<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".06" citation="COMAR 26.03.12.06" title_num="26" subtitle_num="03" chapter_num="12" heading="Major Sewerage System Application and Permit Fees.">
  <paragraph num="A.">
    <text>Exception. Notwithstanding §§B—E of this regulation and Regulation .09 of this chapter, and in the discretion of the Department, fees for minor improvements or revisions to existing permits may be waived or reduced.</text>
  </paragraph>
  <paragraph num="B.">
    <text>Application and Permit Fees. An applicant for a permit to install, materially alter, or materially extend a major sewerage system shall pay the sum of the applicable fees set forth in the fee schedules in §§C—E of this regulation.</text>
  </paragraph>
  <paragraph num="C.">
    <text>Sewage Treatment Plants.</text>
    <paragraph num="(1)">
      <text>Fees for a new plant and fees for an existing plant at which two or more new unit processes are to be constructed are as follows:</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Fees for an existing plant at which only one new unit process is to be constructed are as follows:</text>
    </paragraph>
    <paragraph num="(3)">
      <text>If no fee is due under §C(1) or (2) of this regulation, the fee shall be the lesser of the:</text>
      <paragraph num="(a)">
        <text>Amount listed in §C(2) of this regulation for the design capacity of the particular plant; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Sum of the following:</text>
        <paragraph num="(i)">
          <text>$125 for each unit process that is installed, materially altered, or materially extended, plus</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>$125 for each component, which is not part of a unit process, that is installed, materially altered, or materially extended.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>In §C(3)(b) of this regulation, examples of components which are not part of a unit process include bar screens, comminutors, splitter boxes, flow meters, sludge holding tanks, and sludge drying beds.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Sewage Collection Lines.</text>
    <paragraph num="(1)">
      <text>Fees for new lines and material alterations and material extensions to existing lines are set forth in §D(2) and (3) of this regulation. Sewage treatment plant and pumping station fees are additional.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Fees for sewage collection lines and appurtenances are as follows:</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Pumping Stations.</text>
    <paragraph num="(1)">
      <text>Fees for new pumping stations and for material alterations and material extensions to existing pumping stations are set forth in the following fee schedule:</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The combined design capacity of all lift stations applied for under the permit shall be used in calculating the design capacity.</text>
    </paragraph>
  </paragraph>
</regulation>