  <paragraph num="A.">
    <text>The applicant shall complete a preapplication form supplied by the Department which shall include:</text>
    <paragraph num="(1)">
      <text>Type and general description of the stormwater pollution control practice to be used;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Project location, existing and proposed land use, ownership, drainage area, topography, and soil characteristics;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Approximate cost, based on accepted engineering judgment;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Approximate project implementation schedule;</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Location of any water supply in immediate vicinity;</text>
    </paragraph>
    <paragraph num="(6)">
      <text>Adjacent watercourse and structures.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>The applicant shall forward the preauthorization form to the Department within 60 days of the adoption of this regulation.</text>
  </paragraph>
  <paragraph num="C.">
    <text>Within 45 days after the receipt of the preapplication form, the Department shall notify the applicant as to whether its preapplication is approved or disapproved.</text>
  </paragraph>
  <paragraph num="D.">
    <text>Departmental approval of the preapplication form assures placement on the priority list, although not necessarily within the fundable range.</text>
  </paragraph>
  <paragraph num="E.">
    <text>If the preapplication is approved, the applicant will be notified of the project's position on the priority list and the availability of funding.</text>
  </paragraph>