  <paragraph num="A.">
    <text>Permit Application Requirements. To obtain a permit to construct or operate a land clearing debris landfill, an applicant shall submit eight copies of the following information:</text>
    <paragraph num="(1)">
      <text>A completed and signed application on a form provided by the Department.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>A U.S.G.S. 7.5 minute quadrangle map with the proposed site outlined.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>A topographic map which is an accurate depiction of the site at the time of the application, prepared to a scale not smaller than 1 inch equals 200 feet, which depicts the property boundaries, on site buildings and structures, and obvious surficial features including, but not limited to:</text>
      <paragraph num="(a)">
        <text>Springs;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Seeps;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Streams;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Rock outcrops;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>Sink holes;</text>
      </paragraph>
      <paragraph num="(f)">
        <text>Surface impoundments;</text>
      </paragraph>
      <paragraph num="(g)">
        <text>Water wells;</text>
      </paragraph>
      <paragraph num="(h)">
        <text>100-year flood plain;</text>
      </paragraph>
      <paragraph num="(i)">
        <text>Forested and other vegetated areas; and</text>
      </paragraph>
      <paragraph num="(j)">
        <text>The location of any buried or overhead power transmission lines, utility pipelines, or storage tanks on the property.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(4)">
      <text>A discussion of the geologic formations directly underlying and in close proximity to the site which shall include a review of their effect on the factors set forth in Regulation .03A of this chapter.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>A map depicting the planned final grades of the site after completion of landfilling activities.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>A discussion of the projected future use of the landfilled area.</text>
    </paragraph>
    <paragraph num="(7)">
      <text>A description of the types of solid waste which will be accepted, and a discussion as to how unacceptable wastes which are delivered to the site will be segregated and handled before final disposal.</text>
    </paragraph>
    <paragraph num="(8)">
      <text>The anticipated quantities of solid waste which will be accepted and the calculations used to determine the useful life of the facility.</text>
    </paragraph>
    <paragraph num="(9)">
      <text>The volume and type of available cover material, the calculated volume of earth needed for daily, intermediate, and final cover, the location of earth stockpiles, and provisions for saving topsoil for use as top dressing.</text>
    </paragraph>
    <paragraph num="(10)">
      <text>Proposed means of controlling unauthorized access to the site.</text>
    </paragraph>
    <paragraph num="(11)">
      <text>Proposed operating procedures including:</text>
      <paragraph num="(a)">
        <text>Hours and days of operation;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Number and types of equipment to be used;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Number of employees and their duties;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Listing of qualifications that demonstrate employees can fulfill the duties submitted by the applicant as required in §A(11)(c) of this regulation;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>Provisions for fire prevention and control;</text>
      </paragraph>
      <paragraph num="(f)">
        <text>Means of preventing public health hazards and nuisances from vermin, noise, dust, and odors; and</text>
      </paragraph>
      <paragraph num="(g)">
        <text>Proposed method of daily operation including wet weather operation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(12)">
      <text>The location and depth of solid waste cells and the sequence of filling.</text>
    </paragraph>
    <paragraph num="(13)">
      <text>Methods of controlling on-site drainage, drainage leaving the site, and drainage onto the site from adjoining areas. Erosion and sediment control provisions shall be approved by the local soil conservation district or the appropriate approving authority, and satisfy the requirements of Environment Article, Title 4, Subtitle 1, and COMAR 26.09.01.</text>
    </paragraph>
    <paragraph num="(14)">
      <text>Proposed methods for covering and stabilizing completed areas.</text>
    </paragraph>
    <paragraph num="(15)">
      <text>Other information considered necessary by the Department to evaluate the adequacy of a site.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Plan Review.</text>
    <paragraph num="(1)">
      <text>Following receipt of the specified number of copies of the required information, the Department shall distribute one copy to each of the persons or agencies specified in Regulation .06C(1)(a)—(g) and(i)—(k) of this chapter.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>A person receiving a copy of the application and supporting information shall be requested by the Approving Authority to submit comments to the Approving Authority within 20 days of receipt of the application.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Following receipt of complete plans and specifications, the Approving Authority shall set a date, time, and place for a joint plan review meeting with interested agencies and the applicant.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>When practicable, within 60 days following this meeting, the Approving Authority shall either deny the permit or determine if:</text>
      <paragraph num="(a)">
        <text>Sufficient information is available to schedule a public hearing on the request for a permit; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Revisions to the plans and specifications are needed.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(5)">
      <text>If the Department is unable to complete the review within the established 60-day time schedule, the Department shall notify the applicant in writing within 30 days of receipt of the information and inform the applicant of the anticipated time required to complete the review.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Public Hearing. Before issuing a refuse disposal permit for a sanitary landfill to accept land clearing debris, a public hearing shall be conducted in accordance with the provisions of Regulation .09A of this chapter.</text>
  </paragraph>
  <paragraph num="D.">
    <text>Deed Amendment and Bonding Requirement. Before issuance of a permit for a sanitary landfill for land clearing debris, the applicant shall submit proof:</text>
    <paragraph num="(1)">
      <text>That the deed pertaining to the site in question has been amended to stipulate, upon close-out of this operation, that construction on this site may not begin without first obtaining written authorization from the Approving Authority.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Of the bonding as required by Environment Article, §9-211(c), Annotated Code of Maryland.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Consistency with the County Solid Waste Plan. Before issuance of the permit the applicant shall provide:</text>
    <paragraph num="(1)">
      <text>A statement from the appropriate local governmental agency concerning the consistency of the proposed facility with the approved county comprehensive solid waste management plan. If the local government fails to provide a response within 60 days of receipt of a request for a statement, a copy of the certified letter to the county requesting a statement shall be deemed to satisfy this requirement;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Proof that the facility is consistent with the approved county comprehensive solid waste management plant.</text>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>Periodic Reports to Approving Authority. An annual written report shall be submitted to the Approving Authority concerning the status of the landfill. This report shall be submitted not later than 60 days following the date specified in the permit and shall as a minimum include the:</text>
    <paragraph num="(1)">
      <text>Quantity of solid waste received per month during each of the preceding 12 months. Quantities shall be given in tons and in-place cubic yards.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Percentage of total capacity of the landfill used for emplacement of solid waste.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Projected date at which the landfill will reach capacity, and the premises upon which this determination is made.</text>
    </paragraph>
  </paragraph>
  <paragraph num="G.">
    <text>Other Requirements. The Approving Authority may impose other requirements considered necessary to protect the public health and the environment, or to prevent nuisance conditions.</text>
  </paragraph>