<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".05" citation="COMAR 26.03.04.05" title_num="26" subtitle_num="03" chapter_num="04" heading="Review and Evaluation.">
  <paragraph num="A.">
    <text>Applications for grants under section 5.2(a) of Chapter 55 shall be reviewed by the Water Management Administration. The review shall include the following:</text>
    <paragraph num="(1)">
      <text>An evaluation to determine that:</text>
      <paragraph num="(a)">
        <text>The project is ineligible for a federal grant; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>A timely and sufficient federal grant is not available.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>The Secretary shall submit a copy of the grant application and supporting material to the A-95 clearinghouse for review and comment.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>A determination of the amount of grant funds necessary to permit the project to proceed. These funds may not exceed 87-1/2 percent of the eligible construction cost.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>A recommendation to the Secretary of the Environment which shall indicate a course of action to be taken.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>The Secretary shall:</text>
    <paragraph num="(1)">
      <text>Approve the application and send a letter of recommendation to the Board of Public Works for approval of State grant funds for the project;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Reject the application either because it is not suitable under the “Water Quality Loan of 1973” or does not have high enough priority to qualify under section 5.2(a); or</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Cause the return of the application with a request for additional information required by him.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>When the State grant is approved by the Board of Public Works, the Secretary shall give notification to the applicant that preparation of contract plans and specifications may proceed for review by his staff and the federal agency, if any, before issuing a construction permit required by Environment Article, §9-204, Annotated Code of Maryland.</text>
  </paragraph>
</regulation>