<regulation prefix="Regulation" num=".03" citation="COMAR 26.03.10.03" title_num="26" subtitle_num="03" chapter_num="10" heading="Project Eligibility.">
  <paragraph num="A.">
    <text>Project costs which are eligible for financial assistance under this chapter may include:</text>
    <paragraph num="(1)">
      <text>The acquisition of new facilities;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The construction of new facilities;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Additions to, or modifications of, existing facilities;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Equipment purchases; and</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Lands, easements, and rights-of-way.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Project costs which may not be funded, except as provided for in §C, of this regulation, include:</text>
    <paragraph num="(1)">
      <text>Feasibility studies;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Planning;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Administrative costs and overhead; or</text>
    </paragraph>
    <paragraph num="(4)">
      <text>Plans and specifications.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Project costs outlined in §B, of this regulation, may be funded if the:</text>
    <paragraph num="(1)">
      <text>Secretary determines that the applicant does not have the financial capability to produce the necessary feasibility studies, plans, and specifications; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Applicant is requesting financial assistance in the form of a loan or a loan guarantee.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>The award of a loan or loan guarantee does not eliminate the requirement that the applicant obtain all required permits for a solid waste processing or disposal facility. The applicant shall remain liable for repayment of all applicable loans regardless of whether a permit is issued or the facility becomes operational.</text>
  </paragraph>
  <paragraph num="E.">
    <text>Allowances. The additional costs permitted in §C, of this regulation, may not exceed the percent of the total project cost as interpolated from Tables 1 and 2. State participation for these costs shall require a bona fide commitment from the applicant that construction of the proposed project will begin within 2 years.</text>
  </paragraph>
</regulation>