplier an undisputed amount to which the subcontractor or supplier is entitled within 10 calendar days of receiving the payment.</text>
    </paragraph>
    <paragraph num="B.">
      <text>If a contractor withholds payment from a subcontractor or supplier within the time period in which the payment normally would be made, the contractor shall:</text>
      <paragraph num="(1)">
        <text>Notify the subcontractor or supplier in writing and state the reason why payment is being withheld;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Provide a copy of the notice to the prime contractor or supplier and, if different, to the person or firm that made the progress payment or final payment to the contractor; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Provide a copy of the notice to the procurement officer.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Written Notice of Nonpayment.</text>
      <paragraph num="(1)">
        <text>If a subcontractor or supplier does not receive a payment within the required time period, the subcontractor or supplier shall give written notice of the nonpayment to the procurement officer.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The notice shall:</text>
        <paragraph num="(a)">
          <text>Indicate the:</text>
          <paragraph num="(i)">
            <text>Name of the contractor and, if different, of the prime contractor;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Project under which the dispute exists; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Amount in dispute;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>Provide an itemized description on which the amount is based; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>If known, provide an explanation for any dispute concerning the payment not received.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Duties.">
    <paragraph num="A.">
      <text>Within 2 business days of receipt of written notice from a subcontractor or supplier, a representative of the unit designated by the procurement officer shall verbally contact the contractor that withheld payment to ascertain whether the amount withheld is an undisputed amount.</text>
    </paragraph>
    <paragraph num="B.">
      <text>If the representative of the unit determines that a part or all of the amount withheld is an undisputed amount, the representative of the unit shall instruct the contractor that withheld payment to pay the subcontractor or supplier the undisputed amount within 3 business days. The instruction shall be confirmed in writing.</text>
    </paragraph>
    <paragraph num="C.">
      <text>The representative of the unit shall verbally communicate to the subcontractor or supplier the results of discussions with the contractor that withheld payment.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Actions.">
    <paragraph num="A.">
      <text>If the contractor fails to pay the subcontractor or supplier the undisputed amount within the time instructed to do so under Regulation .04B of this chapter, the subcontractor or supplier may report the nonpayment in writing to the procurement officer.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Meeting.</text>
      <paragraph num="(1)">
        <text>If the subcontractor or supplier notifies the procurement officer in writing under §A of this regulation that payment has not been made, the representative of the unit shall schedule a meeting to discuss the dispute with the unit's project manager, the contractor, the subcontractor or supplier, and any other person or entity that the representative considers to have an interest in the matter:</text>
        <paragraph num="(a)">
          <text>At a time and location designated by the representative of the unit; but</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Not later than 10 calendar days after receiving written notice from the subcontractor or supplier under §A of this regulation.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The purpose of the meeting is to establish why the contractor has not paid the subcontractor or supplier in the required time period.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The representative of the unit shall require the parties to provide at the meeting any information that the representative believes necessary to evaluate the dispute.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The procurement officer may require the parties to submit documentation that the procurement officer deems appropriate.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".06" heading="Remedies.">
    <paragraph num="A.">
      <text>If the representative of the unit determines that the contractor is delinquent in payment of an undisputed amount to the subcontractor or supplier, the representative may order that further progress payments to the contractor that withheld payment shall be withheld until the subcontractor or supplier is paid.</text>
    </paragraph>
    <paragraph num="B.">
      <text>If payment is not paid to the subcontractor or supplier within 7 business days after the representative of the unit determines that the contractor is delinquent in paying the subcontractor or supplier under §A of this regulation, the representative shall schedule a second meeting to address the dispute:</text>
      <paragraph num="(1)">
        <text>At a time and location designated by the representative of the unit; but</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Not later than 5 business days after the close of the 7-day period.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>If, at the completion of the second meeting, the representative of the unit determines that the contractor continues to be delinquent in payments owed to the subcontractor or supplier, the representative:</text>
      <paragraph num="(1)">
        <text>Shall order that further payments to the contractor not be processed until payment to the subcontractor or supplier is verified;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>May order that all or some of the work under the contract or subcontract be suspended without affecting the contractually required completion date for the work, based on the failure of the contractor to meet obligations under the contract;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If the contractor is not a prime contractor, may order that the prime contractor act as a representative of the unit and:</text>
        <paragraph num="(a)">
          <text>Pay or cause payment of an amount determined as undisputed, together with any penalty assessed against the contractor under §C(4) of this regulation, to be made to the subcontractor or supplier from monies otherwise due or that may become due under the State contract for the contractor’s work;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>From monies otherwise due or that may become due under the State contract for the contractor's work, place a payment for an undisputed amount and any penalty in an interest-bearing escrow account rather than making the payment to the subcontractor or supplier; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Take other or further actions to resolve the dispute; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Subject to §D of this regulation, may order that the contractor pay a penalty to the subcontractor or supplier, in an amount not exceeding $100 per day, from the date that payment was required under Regulation .04B of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>A penalty may not be imposed under §C(3) of this regulation for any period that the representative of the unit determines the subcontractor or supplier was not diligent in reporting nonpayment to the procurement officer.</text>
    </paragraph>
    <paragraph num="E.">
      <text>A prime contractor and each contractor to whom an instruction or order is directed under this regulation shall comply with the instruction or order.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Appeal.">
    <paragraph num="A.">
      <text>A contractor or a subcontractor or supplier may appeal a decision under Regulation .06C of this chapter to the procurement officer.</text>
    </paragraph>
    <paragraph num="B.">
      <text>The contractor shall comply with the procurement officer's decision.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="Decision.">
    <paragraph num="A.">
      <text>An act, failure to act, or decision of a procurement officer or a representative of a unit, concerning a payment dispute between a contractor and subcontractor or supplier under this chapter, may not:</text>
      <paragraph num="(1)">
        <text>Affect the rights of the contracting parties under any other provision of law;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Be used as evidence on the merits of a dispute between the unit and the contractor or the contractor and the subcontractor or supplier in any other proceeding; or</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Result in liability or prejudice the rights of the unit or a prime contractor that acts as a representative of a unit under Regulation .06C(3) of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>A decision of a procurement officer or a representative of the unit designated by the procurement officer under this chapter is not subject to judicial review or the provisions of COMAR 21.10.04.</text>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">State Finance and Procurement Article, §15-226, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: October 2, 2000 (27:19 Md. R. 1730)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01 amended effective July 9, 2001 (28:13 Md. R. 1216); September 18, 2023 (50:18 Md. R. 800)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01B amended effective March 3, 2025 (52:4 Md. R. 221)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02 amended effective September 18, 2023 (50:18 Md. R. 800); March 3, 2025 (52:4 Md. R. 221)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03 amended effective July 9, 2001 (28:13 Md. R. 1216); March 3, 2025 (52:4 Md. R. 221)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04 amended effective July 9, 2001 (28:13 Md. R. 1216); March 3, 2025 (52:4 Md. R. 221)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .045 amended effective March 3, 2025 (52:4 Md. R. 221)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .05B amended effective July 9, 2001 (28:13 Md. R. 1216)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06 amended effective July 9, 2001 (28:13 Md. R. 1216); September 18, 2023 (50:18 Md. R. 800); March 3, 2025 (52:4 Md. R. 221)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .07A amended effective March 3, 2025 (52:4 Md. R. 221)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08A amended effective July 9, 2001 (28:13 Md. R. 1216); March 3, 2025 (52:4 Md. R. 221)</annotation>
  </annotations>
</chapter>