<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".08" citation="COMAR 26.03.12.08" title_num="26" subtitle_num="03" chapter_num="12" heading="As-Constructed Plans.">
  <text>Within 60 days after the completion of the work under a permit, the holder of the permit shall submit to the Department, for permanent record, a copy of the plans, with a certification satisfactory to the Department, that shows the work as built, or a certification satisfactory to the Department that the work was built in accordance with the original plans approved by the Department.</text>