<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".05" citation="COMAR 26.10.03.05" title_num="26" subtitle_num="10" chapter_num="03" heading="Precision Tightness Testing.">
  <paragraph num="A.">
    <text>After completing the installation or replacement, repair, or upgrade of a UST system, an owner and an operator of a UST system shall test the UST system for tightness using a precision tightness test as defined in COMAR 26.10.02.02B before operation of the UST system.</text>
  </paragraph>
  <paragraph num="B.">
    <text>An owner and an operator of a UST system shall only conduct a precision tightness test approved by the Department.</text>
  </paragraph>
  <paragraph num="C.">
    <text>For each precision tightness test conducted on a UST system, the owner and the operator of the UST system shall:</text>
    <paragraph num="(1)">
      <text>Maintain and make available for inspection by the Department upon request, records regarding a precision tightness test;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Keep the records on file at the regulated substance storage facility or at a location designated by and the under control of the owner and the operator of the UST system for as long as the UST system is used to store a regulated substance; and</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Include in the records all of the following information:</text>
      <paragraph num="(a)">
        <text>The commercial name of the test equipment;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The name of the testing company;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The name of the individual conducting the test;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>The date of the test;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>The data accumulated by the test; and</text>
      </paragraph>
      <paragraph num="(f)">
        <text>The results of the precision tightness test.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Inconclusive Precision Tightness Test Results.</text>
    <paragraph num="(1)">
      <text>When a precision tightness test conducted on a UST system results in an inconclusive test result, the owner and the operator of the UST system shall retest the UST system not later than 2 working days after the inconclusive test result.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>If a subsequent precision tightness test conducted on a UST system also results in an inconclusive test result, the owner and the operator of the UST system and the person conducting the precision tightness test shall report the test result as a failure to the Department within 2 hours in accordance with COMAR 26.10.08.01.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>When a precision tightness test conducted on a UST system results in a failed test result, the owner and the operator of the UST system and the person conducting the precision tightness test shall report the failed test result to the Department within 2 hours in accordance with COMAR 26.10.08.01.</text>
  </paragraph>
  <paragraph num="F.">
    <text>Consumptive Use UST Systems.</text>
    <paragraph num="(1)">
      <text>An owner and an operator of a consumptive use UST system shall comply with the requirements of §§A—E of this regulation.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Unless otherwise required by the Department, an owner and an operator of a consumptive use UST system are not required to conduct precision tightness tests on the consumptive use UST system at the frequency required under §F(3)(a) if the following conditions are met:</text>
      <paragraph num="(a)">
        <text>The UST system is protected against corrosion in accordance with the requirements of this chapter;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The UST system is installed in accordance with the requirements of this chapter; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The owner and the operator of the UST system conduct monthly release detection monitoring of the UST system in accordance with COMAR 26.10.05.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>If the conditions in §F(2) of this regulation are not met, an owner and an operator of a consumptive use UST system shall:</text>
      <paragraph num="(a)">
        <text>Conduct a precision tightness test on the UST system:</text>
        <paragraph num="(i)">
          <text>15 years after the installation date for the UST system or, if the installation date cannot be determined, immediately; and</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>At least every 5 years after the most recent precision tightness test; and</text>
        </paragraph>
      </paragraph>
      <paragraph num="(b)">
        <text>Conduct a precision tightness test on the UST system immediately upon receipt of a notice from the Department to conduct a precision tightness test.</text>
      </paragraph>
    </paragraph>
  </paragraph>
</regulation>