  <regulation prefix="Regulation" num=".01" heading="Discharge Permits Required.">
    <paragraph num="A.">
      <text>Issuance of Discharge Permits. The Department shall issue State discharge permits or NPDES permits in accordance with provisions and conditions of COMAR 26.08.01—26.08.04 and 26.08.08, to satisfy the regulatory requirements of the National Pollutant Discharge Elimination System (NPDES), established under the Federal Act.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Activities for Which Discharge Permits Are Required. A person may not commit any of the following acts except as authorized by a discharge permit issued by the Department:</text>
      <paragraph num="(1)">
        <text>Except as provided in COMAR 26.08.02.09A(3) and Regulation .08 of this chapter, discharge into the waters of this State any waste or wastewater regardless of volume.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Construct, install, modify, extend, alter, or operate any system for the disposal of waste or wastewater into the waters of the State, or a system which may result in a discharge into these waters, regardless of quality or volume, with the exception of storm water runoff that is not regulated under the Federal Act.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Increase or otherwise modify in volume, temperature, or concentration, any existing waste or wastewater in excess of the discharges authorized by any existing discharge permit. To the extent that the modification is in excess of limits specified in a discharge permit, the permittee shall report the change to the Department within 1 week of the commencement of the modification. This report shall include information on what, how, and why modifications were made and whether they will be temporary or permanent.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Construct, install, or operate any industrial, commercial, or other establishment or any extension or modification or addition to them, including the construction or use of any new discharge outlet, the construction, installation, or operation of which would cause an increase in the discharge of waste or wastewater into the waters of the State or otherwise alter the physical, chemical, or biological properties of any waters of the State in any manner not lawfully authorized.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-1" heading="Discharge Permit Application.">
    <paragraph num="A.">
      <text>Application Required.</text>
      <paragraph num="(1)">
        <text>Persons engaged or planning to engage in activities requiring a discharge permit shall file a complete application:</text>
        <paragraph num="(a)">
          <text>Not less than 180 days in advance of the date on which the discharge permit is desired to commence the activities; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>In sufficient time before the commencement of activities to ensure compliance with provisions of appropriate State and federal laws and regulations.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Permittees holding an active discharge permit shall file an updated application not less than 180 days in advance of the expiration date on that discharge permit.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Permittees no longer engaging in activities requiring a discharge permit shall notify the Department of the change in status of their facility within 30 days of ceasing the actions requiring a discharge permit.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Requirements.</text>
      <paragraph num="(1)">
        <text>Applications shall be made on the appropriate State discharge or NPDES application forms.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The following information shall be submitted with the completed application:</text>
        <paragraph num="(a)">
          <text>Name of any affiliate;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Permit numbers for any State discharge or NPDES permits presently held by the applicant or his affiliate;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Identification of administrative complaints or orders, if any, against the operation of the applicant or his affiliate; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The location of all sites involved in the storage of solid or liquid waste and the ultimate disposal sites of solid or liquid waste from any treatment system.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>If the discharge is from a new facility, preliminary plans and specifications, sufficiently adequate in scope and form to enable the Department to evaluate the proposed facility, shall be submitted with the application.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Department may require that an applicant for a discharge permit provide additional reports, specifications, plans, or other information on the existing or proposed pollution control program, including a material balance if considered necessary.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Required Signatures. The application for a State discharge or NPDES permit shall be signed by a responsible official, as follows:</text>
        <paragraph num="(a)">
          <text>For a corporation, by a responsible corporate officer such as:</text>
          <paragraph num="(i)">
            <text>A president, secretary, treasurer, or vice-president of the corporation in charge of a principal business function, or any other person who performs similar policy or decision-making functions for the corporation; or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The manager of one or more manufacturing, production, or operating facilities employing more than 250 individuals or having gross annual sales or expenditures exceeding $25 million, in second-quarter 1980 dollars, if authority to sign documents has been assigned or delegated to the manager according to corporate procedures;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>For a partnership or sole proprietorship, by a general partner or the proprietor, respectively;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>For a municipal, State, or other public agency, by either a principal executive officer, ranking elected official, or other duly authorized employee; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>For a federal agency, by a principal executive officer that includes:</text>
          <paragraph num="(i)">
            <text>The chief executive officer of the agency, or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>A senior executive officer having responsibility for the overall operations of a principal geographic unit of the agency such as a regional administrator of the EPA.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Application Fee. Each application shall be accompanied by a fee in the amount established by the Department in Regulation .11 of this chapter. The Department shall inform the applicant of the applicable fee which shall be paid by check or money order, made payable to the Department.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Receipt of Application. Upon receipt of an application, the Department shall:</text>
      <paragraph num="(1)">
        <text>Notify the applicant that:</text>
        <paragraph num="(a)">
          <text>The application has been received;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The applicant is responsible for the cost of the public notice required under the provisions of this chapter and for transcripts from any informational meetings or public hearings;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The applicant or the applicant's representative may be required to attend all public informational meetings and public hearings;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Failure to pay the costs of public notification or failure to attend the public informational meetings or public hearings may result in the Department not approving the applicant's permit; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Publish according to §E of this regulation a notice of application that includes the following:</text>
        <paragraph num="(a)">
          <text>The name of the applicant;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The type of permit applied for;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The type of proposed discharge;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The volume of the proposed discharge;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The location of the proposed discharge;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>A statement that persons may review and copy the application or related material and the procedure for doing so;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>A statement that the Department shall hold an informational meeting, if a person makes a written request within 10 working days of the publication of the notice, and the procedure for requesting an informational meeting; and</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Other information the Department determines is necessary for adequate public notification.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Public Notice and Access to Information and Confidential Information.</text>
      <paragraph num="(1)">
        <text>The applicant shall pay the cost of all public notice required by this chapter.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>When this chapter requires publication of public notice, the Department shall publish or shall require the applicant to publish the notice at least once a week for 2 consecutive weeks in a daily or weekly newspaper of general circulation in the geographical area in which the proposed discharge is to be located.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Department may post or require the applicant to post the notice at the site of the proposed discharge or at public facilities in the geographical area of the proposed discharge.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Department shall maintain lists of persons, government agencies, and other concerned groups to which notice is sent concerning discharge permits.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The Department shall provide notice of an informational meeting or a public hearing by mail to each person requesting the meeting or hearing or to the person's authorized representatives.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The Department shall ensure that any State discharge or NPDES permit application and its supporting information, including any public comment concerning the application, shall be available to the public for inspection and copying.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>The Department shall provide facilities for the inspection of the State discharge or NPDES permit application and its supporting information and ensure that State employees respond to requests for inspection promptly without undue requirements or restrictions. The Department shall either:</text>
        <paragraph num="(a)">
          <text>Ensure that a machine or device for the copying of papers and documents is available for a reasonable fee; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Otherwise provide for, or coordinate with, copying facilities or services so that requests for copies of nonconfidential documents may be responded to promptly.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(8)">
        <text>Protection of Information.</text>
        <paragraph num="(a)">
          <text>Except for effluent data, the Department shall protect any information contained in an NPDES application, or other records, reports, or plans, as confidential upon a showing by a person that the information, if made public, would divulge methods or processes entitled to protection as the person's trade secrets.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>If the information being considered for confidential treatment is contained in an NPDES application, the Department shall forward this information to the EPA for concurrence in any determination of confidentiality.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>If the EPA determines that some or all of the information being considered for confidential treatment does not merit this protection, and communicates to the Department that it is the EPA decision not to concur in the withholding of the information, the Department shall:</text>
          <paragraph num="(i)">
            <text>Notify the applicant of EPA's decision; and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>After ascertaining that the applicant has exhausted or waived the EPA appeal process concerning confidentiality of business information, make available to the public, upon request, that information determined not to constitute trade secrets.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(9)">
        <text>Any information accorded confidential status, whether or not contained in an NPDES application, shall be disclosed, upon request, to an authorized EPA representative, who shall maintain the disclosed information as confidential.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-2" heading="Discharge Permit Application Processing.">
    <paragraph num="A.">
      <text>Informational Meetings.</text>
      <paragraph num="(1)">
        <text>Upon written request by a person within 10 working days of the publication of a notice of application for a discharge permit, the Department shall hold an informational meeting to discuss the application.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department also may hold an informational meeting or meetings at the Department's discretion.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The informational meeting may be cancelled if all persons who made timely written requests withdraw their requests before the meeting.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Department may require the applicant to attend all informational meetings and present information concerning the application.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>If an informational meeting is required, the Department shall publish or require the applicant to publish notice of the informational meeting, unless the notice of application contained a notice of the informational meeting. This notice shall:</text>
        <paragraph num="(a)">
          <text>Conform to the requirements of Regulation .01-1E of this chapter; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Contain:</text>
          <paragraph num="(i)">
            <text>The information required under Regulation .01D of this chapter,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The date, time, and location of the informational meeting, and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Other information the Department determines to be necessary for adequate public notice.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>When the notice of the informational meeting also contains a notice of public hearing, the first notice of public hearing shall be given at least 30 days before the hearing.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Tentative Determination.</text>
      <paragraph num="(1)">
        <text>Preparation of Tentative Determination and Fact Sheet.</text>
        <paragraph num="(a)">
          <text>After the Department receives the discharge permit application, the Department shall prepare a tentative determination, which shall include:</text>
          <paragraph num="(i)">
            <text>The name of the applicant;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>A proposal to issue or not issue the permit;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The type, volume, and location of the proposed discharge;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Proposed permit limitations and conditions;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>A brief explanation of the Department's tentative decision;</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>If applicable, a proposed schedule of compliance;</text>
          </paragraph>
          <paragraph num="(vii)">
            <text>A brief summary, if appropriate, concerning the development of a site-specific criterion, use of a biological or chemical translator for derivation of permit limits, or a temporary permit modification; and</text>
          </paragraph>
          <paragraph num="(viii)">
            <text>Other information the Department considers necessary.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>When the tentative determination is to issue a discharge permit, the tentative determination shall include a draft permit, which shall be available to the public for inspection and copying.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The Department shall prepare a fact sheet as required by the Federal Act for all proposed permits for major facilities.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Publication of Notice of Tentative Determination.</text>
        <paragraph num="(a)">
          <text>The Department shall publish or require the applicant to publish the notice of tentative determination according to Regulation .01-1E of this chapter.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The notice of tentative determination shall include:</text>
          <paragraph num="(i)">
            <text>The information in §B(1)(a) of this regulation;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The procedures for a person to review and copy the tentative determination, draft permit, or related material;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A statement allowing 30 days for public comment to the notice of tentative determination before the issuance of the final determination and the procedures for offering public comment;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>A statement that the Department shall hold a public hearing when a written request for a public hearing is made within 20 days of the publication of the notice of tentative determination and the procedure for making a written request for a public hearing; and</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Other information the Department considers necessary to ensure adequate public notice.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>When the notice of tentative determination also includes a notice of public hearing, the first notice of public hearing shall be given at least 30 days before the hearing.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Mailing List for the Notice of Tentative Determination and Fact Sheet.</text>
        <paragraph num="(a)">
          <text>The notice of tentative determination shall be mailed to any other state whose waters may be affected by the issuance of a permit, so that the affected state may submit written comments to the Department and to the EPA.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The notice of tentative determination and, if prepared, a fact sheet, shall be mailed, unless waived, to the appropriate district engineer of the U.S. Army Corps of Engineers, the U.S. Fish and Wildlife Service, and the National Marine Fisheries Service.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Upon written request by a person, the Department shall add the name of that person to a mailing list to receive a copy of the notice of tentative determination and fact sheet, if prepared, for a specific NPDES permit application.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Obligation of Discharger to Notify Department. A person who desires to apply for a site-specific criterion, biological translator, or chemical translator shall notify the Department before the later of the end of the comment period established:</text>
        <paragraph num="(a)">
          <text>In the notice of tentative determination; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>For the public hearing.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Public Hearing.</text>
        <paragraph num="(a)">
          <text>The Department shall schedule a public hearing on the tentative determination when a written request for a public hearing is made within 20 calendar days of the publication of the notice of tentative determination.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The Department may schedule a public hearing on a State discharge or NPDES permit at the Department's discretion.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The public hearing may be cancelled if all persons who made timely written requests withdraw the requests before the hearing.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The applicant, if requested by the Department, shall provide information concerning the application.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>If the Department requires the applicant to attend the public hearing, failure of the applicant to attend the hearing and present information may result in the Department not issuing the permit.</text>
        </paragraph>
        <paragraph num="(f)">
          <text>A person shall be given an opportunity to present information at the public hearing concerning the tentative determination.</text>
        </paragraph>
        <paragraph num="(g)">
          <text>The Department shall accept written comments for 5 calendar days after the date of the public hearing.</text>
        </paragraph>
        <paragraph num="(h)">
          <text>The applicant shall be responsible for the cost of preparing and obtaining a transcript of public hearings.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>Notice of Public Hearing.</text>
        <paragraph num="(a)">
          <text>If a public hearing is scheduled, a notice of the hearing shall be published according to Regulation .01-1E of this chapter. The first notice shall give a minimum of 30 days notice before the hearing.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The notice of public hearing shall include:</text>
          <paragraph num="(i)">
            <text>The name of the applicant;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The type of discharge permit to be discussed at the public hearing, including the volume of the proposed discharge;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The location of the proposed discharge;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>A brief description of the proposed permit conditions and limitations, proposed schedule of compliance, and any proposed special conditions including procedures for obtaining access to or copies of the tentative determination;</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Information concerning the date, time, and location of the public hearing; and</text>
          </paragraph>
          <paragraph num="(vi)">
            <text>Other information the Department determines to be necessary for adequate public notification.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>The Department shall provide the applicant with a copy of the notice of public hearing.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".01-3" heading="Discharge Permit Issuance and Contested Case Hearings.">
    <paragraph num="A.">
      <text>Final Determination.</text>
      <paragraph num="(1)">
        <text>If the Department is not required to prepare a final determination, the tentative determination shall be a final decision by the Department and a permit may be issued.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department shall prepare a final determination if:</text>
        <paragraph num="(a)">
          <text>Written comments adverse to the tentative determination are received by the Department within 30 days after publication of the notice of tentative determination;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Comments adverse to the tentative determination were received in writing at, or within 5 days after, a public hearing held according to Regulation .01-2B(5) of this chapter;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Comments adverse to the tentative determination were received orally at the public hearing conducted under this section and the Department prepared a transcript of the comments made at the hearing; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The final determination is substantively different from the tentative determination and all persons who may be aggrieved by the final determination have not waived, in writing, their right to request a contested case hearing.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Those persons, including applicants, who believe any condition of a draft permit is inappropriate or that the Department's tentative determination is inappropriate, shall raise all reasonably ascertainable issues and submit all reasonably available arguments and documents supporting their position by the close of the public comment period, including any public hearing, as established by this chapter.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Supporting materials which are submitted shall be included in full and may not be incorporated by reference, unless they are already part of the administrative record in the same proceeding, or consist of State or federal statutes and regulations, EPA documents of general applicability, or other generally available reference materials.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Those offering comments shall make supporting materials not already included in the administrative record available by submitting a complete copy of all supporting materials at the time they submit their comments, or, if this submission is not practical, as determined solely by the Department, comments shall identify the location of the supporting materials.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The final determination shall include:</text>
        <paragraph num="(a)">
          <text>The name of the applicant;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The type of discharge;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The location of the discharge;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The volume of the discharge;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A statement of the Department's final determination and a brief explanation of the Department's decision;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The permit limitations and conditions; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>A schedule of compliance, if applicable.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>The final determination shall be available to the public for inspection and copying according to Regulation .01-1E of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Notice of Final Determination.</text>
      <paragraph num="(1)">
        <text>When the Department is required to prepare a final determination under §A of this regulation, a notice of final determination shall be published according to Regulation .01-1E of this chapter.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The notice of final determination shall be published in the same newspapers as the notice of hearing.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The notice of final determination shall include:</text>
        <paragraph num="(a)">
          <text>The information contained in the final determination required by §A(3)(a)—(e) of this regulation, and any limitations, change in permit conditions, or schedule of compliance;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A statement that the notice of final determination is available for inspection and copying;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The procedure for inspection and copying of the final determination;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A statement that a person may request a contested case hearing to appeal a final determination if the person makes factual allegations with sufficient particularity to demonstrate that the person is aggrieved by the final determination and the final determination is:</text>
          <paragraph num="(i)">
            <text>Legally inconsistent with any provisions of law applicable to the final determination being challenged, or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Based upon an incorrect determination of a relevant and material fact;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>A statement that a person requesting a contested case hearing shall submit a written request for adjudication within 15 days after publication of the notice of final determination;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The procedure for requesting a contested case hearing; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Other information the Department determines to be necessary for adequate public notification.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Request for Contested Case Hearing.</text>
      <paragraph num="(1)">
        <text>A person may not request a contested case hearing based on, or in a contested case hearing may not challenge, a facility's compliance with zoning and land use requirements or conformity with a county plan issued under Environment Article, Title 9, Subtitle 5, Annotated Code of Maryland. This regulation does not prevent a party from contesting the compliance of the facility with zoning and land use or county plan requirements in any proceeding brought in accordance with or under any applicable local laws.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A person requesting a contested case hearing to appeal a final determination shall:</text>
        <paragraph num="(a)">
          <text>Submit a written request in the manner specified in the notice of final determination within 15 days after publication of the notice of final determination; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Provide documentation that the requirements of §A of this regulation were met.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>A request for a contested case hearing shall include:</text>
        <paragraph num="(a)">
          <text>The name, address, and telephone number of the person filing the request; (b) The particular factual allegations which demonstrate that the:</text>
          <paragraph num="(i)">
            <text>Person is aggrieved by the final determination, and</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Final determination is legally inconsistent with any provisions of law applicable to the final determination being challenged or is based on an incorrect determination of a relevant and material fact.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The request for a contested case hearing shall be processed and the hearing conducted in accordance with the provisions of State Government Article, Title 10, Subtitle 2, and Environment Article, Title 1, Subtitle 6, Annotated Code of Maryland.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02" heading="Requirements for the Issuance and Reissuance of Discharge Permits.">
    <paragraph num="A.">
      <text>General. The Department shall issue or reissue a discharge permit upon a determination that:</text>
      <paragraph num="(1)">
        <text>The discharge or proposed discharge specified in the application is or will be in compliance with all applicable requirements of:</text>
        <paragraph num="(a)">
          <text>Effluent limitations,</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Surface and ground water quality standards,</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The Federal Act,</text>
        </paragraph>
        <paragraph num="(d)">
          <text>State law or regulation,</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Best available technology, and</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Federal effluent guidelines;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The discharge or proposed discharge from publicly owned treatment works (POTW) or other sewage treatment works, and the sewerage systems, including the pumping stations, which serve the POTW or other treatment works, are in compliance with:</text>
        <paragraph num="(a)">
          <text>The continuing planning process required under §303(e) of the Federal Act; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The approved county water and sewerage plan adopted under Environment Article, Title 9, Subtitle 5, Annotated Code of Maryland;</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The provisions of existing discharge permits, as issued, and any outstanding administrative orders affecting the applicant or his affiliate have been or are being complied with by the applicant and his affiliate;</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Industrial waste treatment works, publicly owned treatment works, or other sewage treatment works are operated and maintained by a certified operator under the provisions of Environment Article, Title 12, Annotated Code of Maryland, and applicable regulations; and</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The requirements of Regulations .01, .01-1, and .01-2 of this chapter have been met.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Conformance with Federal Act. In the absence of formally promulgated effluent standards and limitations under the Federal Act, the Department shall apply, in the terms and conditions of issued discharge permits, effluent limitations to achieve the purpose of the Federal Act.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Compliance Schedule.</text>
      <paragraph num="(1)">
        <text>The Department may impose a compliance schedule as a condition of a permit for existing discharges which do not comply with permit conditions, effluent limits, or water quality standards.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>When a compliance schedule is imposed, the Department shall:</text>
        <paragraph num="(a)">
          <text>Require the permittee to achieve compliance within:</text>
          <paragraph num="(i)">
            <text>Applicable periods established in effluent limitations or water quality standards, or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>In the absence of any legally applicable schedule of compliance, the shortest reasonable time consistent with the requirements of the Federal Act and State law or regulation;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>Set for each compliance schedule that is longer than 9 months, interim dates of 9 months or less for:</text>
          <paragraph num="(i)">
            <text>Compliance with interim requirements, or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Submission of reports of progress toward completion of the interim requirements;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>Require the permittee to provide written notice of the permittee's compliance or noncompliance with the interim or final requirements within 14 days following each interim or final compliance date;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Prepare and report to the EPA on the last day of February, May, August, and November, a list of all instances occurring in the quarter before the report where the permittee failed to:</text>
          <paragraph num="(i)">
            <text>Comply with an interim or final requirement, or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Notify the Department of compliance or noncompliance with each interim or final requirement; and</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>Make available to the public for inspection and copying, the quarterly lists reporting failure to comply with compliance schedules.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The compliance schedule may be modified according to Regulation .10D of this chapter.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02-1" heading="Discharge Permit Limits.">
    <paragraph num="A.">
      <text>General.</text>
      <paragraph num="(1)">
        <text>Each discharge permit, unless inappropriate, shall specify average and maximum daily quantitative limits, in terms of weight, for the discharge of pollutants in the authorized discharge.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Other discharge limits, such as minimum, average, or maximum concentration limits, may be imposed.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If a schedule of compliance is included as a discharge permit condition, quantitative limits shall be set for the interim period as well as for the period following the final compliance date.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Net Credits. The discharge permit limits for the discharge of noncontact cooling water shall be based on the water quality standard unless the discharger applies to have the permit limits based on the concentration in the intake water. A discharger may make this application if:</text>
      <paragraph num="(1)">
        <text>The intake water is the receiving water;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The pollutant concentration in the intake water exceeds the water quality standard;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Except for the additional provisions of a compliance schedule for corrosion and erosion in §C of this regulation, the discharger demonstrates to the Department's satisfaction, using a statistically rigorous demonstration, that no significant difference exists, at the edge of the appropriate mixing zone, between the intake concentration or loading and the effluent concentration or loading of the pollutant which exceeds the water quality standard; and</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The discharger demonstrates to the Department's satisfaction that no other activity, condition, method of operation, or materials used or produced at the facility which results in the introduction of wastewater into the facility's discharge (including entrainment of pollutants previously discharged or disposed of by the facility), significantly contributes to the exceedance of surface water quality standards.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Corrosion and Erosion.</text>
      <paragraph num="(1)">
        <text>Reasonable Potential. A discharger will not be found to cause, have the reasonable potential to cause, or contribute to an exceedance of a numerical water quality standard for a pollutant caused by normal corrosion and erosion from a facility’s water distribution piping and appurtenances or associated with intake water from a municipal drinking water supply, if:</text>
        <paragraph num="(a)">
          <text>The facility is an existing facility as of the effective date of this section;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The permitted dry-weather discharge from the facility consists of a combination of drinking fountain drainage, fire protection system drainage, and interior atmosphere control equipment drainage;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The total annual estimated dry-weight mass loading for the pollutant of concern of the permitted dry-weather discharge from the facility does not exceed 5 pounds;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The annual average effluent concentration of the permitted dry-weather discharge at the facility does not exceed the ambient concentration of the pollutant of concern in the facility's receiving water body; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The discharger’s receiving water body for the discharge is not a Class III or Class III-P water.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Compliance Schedule for Noncontact Cooling Water Discharges.</text>
        <paragraph num="(a)">
          <text>For purposes of this section, normal corrosion and erosion shall be determined through site-specific calculations that are performed in accordance with scientifically defensible methodology approved by the Department and are based, where appropriate, on annual average intake concentrations.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>In establishing discharge permit limits on the basis of either water quality standards or intake water pollutant concentrations, the Department may grant a credit for normal corrosion and erosion associated with the discharging facility's noncontact cooling water condenser tubes, if the discharger:</text>
          <paragraph num="(i)">
            <text>Demonstrates that, in the absence of the pollutant corroded and eroded from the facility's piping and appurtenances or noncontact cooling water condenser tubes, the discharger would not exceed the otherwise applicable permit limit;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Demonstrates that the normal corrosion and erosion associated with the intake water used by the facility for noncontact cooling water is sufficient to cause an exceedance of the otherwise applicable permit limit; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Has entered into a consent order requiring that, within 5 years after the promulgation of this regulation or the permit expiration date at the time of promulgation, whichever is later, sufficient noncontact cooling water condenser tubes or other piping and appurtenances for noncontact cooling water will be modified, replaced, or repaired, to consist of noneroding and noncorroding materials, until the need for the corrosion/erosion credit is eliminated.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>The Department may reduce or deny the credit if any other activity, condition, method of operation, or material used or produced at the facility results in the increase of the erosion and corrosion-based pollutant in the facility's discharge (including entrainment of a pollutant previously discharged or disposed of by the facility) and significantly contributes to the exceedance of the water quality standard for that pollutant in the receiving water.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Mixing Zones.</text>
      <paragraph num="(1)">
        <text>When any effluent meets water quality criteria at the end of the discharge pipe, the Department may not require the discharger to submit mixing zone calculations.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>When mixing zones are used to establish discharge permit limits, the discharger, at the time of application for permit issuance or renewal, or at a later time stipulated by the Department, shall select the mixing zone technique appropriate for each discharge and submit actual mixing zone calculations. All calculations and supporting studies should be based on established criteria and protocols or otherwise performed in accordance with scientifically defensible methodology approved by the Department. Supporting documentation may include one or more of the following:</text>
        <paragraph num="(a)">
          <text>Tracer studies;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Receiving water and discharge flow measurements;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Surface water bathymetry;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Diffuser design and performance data; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Effluent modeling results.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>When a mixing zone has been previously used to establish permit limits, the Department may, in its discretion, waive the requirement for full mixing zone development if the discharger demonstrates that:</text>
        <paragraph num="(a)">
          <text>Discharge conditions have not changed; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>No surface water impacts attributable to the facility have been identified.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02-2" heading="Minimum Levels for Discharge Permit Limits.">
    <text>Some permit limits expressed as concentrations of specific chemicals may be below the minimum levels for those chemicals. For these permit limits, the level of compliance shall be the minimum level.</text>
  </regulation>
  <regulation prefix="Regulation" num=".02-3" heading="Discharge Permit Limits Based on Biological Translator.">
    <paragraph num="A.">
      <text>General. Biologically available equivalence addresses the potential for an effluent constituent, present primarily in the particulate or relatively non-bioavailable form, to become transformed by mixing with the receiving water to a bioavailable form. The biological translator utilizes the relationship between effluent-receiving water toxicity testing results and the laboratory standard dilution water toxicity data to relate an instream aquatic life criterion to the impact of a specific effluent. This ratio provides discharge-specific information concerning the assimilative capacity of the surface water for a specific pollutant when contained in a particular discharge.</text>
    </paragraph>
    <paragraph num="B.">
      <text>Discharge Requirements for Use of the Biological Translator.</text>
      <paragraph num="(1)">
        <text>Before the use of a biological translator in a waste load allocation to determine specific discharge permit limits, a discharger shall demonstrate:</text>
        <paragraph num="(a)">
          <text>For acute aquatic life criteria, a history of repeated whole effluent toxicity testing at four consecutive quarterly intervals where the effluent, upon allowance for confirmation tests on failures, consistently exhibits an LC50 greater than 100 percent;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>For chronic aquatic life criteria, a history of repeated whole effluent toxicity testing at four consecutive quarterly intervals where the effluent, upon allowance for confirmation tests on failures, consistently exhibits an IC25 greater than the instream waste concentration at the edge of the chronic mixing zone; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Achievement of best available technology with satisfactory operation and maintenance.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The discharger shall continue to demonstrate, as appropriate, through whole effluent toxicity testing at quarterly intervals, as required by the discharge permit:</text>
        <paragraph num="(a)">
          <text>An LC50 which, upon allowance for confirmation tests for failures, consistently exceeds 100 percent; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An IC25 which, upon allowance for confirmation tests for failures, consistently exceeds the instream waste concentration at the edge of the chronic mixing zone.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>To have the Department continue using a biological translator to derive permit limits, a discharger shall repeat the process of data collection and effects ratio calculation each time the permit is renewed or changed to assure that all factors influencing the effluent-receiving water effects ratio remain the same.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The discharger shall demonstrate that no new BAT is available at each permit renewal.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The discharger shall provide all the necessary data to support the biological translator to the satisfaction of the Department.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Procedure.</text>
      <paragraph num="(1)">
        <text>Notification. A discharger who wants permit limits developed using the biological translator shall notify the Department in writing in accordance with Regulation .01-2B of this chapter. This notification shall include:</text>
        <paragraph num="(a)">
          <text>The substance or substances for which biologically available equivalence limits are to be developed;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The data demonstrating that the preconditions specified in §B of this regulation have been met; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The proposed methodology for deriving the biological translator, including sampling times and locations, effluent dilutions, species to be tested, and laboratory quality assurance/quality control procedures.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Time for Completion of Studies. A discharger, having notified the Department as required by §C(1) of this regulation, shall complete all studies supporting use of the biological translator and apply to the Department for approval of the biological translator within 12 months after this notification.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Application. An application for the biological translator shall include the:</text>
        <paragraph num="(a)">
          <text>Substance or substances for which biologically available equivalence limits are to be developed;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Most recent data collected to satisfy the preconditions in §B of this regulation; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Data supporting the biological translator.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Development of the Biological Translator. The biological translator shall be developed in accordance with “Guidelines for the Use of a Biological Translator in Wasteload Allocations”, (MDE-WMA-003, March 16, 1992), which is incorporated by reference, and current EPA sampling and testing procedures listed in the 1994 Interim Guidance on Determination and Use of Water-Effect Ratios for Metals (EPA-823-B-94-001) or the 2001 Streamlined Water-Effect Ratio Procedure for Discharges of Copper (EPA-822-R-01-005), which are incorporated by reference.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Time for Department Action on Application. The Department shall complete its review and either approve or deny use of the biological translator within 6 months after receipt of the application.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Use of the Biological Translator. When the Department has completed its review and determined that the supporting data are satisfactory, the Department shall use the resulting ratio with the appropriate water quality criterion to obtain a revised value for use in the derivation of a permit limit.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Unsatisfactory Biological Translator. If the Department determines that the data supporting the biological translator are unsatisfactory, the Department may not use the resulting ratio. The discharger shall be required by the Department to revise the application or select an alternative approach for establishing permit limits.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Public Participation. Those permit limits developed using the biological translator shall be included in the draft NPDES permit and in the public participation process for permit review.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".02-4" heading="Discharge Permit Limits Based on Chemical Translator.">
    <paragraph num="A.">
      <text>General.</text>
      <paragraph num="(1)">
        <text>The chemical translator is a mechanism for establishing the relationship between the dissolved concentration used in determining compliance with the instream aquatic life water quality criteria for metals and the measurement required for permit limits and waste load allocation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The chemical translator may not be used to establish discharge permit limits if the discharger has completed studies, under Regulation .02-3 of this chapter, which support the use of the biological translator.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Discharge Requirements for Use of the Chemical Translator.</text>
      <paragraph num="(1)">
        <text>Before the use of a chemical translator in a waste load allocation to determine specific discharge permit limits, a discharger shall demonstrate:</text>
        <paragraph num="(a)">
          <text>For acute aquatic life criteria, a history of repeated whole effluent toxicity testing at four consecutive quarterly intervals where the effluent, upon allowance for confirmation tests of failures, consistently exhibits an LC50 greater than 100 percent;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>For chronic aquatic life criteria, a history of repeated whole effluent toxicity testing at four consecutive quarterly intervals where the effluent, upon allowance for confirmation tests on failures, consistently exhibits an IC25 greater than the instream waste concentration at the edge of the chronic mixing zone; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Achievement of best available technology with satisfactory operation and maintenance.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The discharger shall continue to demonstrate, as appropriate, through whole effluent toxicity testing at quarterly intervals throughout the period of the permit:</text>
        <paragraph num="(a)">
          <text>An LC50 which, upon allowance for confirmation tests for failures, consistently exceeds 100 percent; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An IC25 which, upon allowance for confirmation tests for failures, consistently exceeds the instream waste concentration at the edge of the chronic mixing zone.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>To have the Department continue using a chemical translator to derive permit limits, a discharger shall repeat the process of data collection and calculation each time the permit is renewed or changed to assure that all factors influencing the chemical translator remain the same.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The discharger shall demonstrate that no new BAT is available at each permit renewal.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The discharger shall provide all the necessary data to support the chemical translator to the satisfaction of the Department.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Procedure.</text>
      <paragraph num="(1)">
        <text>Notification. A discharger who wants permit limits developed using the chemical translator shall notify the Department in writing in accordance with Regulation .01-2B(4) of this chapter. This notification shall include:</text>
        <paragraph num="(a)">
          <text>The metal or metals for which chemical translator limits are to be developed;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The data demonstrating that the preconditions in §B of this regulation have been met; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The proposed methodology for deriving the chemical translator, including sampling times and locations, analytical methods, and all quality assurance/quality control procedures.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Time For Completion of Studies. A discharger, having notified the Department as required by §C(1) of this regulation, shall complete all necessary studies supporting the use of the chemical translator and apply to the Department for approval of the chemical translator within 12 months of this notification.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Application. An application for the chemical translator shall include the:</text>
        <paragraph num="(a)">
          <text>Substance or substances for which the chemical translator limits are to be developed;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Most recent data collected to satisfy the preconditions in §B of this regulation; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Data supporting the chemical translator developed permit limits.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Development of Chemical Translator. The chemical translator is a ratio designed to estimate concentrations of total recoverable metal from a water quality criterion applied as dissolved metal. This ratio shall be developed using one of the following methods:</text>
        <paragraph num="(a)">
          <text>The discharger demonstrates, to the satisfaction of the Department, the ratio between dissolved and total recoverable metal concentrations through the collection and evaluation of appropriate field data; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>For fresh receiving waters only, the discharger uses the following ratio of total recoverable (CT) to dissolved (C) metal concentrations:</text>
          <paragraph num="(i)">
            <text>Kp is the linear partition coefficient in the units Kg-1);</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>[ss] is the concentration of suspended solids in the units mg/L; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Kp = Kpo [ss] a, where the values for Kpo and a are given in the following table:</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>Time for Department Action on Application. The Department shall complete its review and either approve or deny use of the chemical translator within 6 months of receipt of the application.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Use of the Chemical Translator. When the Department has completed its review and determined that the supporting data are satisfactory, the Department shall use the resulting ratio with the appropriate water quality criterion to obtain a revised value for use in the derivation of a permit limit.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Unsatisfactory Chemical Translator. If the Department determines that the data are unsatisfactory, the Department may not use the resulting ratio supporting the chemical translator. The discharger shall be required by the Department to revise the application or select an alternative approach for establishing permit limits.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Public Participation. Permit limits developed using the chemical translator shall be included in the draft NPDES permit and in the public participation process for permit review.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".03" heading="Monitoring, Recording, and Reporting for Discharge Permits.">
    <paragraph num="A.">
      <text>Monitoring.</text>
      <paragraph num="(1)">
        <text>A discharge authorized by a discharge permit shall be subject to any monitoring requirements the Department deems necessary, including:</text>
        <paragraph num="(a)">
          <text>The installation, use, and maintenance of monitoring equipment or methods; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>When appropriate, biological monitoring methods.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Each permit shall specify the sampling and analysis requirements, including the frequency and type of sampling and analysis.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Each permittee shall submit the name and address of the laboratory performing analyses within 30 days of the issuance of the State discharge or NPDES permit. If the permittee changes laboratories during the operating permit, the Department shall be notified within 30 days in writing.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Record Keeping.</text>
      <paragraph num="(1)">
        <text>The permittee shall retain for a minimum of 3 years any records of monitoring activities and results including all:</text>
        <paragraph num="(a)">
          <text>Raw data and original strip chart recordings;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Calibration and maintenance records; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Reports.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>This period of retention shall be extended during the course of unresolved litigation regarding the discharge of pollutants, or when requested by the Department.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>All records of monitoring shall include for all samples:</text>
        <paragraph num="(a)">
          <text>The date, exact place, time, and method of sampling;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The dates of analyses;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Who performed the analyses;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The analytical techniques and methods used; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The results of the analyses.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Reporting.</text>
      <paragraph num="(1)">
        <text>The permittee shall submit the monitoring results to the Department on the proper discharge monitoring report form.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The report shall be submitted in the time frame required by each permit.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The reporting period may not be less than once per year.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Measurements below the minimum level may be reported as BML (below minimum level).</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".04" heading="Sewage Treatment Works.">
    <paragraph num="A.">
      <text>The person holding the permit for publicly owned treatment works or other sewage treatment works shall provide the Department with a notice concerning:</text>
      <paragraph num="(1)">
        <text>The introduction of pollutants into these treatment works from any discharge of industrial waste for which a State discharge permit would be required if the discharge were made directly to the waters of the State; or</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Any substantial change in volume, character, or concentration of pollutants from any discharge of industrial waste being introduced into the treatment facilities.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>The notice shall include the following:</text>
      <paragraph num="(1)">
        <text>The quantity and quality of the discharge; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The anticipated impact of the discharge on the quantity and quality of the permittee's discharge.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Level of Required Treatment.</text>
      <paragraph num="(1)">
        <text>Secondary Treatment. Secondary treatment shall be required as a minimum for sewage treatment works discharging into any waters of the State.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Special Treatment Requirements for Discharge to Shellfish Harvesting Waters.</text>
        <paragraph num="(a)">
          <text>Treatment sufficient to afford protection for shellfish harvesting waters shall be required for all sewage treatment works discharging into Class II waters.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>This treatment may require a higher level of secondary treatment or advanced waste treatment.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>These treatment works shall incorporate a bypass control system, including a minimum 24-hour emergency holding facility, and shall provide for biocide residual control.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Advanced Waste Treatment Required. Advanced waste treatment as determined by waste load allocation shall be required for all sewage treatment works with a design capacity exceeding 1 million gallons per day and discharging into water quality limited waters. Advanced waste treatment may also be required for smaller sewage treatment works where the Department determines that this level of treatment is necessary.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Special Advanced Wastewater Treatment Requirements. An effluent limitation of 2 milligrams/liter total phosphorus shall be required for all facilities discharging more than:</text>
        <paragraph num="(a)">
          <text>0.5 million gallons per day to the Chesapeake Bay and its tributaries above the Baltimore Harbor; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>10 million gallons per day in the vicinity of Baltimore Harbor to the Bay Bridge.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".05" heading="Reserved." />
  <regulation prefix="Regulation" num=".06" heading="Term and Approval of Discharge Permit.">
    <paragraph num="A.">
      <text>Term of Permit.</text>
      <paragraph num="(1)">
        <text>The term of each discharge permit shall be for a maximum of 5 years, unless the permit is previously amended, suspended, or revoked.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Each discharge permit shall specify the expiration date.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If a timely and complete reapplication has been submitted and the Department, through no fault of the permittee, is unable to issue a new permit, the terms and conditions of the existing discharge permit shall continue and remain fully effective and enforceable.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Permittee Responsibility for Continuing Pollution Control. The issuance of a discharge permit by the Department does not relieve the permittee from the continuing responsibility for:</text>
      <paragraph num="(1)">
        <text>The successful treatment and disposal of wastewater and other waste; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Compliance with applicable provisions of State and federal law and regulations.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".07" heading="Administration of Federal NPDES Program by the State.">
    <paragraph num="A.">
      <text>The Department shall administer the National Pollutant Discharge Elimination System (NPDES) program as part of its own discharge permit system.</text>
    </paragraph>
    <paragraph num="B.">
      <text>This administration shall be in accordance with:</text>
      <paragraph num="(1)">
        <text>Environment Article, Title 9, Annotated Code of Maryland;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>This chapter; and</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Federal Act.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".08" heading="General Discharge Permit Program.">
    <paragraph num="A.">
      <text>Purpose.</text>
      <paragraph num="(1)">
        <text>General permits are discharge permits issued to classes of discharges.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department intends to regulate certain classes of discharges through the issuance of general permits.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>All discharges within the described class are permitted, subject to the specific conditions contained in the general permit.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Only those classes of discharges considered appropriate by the Department for regulation by this mechanism will be covered by a general permit.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>All other dischargers are subject to the requirements of a separate discharge permit issued under Regulations .01 — .07 of this chapter and COMAR 26.08.08.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Classes of Discharges Eligible for Regulation under General Permits.</text>
      <paragraph num="(1)">
        <text>For the purpose of this section, the term “landfill” includes sanitary landfills as defined in COMAR 26.04.07 as well as any land containment or land disposal facility for industrial, commercial, or residential solid waste, whether publicly or privately owned or operated, or both.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The following classes of discharges may be regulated through the General Permit Program:</text>
        <paragraph num="(a)">
          <text>Storm water discharges;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Landfills or sludge-handling facilities designed to achieve natural attenuation of leachate, with no discharge to surface waters other than storm water runoff regulated under §B(2)(a) of this regulation;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Individual on-lot domestic waste subsurface disposal systems permitted by the Department under Environment Article, Title 9, Subtitle 5, Annotated Code of Maryland, and COMAR 26.04.02;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Municipal separate storm sewers;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Ground water heat pumps discharging to waters of this State;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Other categories of discharges as established under this regulation.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Permit Provisions. The Department shall prepare a draft permit for each specific class of dischargers under consideration for regulation according to the General Permit Program. The draft permit shall contain those general and special conditions and, if appropriate, monitoring and reporting requirements considered necessary by the Department to protect public health and the environment.</text>
    </paragraph>
    <paragraph num="D.">
      <text>Permit Coverage. Unless specifically indicated otherwise, a general permit issued under this regulation shall authorize all discharges satisfying the class description. The Department, at its discretion, may notify a discharger and require issuance of a separate State discharge permit under Regulations .01—.07 of this chapter and COMAR 26.08.08.</text>
    </paragraph>
    <paragraph num="E.">
      <text>Permit Duration. A general permit issued under this regulation shall be valid for a period not to exceed 5 years, and shall be renewed at the discretion of the Department according to §§G—K of this regulation.</text>
    </paragraph>
    <paragraph num="F.">
      <text>Discharges Authorized Under a General Permit. The requirements of §§G—J of this regulation do not apply to the discharges authorized under a general permit, only to the issuance of the general permit itself.</text>
    </paragraph>
    <paragraph num="G.">
      <text>Draft Permits and Tentative Determinations.</text>
      <paragraph num="(1)">
        <text>The Department shall prepare a draft permit and a tentative determination for a specific class of dischargers to be regulated under the General Permit Program.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A fact sheet shall also be prepared describing the class of dischargers to be regulated, outlining the proposed permit conditions and limitations, and specifying the procedures for a person to review and copy the tentative determination, draft permit, and related materials.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The tentative determination shall include:</text>
        <paragraph num="(a)">
          <text>A statement that the Department proposes to issue a general permit for a certain class of discharges;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The procedures for a person to review and copy the tentative determination, draft permit, or related material;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A brief explanation of the Department's tentative decision;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Proposed permit limitations and conditions; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>If applicable, a proposed schedule of compliance.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Public Notice of Tentative Determination.</text>
        <paragraph num="(a)">
          <text>The Department shall publish a public notice of the Department's tentative determination in the Maryland Register and according to Regulation .01-1E of this chapter.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The notice of tentative determination shall include:</text>
          <paragraph num="(i)">
            <text>The information required in §G(2) of this regulation;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>A statement that the Department shall allow 30 days for public comment to the tentative determination before the issuance of the final determination and the procedure for submitting comments;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A statement that the Department shall hold a public hearing when a written request for a public hearing is made by a person within 20 days of the publication of the notice of tentative determination and the procedure for making a written request for a public hearing; and</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Other information the Department determines to be necessary for adequate public notification.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(c)">
          <text>If the notice of tentative determination also includes a notice of public hearing, the notice of public hearing shall be given at least 30 days before the hearing.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="H.">
      <text>Public Hearings.</text>
      <paragraph num="(1)">
        <text>The Department shall schedule a public hearing on the tentative determination when a written request for a public hearing is made within 20 calendar days of the publication of the notice of tentative determination.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department, at its own discretion, may hold:</text>
        <paragraph num="(a)">
          <text>An informational meeting or meetings; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A public hearing or hearings.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>The public hearing may be cancelled if all persons who made timely written request for such a meeting withdraw their requests.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>If a public hearing is required, the Department shall:</text>
        <paragraph num="(a)">
          <text>Publish a notice of the hearing according to Regulation .01-1E of this chapter, and the first notice shall give a minimum of 30 days notice before the hearing; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Publish a notice of the public hearing that includes:</text>
          <paragraph num="(i)">
            <text>The information required under §G(2) of this regulation,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The date, time, and location of the public hearing, and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Other information the Department determines to be necessary for adequate public notification.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(5)">
        <text>The Department shall:</text>
        <paragraph num="(a)">
          <text>Give a person who attends a public hearing an opportunity to make comments concerning the issuance of a general permit; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Accept written comments on the proposal to issue a general permit for at least 5 days after a public hearing.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="I.">
      <text>Final Determinations for General Permits.</text>
      <paragraph num="(1)">
        <text>If the Department is not required to prepare a final determination, the tentative determination shall be a final decision by the Department and a permit may be issued.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The Department shall prepare a final determination if:</text>
        <paragraph num="(a)">
          <text>Written comments adverse to the tentative determination were received by the Department within 30 days after publication of the notice of tentative determination;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Comments adverse to the tentative determination were received in writing at, or within 5 days after, a public hearing held under the provisions of §H of this regulation;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Comments adverse to the tentative determination were received orally at the public hearing conducted under this section and the Department prepared a transcript of the comments made at the hearing; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The final determination is substantively different from the tentative determination and persons who may be aggrieved by the final determination have not waived, in writing, their right to request a contested case hearing.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Those persons, including applicants, who believe any condition of a draft permit is inappropriate or that the Department's tentative determination is inappropriate, shall raise all reasonably ascertainable issues and submit all reasonably available arguments and documents supporting their position by the close of the public comment period, including any public hearing, as established by this chapter.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Supporting materials which are submitted shall be included in full and may not be incorporated by reference, unless they are already part of the administrative record in the same proceeding, or consist of State or federal statutes and regulations, EPA documents of general applicability, or other generally available reference materials.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Those offering comments shall make supporting materials not already included in the administrative record available by submitting a complete copy of all supporting materials at the time they submit their comments or, if this submission is not practical, as determined solely by the Department, comments shall identify the location of the supporting materials.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>The final determination shall include the following:</text>
        <paragraph num="(a)">
          <text>A description of the type of discharges to be included in the general permit;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A statement of the Department's final determination and a brief explanation of the Department's decision;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The permit limitations;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The general and special permit conditions; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>A schedule of compliance, if applicable.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>The final determination shall be available to the public for inspection and copying according to Regulation .01-1E of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="J.">
      <text>Notice of Final Determination.</text>
      <paragraph num="(1)">
        <text>When the Department is required to prepare a final determination under §I of this regulation, a notice of final determination shall be published according to Regulation .01-1E of this chapter.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The notice of final determination shall include:</text>
        <paragraph num="(a)">
          <text>The information required under §I(3)(a)—(b) of this regulation, including any change in permit limitations, conditions, or schedule of compliance;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>A statement that the notice of final determination is available for inspection and copying;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The procedure for inspecting and copying the final determination;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A statement that a person may request a contested case hearing to appeal a final determination if the person makes factual allegations with sufficient particularity to demonstrate that the person is aggrieved by the final determination and the final determination is:</text>
          <paragraph num="(i)">
            <text>Legally inconsistent with any provisions of law applicable to the final determination being challenged, or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Based upon an incorrect determination of a relevant and material fact;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(e)">
          <text>A statement that a person requesting a contested case hearing shall submit a written request for adjudication within 15 days after the publication of the notice of final determination;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The procedure for requesting a contested case hearing; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Other information the Department determines to be necessary for adequate public notification.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="K.">
      <text>Request for Contested Case Hearings for General Permits.</text>
      <paragraph num="(1)">
        <text>A person may not request a contested case hearing on an individual discharge covered under a general permit adopted under the provisions of this chapter.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A person requesting a contested case hearing to appeal the final determination of the Department to issue a general permit shall:</text>
        <paragraph num="(a)">
          <text>Submit a written request in the manner specified in the notice of final determination within 15 days after publication of the notice of final determination; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Provide documentation that the requirements of §I of this regulation were met.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Requests for a contested case hearing shall include:</text>
        <paragraph num="(a)">
          <text>The name, address, and telephone number of the person filing the request; (b) The particular factual allegations which demonstrate that the person is aggrieved by the final determination and the final determination is:</text>
          <paragraph num="(i)">
            <text>Legally inconsistent with any provisions of law applicable to the final determination being challenged; or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Based on an incorrect determination of a relevant and material fact.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>The Department shall process requests for contested case hearings according to State Government Article, Title 10, and Environment Article, Title 1, Annotated Code of Maryland.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".09" heading="General Discharge Permits.">
    <paragraph num="A.">
      <text>General Discharge Permit for Stormwater Discharge Associated with Construction Activity.</text>
      <paragraph num="(1)">
        <text>Exception. Construction activity excluded under the Federal Act and regulated under COMAR 26.09.02 is not covered under this general permit.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Activities Covered. Activities covered under this general permit are new and existing stormwater discharges that are composed in whole or in part of discharges associated with construction activity as regulated under the Federal Act and Environment Article, Title 4, Subtitles 1 and 2, Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Need for Additional Permits. Stormwater discharges which result from the completed construction authorized under this regulation may require additional authorization under other general permit regulations or an individual permit.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Application. Before the initiation of an activity covered under this permit, an applicant shall make application to the Department, including the payment of any fees.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Specific Requirements. A permittee shall comply with requirements to obtain approval for:</text>
        <paragraph num="(a)">
          <text>Erosion and sediment control plans required under Environment Article, Title 4, Subtitle 1, Annotated Code of Maryland; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Stormwater management plans required under Environment Article, Title 4, Subtitle 2, Annotated Code of Maryland.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>General Discharge Permit for StormWater Discharges Associated with Industrial Activity.</text>
      <paragraph num="(1)">
        <text>Exceptions. The following activities are not regulated under this general permit:</text>
        <paragraph num="(a)">
          <text>Industrial stormwater discharges with federal effluent guideline limitations;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Stormwater discharges associated with industrial activity from inactive mining or inactive oil and gas operations occurring on federal lands; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Stormwater discharges for which the:</text>
          <paragraph num="(i)">
            <text>NPDES permit has expired, has been terminated, or has been denied; or</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Department requires an individual permit or a different general permit.</text>
          </paragraph>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Activities Covered. Existing stormwater discharges that are comprised in whole or in part of stormwater runoff associated with industrial activity are covered.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Application. After the effective date of this regulation, an applicant shall make application to the Department, including the payment of any fees, for any existing or new discharge.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Specific Requirements. Stormwater discharge associated with industrial activity shall comply at all times with the provisions of:</text>
        <paragraph num="(a)">
          <text>Environment Article, Title 7, Subtitle 2, Annotated Code of Maryland;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Environment Article, Title 9, Subtitle 3, Annotated Code of Maryland; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The Federal Act.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>General Permits for Municipal Separate Storm Sewer Systems.</text>
      <paragraph num="(1)">
        <text>Definitions. “Municipal separate storm sewer systems” means systems that convey stormwater runoff from municipalities as defined in the Federal Act or as designated by the Department in accordance with the Federal Act.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Required Permits. The Department shall promulgate general permits as necessary to meet the requirements of the Federal Act, including permits for:</text>
        <paragraph num="(a)">
          <text>Municipal separate storm sewer systems required to be permitted under the Federal Act; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Those systems designated by the Department in accordance with the Federal Act.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Specific Requirements for Landfills Designed for Natural Attenuation of Leachate with No Discharge to Surface Waters other than Stormwater Run-off.</text>
      <paragraph num="(1)">
        <text>Landfills designed to achieve natural attenuation of leachate shall be designed, constructed, and operated in accordance with the specific provisions included in a permit issued by the Department pursuant to Environment Article, §9-204, Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Stormwater control systems at landfills are regulated through the general permit provisions specified in Regulation .08C(1) of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Specific Requirements for Subsurface Sewage Disposal Systems.</text>
      <paragraph num="(1)">
        <text>Subsurface sewage disposal systems shall include, but are not limited to, septic systems or aerated septic systems with appurtenant seepage pits or trenches, seepage pits, mound systems, or other disposal systems approved by the Department.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The systems shall be designed, installed, and maintained in accordance with the specific conditions included in the permit issued pursuant to Environment Article, Title 9, Subtitle 5, Annotated Code of Maryland, and COMAR 26.04.02.</text>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Ground Water Heat Pumps.</text>
      <paragraph num="(1)">
        <text>Persons operating or planning to install a ground water heat pump not authorized by a separate State discharge permit shall, upon request of the Department, provide information concerning the system as installed or planned to be installed. The information shall include a map or sketch of the site, indicating the location of the source well, the discharge point or well, the well permit number or numbers, and, if appropriate, the name of the receiving streams. This information may be submitted to the Department through the local county health department.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>All permittees shall obtain a ground water appropriation permit from the Water Resources Administration and shall comply with all terms and conditions of that permit.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>All permittees shall obtain a well construction permit from the Department or, if appropriate, the responsible county agency.</text>
      </paragraph>
    </paragraph>
    <paragraph num="G.">
      <text>Grading or Filling Activities Not Otherwise Regulated by the Department. If applicable, permittees shall obtain a permit or license issued pursuant to the Natural Resources Article, §§8-803, 9-202, or 9-306, Annotated Code of Maryland.</text>
    </paragraph>
    <paragraph num="H.">
      <text>General Discharge Permit for Surface Coal Mines and Related Facilities.</text>
      <paragraph num="(1)">
        <text>Exceptions. The following discharges are not covered under this general permit:</text>
        <paragraph num="(a)">
          <text>Discharges of toxic substances which exceed State water quality criteria for toxic substances;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Discharges which elevate temperature in Use III, Use III-P, Use IV, and Use IV-P streams;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Discharges of acid mine drainage from mine reclamation areas;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Discharges from coal mines commingled with other sources of wastewater, particularly wastes from underground mines; and</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Discharges from underground coal mines.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This permit covers all new and existing discharges of stormwater runoff and ground water seepage to surface waters of this State from:</text>
        <paragraph num="(a)">
          <text>Surface coal mines, including active mining areas, access roads, coal storage, and loading areas (tipples);</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Independent coal storage and loading areas (tipples);</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Coal preparation plants; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Reclamation areas.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="I.">
      <text>General Discharge Permit for Seafood Processors.</text>
      <paragraph num="(1)">
        <text>Exceptions. A discharge permit is not required for outdoor crab shedding operations.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This permit covers the following new and existing discharges:</text>
        <paragraph num="(a)">
          <text>Wastewater from blue crab, oyster, and fish processing operations such as cleaning, preparing, and packing;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Auxiliary discharges, which are limited to noncontact cooling water, ice machine drainage, steam or cooling coil condensate, and inside crab shedding tray overflow; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Stormwater runoff from processing or material handling.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="J.">
      <text>General Discharge Permit for Mineral Mines, Quarries, Borrow Pits, and Concrete and Asphalt Plants.</text>
      <paragraph num="(1)">
        <text>Exceptions. This permit may not cover the following discharges:</text>
        <paragraph num="(a)">
          <text>Discharges from coal mines and associated facilities as regulated under 40 CFR 434; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Discharges from industrial sand facilities that utilize HF flotation as regulated by 40 CFR §436.40.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This permit covers all new and existing discharges of:</text>
        <paragraph num="(a)">
          <text>Infiltrated ground water pumped from mines to surface waters;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Wastewater from material processing to surface or ground waters;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Stormwater runoff to surface waters from mine sites (facilities classified within Standard Industrial Classifications 10 and 14), concrete plants (facilities classified within Standard Industrial Classification 32), and asphalt plants (facilities classified within Standard Industrial Classification 29);</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Stormwater runoff to surface waters from industrial activities co-located or appurtenant to a permitted activity specified in §J(2)(c) of this regulation;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Wastewater from washing mixer trucks and concrete mixing equipment to surface or ground waters;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Miscellaneous wastewater from spillage at ready-mix plants to surface or ground waters; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Wastewater from hydrodemolition to ground waters.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="K.">
      <text>General Discharge Permit for Dewatering, Hydrostatic Testing, and Groundwater Remediation.</text>
      <paragraph num="(1)">
        <text>Exceptions. This permit may not cover the following discharges:</text>
        <paragraph num="(a)">
          <text>Discharges of any type from oil terminals;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Tank bottom wastewater discharges to ground waters of the State;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Wastewater from the washing of chemical and petroleum storage tanks, pipes, and pipelines; and</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Wastewater discharges to ground water that, before treatment, contain concentrations of benzene, lead, or other substances in excess of toxicity characteristic leaching procedure (TCLP) concentrations as defined in COMAR 26.13.02.14.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This general permit covers all new and existing discharges of:</text>
        <paragraph num="(a)">
          <text>Treated tank bottom wastewater from storage tanks used only for gasoline, kerosene, fuel oil, no. 6 oil, or aviation fuel to surface waters;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Wastewater from the flushing or hydrostatic testing of pipes, pipelines, or tanks, or wastewater from pipeline infiltration;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Water in excess of 10,000 gallons per day as a monthly average from the overflow, flushing, or dewatering of reservoirs, tanks, or pipelines used for the storage or delivery of untreated water;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Wastewater from cleaning or dewatering of vessels or structures used to store or convey potable water;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Stormwater discharges from storage tank containment structures;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Emergency discharges of potable water;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Extracted water from an aquifer test;</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Wastewater from construction dewatering;</text>
        </paragraph>
        <paragraph num="(i)">
          <text>Foundation drainage which has been treated for any contaminants; and</text>
        </paragraph>
        <paragraph num="(j)">
          <text>Air stripping, activated carbon adsorption, or equivalently treated wastewater from groundwater remediation sites not covered by the General Discharge Permit of Treated Ground Water From Oil Contaminated Ground Water Sources to Surface or Ground Waters of the State.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="L.">
      <text>General Discharge Permit for Swimming Pools and Spas.</text>
      <paragraph num="(1)">
        <text>Exceptions. This permit does not cover sanitary wastewater discharges associated with swimming pool and spa operations.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This permit covers discharges of filter backwash, cleaning water, overflow, and drainage from lowering or emptying a public or private pool or spa to surface or ground water.</text>
      </paragraph>
    </paragraph>
    <paragraph num="M.">
      <text>General Discharge Permit for Marinas.</text>
      <paragraph num="(1)">
        <text>Exceptions. This permit does not cover the following discharges:</text>
        <paragraph num="(a)">
          <text>Stormwater discharges that have shown, or may be reasonably expected to contribute to, a violation of a water quality standard;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Stormwater discharges for which the Department requires an individual permit or an alternative general permit; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Sanitary wastewater discharges.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges.</text>
        <paragraph num="(a)">
          <text>This permit covers the following discharges from marinas and boat maintenance facilities:</text>
          <paragraph num="(i)">
            <text>Stormwater runoff to surface waters from areas involved in boat maintenance including boat rehabilitation, mechanical repairs, painting, and fueling, and boat or equipment cleaning operations;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Wastewater discharges to surface or ground waters from washing of boats and boat equipment; and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Noncontact cooling water discharges such as from ice machines, refrigeration units, and other machinery to surface waters.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(b)">
          <text>The discharge of 10,000 gallons per day or less of noncontact cooling water to ground water does not require a permit.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="N.">
      <text>General Discharge Permit for Animal Feeding Operations.</text>
      <paragraph num="(1)">
        <text>Exceptions.</text>
        <paragraph num="(a)">
          <text>In locations or circumstances in which the Department concludes in its sole discretion that this general discharge permit does not adequately protect State waters, the Department may require a person otherwise eligible for this permit to apply for and obtain an individual discharge permit.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Large duck CAFOs with liquid manure handling systems are not eligible for coverage under this general permit.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This permit covers:</text>
        <paragraph num="(a)">
          <text>Discharges from a CAFO;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Discharges from a MAFO; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Discharges from an AFO that utilizes a spray irrigation system for application of liquid wastewater to the soil surface.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Public Process for CAFOs and MAFOs.</text>
        <paragraph num="(a)">
          <text>A NOI submitted by an AFO is subject to the public participation process described in this subsection.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>“Plan” or “required plan” in this section means a CNMP, NMP, or conservation plan.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Notwithstanding Regulation .01-1E of this chapter, publication of public notices or public notification required by this regulation may be accomplished by posting on the Department's web site at www.mde.state.md.us.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>The Department shall notify the public upon receipt of a NOI or a required plan by posting relevant information, including but not limited to facility name, location, size, type of operation, and date and type of document received, on the Department's web site.</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The Department may require an applicant to place a copy of the NOI and required plans in the main branch of the public library, in the county in which the AFO is located, for the duration of any related public comment period.</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The Department shall make available for review and copying an applicant's NOI and required plans in accordance with Regulation .01-1E(6) and (7) of this chapter.</text>
        </paragraph>
        <paragraph num="(g)">
          <text>The Department shall review the NOI and required plans and, based upon this review, determine whether they satisfy the requirements of the general permit.</text>
        </paragraph>
        <paragraph num="(h)">
          <text>When additional information is necessary to complete the NOI or to clarify, modify, or supplement previously submitted material, the Department may request that information from the permit applicant.</text>
        </paragraph>
        <paragraph num="(i)">
          <text>If the Department determines that the plans satisfy the requirements of the general permit, the Department shall prepare a preliminary approval identifying the terms of the plans that satisfy the general permit requirements.</text>
        </paragraph>
        <paragraph num="(j)">
          <text>The Department shall publish public notice of a preliminary approval of the required plans in accordance with §N(3)(c) of this regulation. The notice shall provide for a period of 30 days for public comment and shall specify how to review and copy the preliminary approval, NOI, and the required plans. For a CAFO, the notice shall also specify the procedure for making a written request for a public hearing regarding the preliminary approval of the terms of the required plans.</text>
        </paragraph>
        <paragraph num="(k)">
          <text>Public Hearing.</text>
          <paragraph num="(i)">
            <text>The Department shall schedule a public hearing on the preliminary approval for a CAFO when a written request for a public hearing is made within 20 days of the publication of notice of the preliminary approval.</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>The Department may, at its discretion, schedule a public hearing on the preliminary approval for a MAFO or a CAFO.</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>A public hearing regarding the Department's preliminary approval of the required plans shall follow the same procedures as those applicable to public hearings on tentative determinations set forth in Regulation .01-2B(5) and (6) of this chapter.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(l)">
          <text>Final Approval of Required Plans.</text>
          <paragraph num="(i)">
            <text>The Department shall prepare and provide notice of its final approval of the required plans following the same procedures as those applicable to final determinations set forth in Regulations .01-3A and B of this chapter.</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Notwithstanding Regulation .08K(1) of this chapter, a person aggrieved by the Department's final approval of the required plans may request a contested case hearing.</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The form and content of a request for a contested case hearing shall be consistent with Regulation .08K(2) and (3) of this chapter. A contested case hearing conducted under this paragraph shall be limited to contesting the terms of the approved plans.</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>When the Department grants final permit coverage to an AFO, the terms of the plans, as revised by the Department, are enforceable under the terms and conditions of the general permit.</text>
          </paragraph>
          <paragraph num="(v)">
            <text>The Department shall notify the AFO owner or operator of the terms and conditions of the plans that are approved by the Department and enforceable under the permit.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(m)">
          <text>A MAFO that has submitted a complete NOI and all required plans may operate under the terms of the general permit pending the outcome of the public participation process and any contested case hearing, unless the Department determines that an unacceptable threat to public health, water quality, or aquatic resources may occur.</text>
        </paragraph>
        <paragraph num="(n)">
          <text>Revisions to Approved Plans. The Department shall follow the public participation procedures of this subsection when an AFO proposes a revision to its approved plans that is significant, as determined by the Department, or for a CAFO as specified under the Federal Act.</text>
        </paragraph>
        <paragraph num="(o)">
          <text>Interested Persons.</text>
          <paragraph num="(i)">
            <text>The Department shall maintain a list of persons who have requested direct notification of an NOI and related plan submittals, either for a specific AFO or for a geographic location or area.</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Upon receipt of a complete NOI or a corresponding required plan, the Department shall notify the interested persons either by electronic mail or U.S. mail that a document of potential interest has been received and that additional details may be available on the MDE web site.</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>The Department shall provide a copy of the public notice of the preliminary approval in §N(3)(i) of this regulation to interested persons and provide them access to a copy of the preliminary approval via electronic mail or U.S. mail or through providing a link to the Department's web site.</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>The Department shall also provide a copy of the notice of the preliminary approval to the persons identified in Regulation .01-2B(3)(a) and (b) of this chapter.</text>
          </paragraph>
        </paragraph>
        <paragraph num="(p)">
          <text>Requests for confidential treatment of information shall be handled according to Regulation .01-1E(8) of this chapter.</text>
        </paragraph>
        <paragraph num="(q)">
          <text>This subsection does not affect the authority and discretion of the Department to require an individual permit.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="O.">
      <text>StormWater and Hydrostatic Test Water from Oil Terminals.</text>
      <paragraph num="(1)">
        <text>Exceptions. This permit does not cover discharges:</text>
        <paragraph num="(a)">
          <text>Of industrial process wastewater from oil terminals or hydrostatic test water from non-oil terminals; or</text>
        </paragraph>
        <paragraph num="(b)">
          <text>From oil terminals with a total aggregate tank capacity of at least 5 million gallons of oil which have marine or pipeline transfer capabilities.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This permit covers all new and existing discharges of stormwater from storage tank dike and loading rack areas and hydrostatic test water from oil terminals to surface or ground waters of the State.</text>
      </paragraph>
    </paragraph>
    <paragraph num="P.">
      <text>Treated Ground Water from Oil-Contaminated Ground Water Sources.</text>
      <paragraph num="(1)">
        <text>Exceptions. This permit does not cover discharges of treated ground water contaminated with other volatile organic compounds or hazardous material (such as, but not limited to, TCE, TCA, DCE) other than oil.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Eligible Discharges. This permit covers all new and existing discharges of treated ground water from oil-contaminated ground water sources which discharge to surface or ground waters of the State.</text>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".09-1" heading="Fees for General Discharge Permits.">
    <paragraph num="A.">
      <text>Applicability.</text>
      <paragraph num="(1)">
        <text>Intent. The Department may charge nonrefundable fees for certain general discharge permits as specified in this regulation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Exemptions. Discharges associated with the following dischargers are exempt from this regulation:</text>
        <paragraph num="(a)">
          <text>Publicly owned treatment works;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Other treatment works which treat only sewage; and</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Facilities or persons culturing or raising aquatic organisms in enclosed systems discharging less than 1,000,000 gallons per day.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>General.</text>
      <paragraph num="(1)">
        <text>Fees are based on the anticipated cost of program activities related to management of discharge to the waters of this State.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Persons engaging in an activity covered under a general permit for which a fee or fees are charged shall submit a notice of intent (NOI) form requesting inclusion under the general permit, accompanied by the appropriate fees, before the initiation of the activity.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The required fees shall be submitted with the Department's approved notice of intent (NOI) forms.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Department may refuse to complete processing on any NOI if the applicant fails or refuses to pay the application fee.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>When the Department questions a fee as submitted by the applicant, the Department shall notify the applicant in writing and a meeting shall be scheduled, if necessary, to resolve the dispute.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>Fees collected by the Department under this regulation shall be paid into the Clean Water Fund. The fees shall be used for activities that are related to the management of discharge to the waters of this State.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>The Department may require the retroactive payment of a general permit fee if the general permit becomes effective before the adoption of a regulation supporting this fee, if the fee was specified in the general permit at the time of general permit issuance.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Fees for General Storm Water Discharge Permits.</text>
      <paragraph num="(1)">
        <text>Storm Water Associated with Industrial Activity.</text>
        <paragraph num="(a)">
          <text>The permit fee for storm water discharges associated with industrial activity shall be either a one-time payment of $550 or an annual payment of $120. The $550 fee shall be submitted with the NOI. The alternative $120 annual payment shall be submitted with the NOI and annually by July 1 of each year.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Facilities which began operating after September 29, 1995, and were registered under the original general permit for storm water associated with industrial activity will be credited $100 for each full calendar year they did not operate between January, 1993, and December, 1996.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The fee for facilities which begin operating after October 1, 1997, shall be prorated on a monthly basis.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The application fees for storm water discharges associated with construction activity are as follows:</text>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Fee for Surface Coal Mine and Related Facilities Discharge.</text>
      <paragraph num="(1)">
        <text>Annual Permit Fee.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The annual permit fee is based on the total flow volume of effluent discharged from the facility, as determined by the storm water runoff volume calculation in §D(3) of this regulation.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Calculation of Storm Water Runoff Volume. Storm water runoff volume is determined by the following method:</text>
        <paragraph num="(a)">
          <text>Annual storm water runoff volume (gallons/day) = Annual rainfall (feet) × drainage area (square feet) × 7.48 × 0.15;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Average storm water runoff volume (gallons/day) = Annual storm water runoff volume divided by 365.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(4)">
        <text>Alternative Storm Water Calculation. As an alternative to the method in §D(3) of this regulation, the permittee may submit a report to the Department which contains calculations of the average daily storm water runoff from the permitted facility. The Department shall make the final decision in determining the acceptability of the alternative method.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>Fee for Discharges from Seafood Processors. Permit Fee.</text>
      <paragraph num="(1)">
        <text>The permittee shall pay an annual permit fee. The first annual fee payment shall be submitted to the Department with the NOI form.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The permit fee is based on the total volume of effluent discharged from the facility. The fees are:</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Department will bill the permittee annually, and the fee shall be paid each year by the anniversary date of the permit.</text>
      </paragraph>
    </paragraph>
    <paragraph num="F.">
      <text>Fees for Discharges from Mineral Mines, Quarries, Borrow Pits, and Concrete and Asphalt Plants.</text>
      <paragraph num="(1)">
        <text>Exemptions. Mineral mines, quarries, and borrow pits which discharge mining wastewater, process generated wastewater, and storm water to ground water only are exempt from the permit fee.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Permit Fee.</text>
        <paragraph num="(a)">
          <text>The permittee shall pay an annual permit fee. The first annual fee payment shall be submitted to the Department with the NOI form.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The permit fee is based on the total volume of effluent discharged from the facility. The fees are:</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The Department will bill the permittee annually, and the fee shall be paid each year by the anniversary date of the permit.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="G.">
      <text>Fees for Discharges from Dewatering, Hydrostatic Testing, and Groundwater Remediation.</text>
      <paragraph num="(1)">
        <text>Exemptions. Discharges from tanks, pipes, and other liquid containment structures associated with drinking water supplies are exempt from the permit fee.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Permit Fee.</text>
        <paragraph num="(a)">
          <text>The permittee shall pay a permit fee with the NOI form and each additional year the permit is held.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The discharge permit fee is based on the total volume of effluent discharged from the facility. The permit fees for the first and subsequent years are:</text>
        </paragraph>
        <paragraph num="(c)">
          <text>The Department will bill the permittee annually, and the fee shall be paid each year by the anniversary date of the permit.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="H.">
      <text>Fee for Discharges from Swimming Pools and Spas; Notice of Intent (NOI) Fee. Persons seeking coverage under this general permit shall submit an NOI together with a fee of $100 for each facility. A fee is not required with the NOI submission for the registration of pools owned by municipalities, counties, or the State. Owners of pools or spas serving individual residences are not required to submit an NOI or pay a fee.</text>
    </paragraph>
    <paragraph num="I.">
      <text>Fee for Discharges from Marinas; NOI Fee.</text>
      <paragraph num="(1)">
        <text>Persons seeking coverage under this general permit shall submit an NOI together with the following fee depending upon the number of slips available at the marina:</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Facilities already registered under 92-GP-0001 shall pay the lesser of the above fee or a fee of $350 before September, 1997, to register for this permit.</text>
      </paragraph>
    </paragraph>
    <paragraph num="J.">
      <text>Fee for Discharges from Concentrated Animal Feeding Operations.</text>
      <paragraph num="(1)">
        <text>A CAFO shall pay an annual permit fee. The first annual fee payment shall be submitted to the Department with the NOI form. The Department will bill the permittee annually, and the fee shall be paid annually not later than the anniversary of the effective date of the permit. The following permit fees shall be collected based on the size category of the facility defined in Table 1 under Regulation 26.08.03.09A(3):</text>
      </paragraph>
      <paragraph num="(2)">
        <text>If the Department questions the fee submitted by the permittee, the Department shall follow the procedure in §B(5) of this regulation.</text>
      </paragraph>
    </paragraph>
    <paragraph num="K.">
      <text>Storm Water and Hydrostatic Test Water from an Oil Terminal and Treated Ground Water NOI Fees.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".10" heading="Permit Review and Modification.">
    <paragraph num="A.">
      <text>General.</text>
      <paragraph num="(1)">
        <text>The Department may review or modify any State discharge permit or other written authorization describing required performance for specific activities and operations under the procedures set forth in this regulation.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>When a permit is modified, only the conditions subject to modification are reopened.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Permit Review. The Department of the Environment may review any permit which it has issued in order to determine whether the:</text>
      <paragraph num="(1)">
        <text>Conditions of the permit have been complied with; and</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Permit should properly be modified, suspended, or revoked.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Minor Modification of Permits.</text>
      <paragraph num="(1)">
        <text>The Department may modify a permit to make minor modifications in the permitted activity.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>A minor modification requested by a permittee shall be in writing.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>Minor modifications may only:</text>
        <paragraph num="(a)">
          <text>Correct typographical errors;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Require more frequent monitoring or reporting by the permittee;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Change an interim compliance date in a schedule of compliance, provided the new date is not more than 120 days after the date specified in the existing permit and does not interfere with attainment of the final compliance date requirement;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Allow for a change in ownership or operational control of a facility when the Department determines that no other change in the permit is necessary, provided that a written agreement containing a specific date for transfer of permit responsibility, coverage, and liability between the current and new permittees has been submitted to the Department;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>Change the construction schedule for a discharger which is a new source if the change does not affect the discharger's obligation to have all pollution control equipment installed and in operation before discharge;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>Delete a point source outfall when the discharge from that outfall is terminated and does not result in discharge of pollutants from other outfalls except in accordance with permit limits; or</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Incorporate conditions of a pretreatment program that has been approved in accordance with COMAR 26.08.08.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Major Permit Modification Request by Permittee.</text>
      <paragraph num="(1)">
        <text>A permittee may request modification of the permit by submitting a written request to the Department.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Upon receipt, the Department shall review the request and promptly notify the permittee of its decision.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If the Department decides to grant the permittee's request, permit modifications shall be processed by the Department according to Regulations .01—.02-4 of this chapter.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The Department of the Environment, upon written request of the applicant, may revise or modify a schedule of compliance without a hearing if:</text>
        <paragraph num="(a)">
          <text>It determines good and valid cause exists for the revision or modification, such as an act of God, materials shortage, or other event over which the permittee has no control; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Within 30 days following receipt of notice from the Department, the Administrator of the EPA, or his designated representative, does not object in writing.</text>
        </paragraph>
      </paragraph>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".10-1" heading="Permit Suspension and Revocation.">
    <paragraph num="A.">
      <text>Action on Permit Violation.</text>
      <paragraph num="(1)">
        <text>Under conditions other than emergency, if the Department determines that there has been a violation of any term or condition of a permit, the Department shall serve a written complaint upon the permittee specifying the nature of the violation. Subsequent to, or concurrent with, service of the complaint, the Department may exercise one of the following options, under the provisions of Environment Article, §9-335, Annotated Code of Maryland:</text>
        <paragraph num="(a)">
          <text>Issue an order requiring necessary corrective action to be taken within the time prescribed in its order. A person named in the order may request in writing a hearing before the Department not later than 10 days after the date the order is served, in which case a hearing shall be scheduled within 10 days from receipt of the request. A decision shall be rendered within 10 days from the date of the hearing.</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Require the alleged violator to file a written report regarding the alleged violation.</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Require the alleged violator to appear before the Department at a time and place the Department specifies to answer the charge outlined in the complaint.</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Require the alleged violator to file a written report regarding the alleged violation and appear before the Department at a time and place the Department specifies to answer the charges outlined in the complaint.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>Every order the Department issues under this regulation shall be served on the person affected according to Environment Article, §9-336, Annotated Code of Maryland. The order shall become effective immediately according to the order's terms upon service.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>If the Department exercises the option provided by §A(1)(b) of this regulation, the alleged violator may request in writing a hearing before the Department not later than 10 days after the date that notice of the requirement of the written report is served.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The appearance of the alleged violator before the Department under the options provided by §A(1)(c) or (d) of this regulation constitutes an administrative hearing and the party has the right of any party in a contested case provided in State Government Article, Title 10, and Environment Article, Title 1, Annotated Code of Maryland.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>If the Department exercises any of the options provided by §A(1)(a), (c), or (d) of this regulation, the Department shall notify the permittee of the consequences of not attending the hearing or, in the case of option §A(1)(b), not filing the written report.</text>
      </paragraph>
      <paragraph num="(6)">
        <text>If the Department exercises the option provided by §A(1)(b), (c), or (d) of this regulation, it may not issue an order requiring corrective action to be taken as a result of the alleged violation before expiration of the time set for filing any report and holding any hearing required under these sections. After that, the Department may issue an order requiring necessary corrective action be taken within the time prescribed in the order. A person is not entitled to a hearing before the Department as a result of this order.</text>
      </paragraph>
      <paragraph num="(7)">
        <text>Notice of a hearing or of a requirement that a written report be filed shall be served on the alleged violator under Environment Article, §§9-335 — 9-337, Annotated Code of Maryland, not less than 10 days before the time set for the hearing or filing of a report.</text>
      </paragraph>
      <paragraph num="(8)">
        <text>Requests for hearings shall be processed and the hearings conducted according to State Government Article, Title 10, and Environment Article, Title 1, Annotated Code of Maryland, and the requirements of this chapter.</text>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Administrative Action With Regard to Permit. If the permittee fails to comply with the requirements of an administrative order under §A(1) of this regulation, a permit may be modified or suspended. Modification or suspension of a permit shall be effective without stay upon receipt by the permittee of appropriate notice. Upon written request for a hearing by the permittee in accordance with the procedure specified in §A(3) of this regulation, a hearing shall be held, but the administrative action may not be stayed pending the hearing.</text>
    </paragraph>
    <paragraph num="C.">
      <text>Emergency Action.</text>
      <paragraph num="(1)">
        <text>The Department may summarily modify or suspend a permit when the Department finds that the protection of public health, safety, or welfare requires immediate emergency action.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>The emergency modification or suspension of a permit shall be effective without stay upon receipt by the permittee of appropriate notice.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Department shall notify the permittee in writing that the permit has been modified or suspended for emergency reasons. The notice shall include:</text>
        <paragraph num="(a)">
          <text>The finding of necessity for suspension or modification;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The reasons that support the findings;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A statement that the permittee has the right to a hearing concerning the Department's action;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>A statement that the permittee has 10 days to request a hearing;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The procedure for requesting a contested case hearing;</text>
        </paragraph>
        <paragraph num="(f)">
          <text>The consequences of not requesting or not attending a hearing; and</text>
        </paragraph>
        <paragraph num="(g)">
          <text>A statement that the permit suspension or modification is effective without stay upon receipt by the permittee.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Permit Revocation.</text>
      <paragraph num="(1)">
        <text>A permit may be revoked after notice to the permittee and opportunity for a hearing, if the Department determines that any of the following have occurred:</text>
        <paragraph num="(a)">
          <text>The permittee has failed to comply with the requirements of an administrative action according to §A, B, or C of this regulation;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>False or inaccurate information was contained in the application for the permit;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Conditions or requirements of the permit have been or are about to be violated;</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Substantial deviation from plans, specifications, or requirements has occurred;</text>
        </paragraph>
        <paragraph num="(e)">
          <text>The permittee has failed to permit an authorized representative of the Department upon presentation of proper credentials to:</text>
          <paragraph num="(i)">
            <text>Enter at any reasonable time upon permittee's premise where a point source is located, pertinent operations are conducted, or records are required to be kept under terms and conditions of the permit;</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Have access to and copy any records required to be kept under terms and conditions of the permit;</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Inspect facilities to ensure compliance with the conditions of the permit;</text>
          </paragraph>
          <paragraph num="(iv)">
            <text>Inspect any monitoring equipment or method required in the permit; or</text>
          </paragraph>
          <paragraph num="(v)">
            <text>Sample any discharge or pollutants;</text>
          </paragraph>
        </paragraph>
        <paragraph num="(f)">
          <text>Change in conditions exists requiring temporary or permanent reduction or elimination of the permitted operation or discharge;</text>
        </paragraph>
        <paragraph num="(g)">
          <text>Any State or federal water quality stream standard or effluent standard has been or is threatened to be violated; or</text>
        </paragraph>
        <paragraph num="(h)">
          <text>Any other good cause exists for revoking the discharge permit.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The permittee has the right to a hearing concerning the revocation of the permit upon a request in writing not later than 10 days after the date on which the revocation notice is served. The Department shall schedule a hearing within 10 days from receipt of the request and give a decision within 10 days from the date of the hearing.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>The hearings in §§B, C, and D of this regulation shall be conducted according to State Government Article, Title 10, and Environment Article, Title 1, Annotated Code of Maryland.</text>
    </paragraph>
  </regulation>
  <regulation prefix="Regulation" num=".11" heading="Discharge Permit Fees.">
    <paragraph num="A.">
      <text>General Requirements.</text>
      <paragraph num="(1)">
        <text>Fees collected by the Department under this regulation shall be paid into the Maryland Clean Water Fund. The fees shall be used for activities that are related to identifying, monitoring, and regulating the proper discharge of effluent into waters of the State including program development of these activities.</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Persons or facilities holding or obtaining State discharge permits, except for those in categories listed below, shall pay both an annual permit fee and an application fee, including any additional cost as required in §C(10) of this regulation:</text>
        <paragraph num="(a)">
          <text>Publicly owned treatment works;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Other treatment works which treat only sewage;</text>
        </paragraph>
        <paragraph num="(c)">
          <text>Persons covered under a general permit as described in Regulations .08 and .09 of this chapter; or</text>
        </paragraph>
        <paragraph num="(d)">
          <text>Facilities or persons culturing or raising aquatic organisms in enclosed systems discharging less than 1 million gallons per day.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(3)">
        <text>Both permit fees and application fees are based on the total flow of all effluents discharged from a facility except for:</text>
        <paragraph num="(a)">
          <text>Uncontaminated stormwater runoff; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Thermal discharge flows which have previously been evaluated by the Department in accordance with COMAR 26.08.03.03C(2).</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="B.">
      <text>Permit Fees.</text>
      <paragraph num="(1)">
        <text>The permit fee is based on the anticipated:</text>
        <paragraph num="(a)">
          <text>Cost of monitoring and regulating the permitted facility; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Needs for program development activities related to management of discharge of pollution to waters of this State.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The permit fee is based on the total flow volume of effluent discharged from the facility. The fees are as follows:</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The Department will calculate permit fees annually and will bill the permittee. The permit fees shall be paid within 30 days of receipt of the bill, unless the permittee questions the calculations or assumptions, or both, used to arrive at the fee. In which case, the Department shall be notified in writing within 15 days of receipt of the bill, and a meeting shall be scheduled, if necessary, within 10 days to resolve the dispute.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>Permit fees shall be paid by July 1 of each year to cover the expenses of the ensuing fiscal year. Fees for those permits which will be in effect for less than the full fiscal year shall be prorated for the number of months of the fiscal year during which the permit is in effect.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>The Department may refuse to issue or renew a discharge permit or may revoke a discharge permit if the applicant fails or refuses to pay the permit fee.</text>
      </paragraph>
    </paragraph>
    <paragraph num="C.">
      <text>Application Fees.</text>
      <paragraph num="(1)">
        <text>An application fee shall be paid for:</text>
        <paragraph num="(a)">
          <text>An application for a new discharge permit;</text>
        </paragraph>
        <paragraph num="(b)">
          <text>An application to renew a discharge permit; or</text>
        </paragraph>
        <paragraph num="(c)">
          <text>A request to modify a discharge permit if the modification is considered significant by the Department.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(2)">
        <text>The application fee is based on the cost of the permit procedure.</text>
      </paragraph>
      <paragraph num="(3)">
        <text>The minimum application fee is $50.</text>
      </paragraph>
      <paragraph num="(4)">
        <text>The application fee is calculated by the following formula: Application fee = volume fee x industry factor x water use factor.</text>
      </paragraph>
      <paragraph num="(5)">
        <text>Volume Fees.</text>
        <paragraph num="(a)">
          <text>Volume fees are determined as follows:</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Volume fees for permit modifications are based only on the discharge volume associated with those operations affected by the modification.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(6)">
        <text>Industry Factors.</text>
        <paragraph num="(a)">
          <text>The industry factors are determined as follows:</text>
        </paragraph>
        <paragraph num="(b)">
          <text>Facilities which wash cars, trucks, or other vehicles are not considered to be primary industries for the purposes of §C(6).</text>
        </paragraph>
      </paragraph>
      <paragraph num="(7)">
        <text>Water Use Factor.</text>
        <paragraph num="(a)">
          <text>The water use factor is determined as follows:</text>
        </paragraph>
        <paragraph num="(b)">
          <text>When a facility has more than one type of water use, the highest of the applicable water use factors should be used.</text>
        </paragraph>
      </paragraph>
      <paragraph num="(8)">
        <text>The Department will calculate the application fee upon receipt of an application for a new permit, permit renewal, or permit modification and will bill the applicant. The application fee shall be paid within 30 days of receipt of the bill, unless the permittee questions the calculations or assumptions, or both, used to arrive at the fee. In which case, the Department shall be notified in writing within 15 days of receipt of the bill, and a meeting shall be scheduled, if necessary, within 10 days to resolve the dispute.</text>
      </paragraph>
      <paragraph num="(9)">
        <text>The Department may refuse to complete processing on any new or renewed permit or on any permit modification if the applicant fails or refuses to pay the application fee.</text>
      </paragraph>
      <paragraph num="(10)">
        <text>In addition to the application fee calculated in accordance with §C(4) of this regulation, the Department shall assess the applicant for any cost associated with evaluating or reviewing mixing zone studies, variance petitions, site-specific criteria studies, chemical or biological translator studies, or any other studies submitted as part of an application to determine discharge permit requirements. For the purposes of this assessment:</text>
        <paragraph num="(a)">
          <text>The minimum fee for each component (for example, mixing zone, variance, etc.) will be established at $5,000; and</text>
        </paragraph>
        <paragraph num="(b)">
          <text>The Department shall:</text>
          <paragraph num="(i)">
            <text>Obtain and provide to the applicant an estimate for any additional costs incurred as part of the evaluation or review,</text>
          </paragraph>
          <paragraph num="(ii)">
            <text>Obtain the applicant's concurrence, and</text>
          </paragraph>
          <paragraph num="(iii)">
            <text>Bill the applicant before the beginning of the evaluation or review.</text>
          </paragraph>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="D.">
      <text>Calculation of Stormwater Runoff Volume. Stormwater runoff volume shall be determined by the following method:</text>
      <paragraph num="(1)">
        <text>Annual stormwater runoff volume = Annual rainfall (feet) x drainage area (square feet) x 7.48 x runoff coefficient;</text>
      </paragraph>
      <paragraph num="(2)">
        <text>Average stormwater runoff volume = Annual stormwater runoff volume divided by 365;</text>
      </paragraph>
      <paragraph num="(3)">
        <text>As an alternative to this method, the permittee may submit a report to the Department which contains calculations of the average daily stormwater runoff from the permitted facility.</text>
      </paragraph>
    </paragraph>
    <paragraph num="E.">
      <text>For storm water discharges eligible for coverage under Regulation .09 of this chapter, the portion of the permit fee calculated in Regulation .11 of this chapter may not exceed $100 per year.</text>
    </paragraph>
  </regulation>
  <annotations>
    <annotation type="Authority">Environment Article, §§1-601—1-606, 9-313, 9-315, 9-323—9-328, and 9-330, Annotated Code of Maryland</annotation>
    <annotation type="History" subtype="Administrative History">Effective date: September 1, 1974 (1:1 Md. R. 33)</annotation>
    <annotation type="History" subtype="Administrative History">COMAR 10.50.01.08, .09, .12, and .14 recodified to COMAR 26.08.04.01, .02, .03, and .04, respectively</annotation>
    <annotation type="History" subtype="Administrative History">COMAR 10.50.01.08J-1 recodified to COMAR 26.08.08.01—.04</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01B, N amended effective August 3, 1981 (8:15 Md. R. 1308)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01E amended effective June 6, 1983 (10:11 Md. R. 976)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01G amended effective July 27, 1987 (14:15 Md. R. 1660)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01J amended effective May 24, 1982 (9:10 Md. R. 1022); December 19, 1983 (10:25 Md. R. 2269); June 17, 1985 (12:12 Md. R. 1165); August 26, 1985 (12:17 Md. R. 1706)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01M amended effective June 17, 1985 (12:12 Md. R. 1166)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01N adopted effective March 9, 1979 (6:5 Md. R. 444)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02 adopted effective December 7, 1981 (8:24 Md. R. 1935)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03A amended effective December 19, 1983 (10:25 Md. R. 2269)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04 adopted effective February 25, 1985 (12:4 Md. R. 360)</annotation>
    <annotation type="History" subtype="Administrative History">Chapter revised effective June 27, 1988 (15:13 Md. R. 1556)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01 amended effective April 15, 1991 (18:7 Md. R. 775)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01 amended and recodified to Regulations .01—.01-3 effective November 6, 1995 (22:22 Md. R. 1670)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01B amended effective September 27, 1993 (20:19 Md. R. 1473); January 12, 2009 (36:1 Md. R. 24); December 22, 2014 (41:25 Md. R. 1486); September 28, 2015 (42:19 Md. R. 1229)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01G amended effective June 7, 1993 (20:11 Md. R. 917)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-1E amended effective March 25, 1996 (23:6 Md. R. 477)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .01-3A, C amended effective March 25, 1996 (23:6 Md. R. 477)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02 amended effective April 16, 1990 (17:7 Md. R. 854); April 15, 1991 (18:7 Md. R. 775); June 7, 1993 (20:11 Md. R. 917); November 6, 1995 (22:22 Md. R. 1670)</annotation>
    <annotation type="History" subtype="Administrative History">Regulations .02-1—.02-4 adopted effective June 7, 1993 (20:11 Md. R. 917)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02-1C amended effective April 28, 2014 (41:8 Md. R. 474)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02-3 amended effective November 6, 1995 (22:22 Md. R. 1670)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .02-3C amended effective July 5, 2004 (31:13 Md. R. 995)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03 amended effective April 16, 1990 (17:7 Md. R. 854); November 6, 1995 (22:22 Md. R. 1670)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .03C amended effective June 7, 1993 (20:11 Md. R. 917)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04 amended effective November 6, 1995 (22:22 Md. R. 1670)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .04C amended effective May 1, 1989 (16:8 Md. R. 911); April 16, 1990 (17:7 Md. R. 854); April 28, 2014 (41:8 Md. R. 474)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06 amended effective November 6, 1995 (22:22 Md. R. 1670)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .06A amended effective April 15, 1991 (18:7 Md. R. 775)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .07 amended effective April 15, 1991 (18:7 Md. R. 775)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08 amended effective November 6, 1995 (22:22 Md. R. 1670); March 25, 1996 (23:6 Md. R. 477)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08B amended effective April 15, 1991 (18:7 Md. R. 775)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .08C, D amended effective September 27, 1993 (20:19 Md. R. 1473)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09 amended effective September 27, 1993 (20:19 Md. R. 1473)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09H adopted effective October 24, 1994 (21:21 Md. R. 1815)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09I—K adopted effective July 31, 1995 (22:15 Md. R. 1122)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09J amended effective November 23, 2015 (42:23 Md. R. 1435)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09K amended effective September 29, 2014 (41:19 Md. R. 1082)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09L—N adopted effective December 16, 1996 (23:25 Md. R. 1786)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09N amended effective January 12, 2009 (36:1 Md. R. 24)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09O, P adopted effective April 7, 1997 (24:8 Md. R. 617)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1 adopted effective September 27, 1993 (20:19 Md. R. 1473)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1A, C amended and K adopted effective April 7, 1997 (24:8 Md. R. 617)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1B amended effective October 24, 1994 (21:21 Md. R. 1815); July 31, 1995 (22:15 Md. R. 1122)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1C amended effective February 14, 1994 (21:3 Md. R. 197); October 20, 1997 (24:21 Md. R. 1453)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1C amended as an emergency provision effective March 1, 2003 (30:6 Md. R. 417); amended permanently effective June 23, 2003 (30:12 Md. R. 792)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1D adopted effective October 24, 1994 (21:21 Md. R. 1815)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1D amended effective February 21, 2000 (27:3 Md. R. 327)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1E—G amended effective August 21, 2000 (27:16 Md. R. 1526)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1G amended effective September 29, 2014 (41:19 Md. R. 1082)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1H—J adopted effective December 16, 1996 (23:25 Md. R. 1786)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1J amended effective January 12, 2009 (36:1 Md. R. 24)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .09-1K amended effective December 21, 2015 (42:25 Md. R. 1547)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .10 amended and recodified to Regulations .10 and .10-1 effective November 6, 1995 (22:22 Md. R. 1670)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .10C amended effective April 15, 1991 (18:7 Md. R. 775)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .11A amended effective July 9, 1990 (17:13 Md. R. 1614); June 7, 1993 (20:11 Md. R. 917)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .11B amended effective April 17, 1989 (16:7 Md. R. 813); June 21, 1993 (20:12 Md. R. 997)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .11C amended effective April 15, 1991 (18:7 Md. R. 775); June 7, 1993 (20:11 Md. R. 917); June 21, 1993 (20:12 Md. R. 997)</annotation>
    <annotation type="History" subtype="Administrative History">Regulation .11E adopted effective October 20, 1997 (24:21 Md. R. 1453)</annotation>
  </annotations>
</chapter>