  <paragraph num="A.">
    <text>Applicability.</text>
    <paragraph num="(1)">
      <text>The owner or operator of a source shall comply with the procedures in this regulation when applying for a permit to construct for any of the activities listed in §A(2) of this regulation at any source:</text>
      <paragraph num="(a)">
        <text>For which a State permit to operate is required, as provided in Regulation .13 of this chapter;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Subject to federal new source performance standards at 40 CFR 60, national emission standards for hazardous air pollutants at 40 CFR 61, or prevention of significant deterioration requirements at 40 CFR §52.21;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>That, after control, will discharge 25 tons per year or more of a pollutant regulated under Environment Article, Title 2, Annotated Code of Maryland, in the areas of Baltimore City designated by the United States Post Office as zip code numbers 21225, 21226, and 21230; or</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Of lead that will discharge 5 tons per year or more of lead or lead compounds measured as elemental lead.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>This regulation applies to applications for permits to construct for the following activities at the sources listed in §A(1) of this regulation:</text>
      <paragraph num="(a)">
        <text>Construction of a new source;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Replacement of components of an existing permitted source, if the fixed capital cost of the replacement components exceeds 1/2 of the fixed capital cost that would be required to construct a new source comparable in process to the existing source; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Modification of an existing permitted source by making a physical or operational change to the source that will result in a significant net increase in emissions of any pollutant from that source.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>Before issuing a permit to construct for any of the activities listed in §A(2) of this regulation, at a source that is subject to federal new source performance standards under 40 CFR 60, the Department shall either comply with the provisions of §§E—N of this regulation, or with the following procedures:</text>
      <paragraph num="(a)">
        <text>Electronically post a notice of an application for the permit on the Department’s website in accordance with Environment Article, §1-602(B)(2), Annotated Code of Maryland;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Give notice to the chief executive of any county or municipal corporation in which any portion of the source is located or is proposed to be located; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Receive comments from the public on the permit application.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Exception for an Approval and for Certain Control Equipment. Notwithstanding the requirements of §A, this regulation does not apply to:</text>
    <paragraph num="(1)">
      <text>The approval phase of a source for which an approval is required; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The construction or installation of air pollution control equipment for which a permit to construct is required, as provided in Regulation .09 of this chapter, and that will control an existing source.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Consolidated Procedures. For a source that is subject to this regulation and is also a Part 70 source, the Department may authorize special procedures, at the applicant's request, for the applicant to apply simultaneously, to the extent possible, for a permit to construct and a Part 70 permit, or a revision to a Part 70 permit. These procedures may provide for combined public notices, informational meetings, and public hearings for both permits but may not adversely affect the rights of a person, including the EPA and affected states, to obtain information about the application for a permit, to comment on an application, or to challenge a permit that is issued. In addition, these procedures may not alter any existing Part 70 permit procedures or time frames.</text>
  </paragraph>
  <paragraph num="D.">
    <text>Application. The owner or operator of a source subject to this regulation shall submit a complete application on forms provided by the Department. The information that the Department requires may vary depending on the type of source. The applicant shall provide information sufficient to enable the Department to determine whether the source can be constructed so that it can comply with all applicable requirements of the Clean Air Act and State air pollution control law. An application shall include evidence of compliance with State Workers' Compensation laws as required by Environment Article, §1-202, Annotated Code of Maryland. Unless otherwise required by the Department, the application forms shall be complete and include the following information:</text>
    <paragraph num="(1)">
      <text>For process or manufacturing equipment or operations:</text>
      <paragraph num="(a)">
        <text>Drawings that depict the layout of the equipment or operations;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Flow sheets that depict how the equipment or operations relate to each other;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Material balance sheets;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Equipment drawings and literature; and</text>
      </paragraph>
      <paragraph num="(e)">
        <text>Purchase specifications;</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>For air pollution control equipment:</text>
      <paragraph num="(a)">
        <text>Vendor proposals or quotations;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Vendor guarantees;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Equipment drawings and literature; and</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Purchase specifications;</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>For a source that will be located at a new facility:</text>
      <paragraph num="(a)">
        <text>An area map; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>If requested, additional information regarding the nature of the area, including distances to residences and other buildings.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Notice of Application; Informational Meeting.</text>
    <paragraph num="(1)">
      <text>The Department shall require the applicant to send to a newspaper for publication a notice regarding the application that satisfies the requirements of Environment Article, §1-602(a), Annotated Code of Maryland. As determined by the Department, the notice shall provide for an informational meeting or an opportunity for the public to request an informational meeting within 10 days of publication of the notice. If the Department decides to hold an informational meeting because of requests for a meeting, the Department shall publish or require the applicant to publish a notice regarding the informational meeting that satisfies the requirements of Environment Article, §1-602(a), Annotated Code of Maryland. Unless the Department determines otherwise, notice of an informational meeting shall be published not later than 10 days before the meeting is held.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>In addition to the requirements under §E(1) of this regulation, on receipt of an application for a permit to construct subject to this regulation, the Department shall give notice immediately or require the applicant to give notice immediately of the application, by certified mail, to:</text>
      <paragraph num="(a)">
        <text>The governing body of each county or municipal corporation in which any portion of the source is located or is proposed to be located;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The governing body of each county or municipal corporation within 1 mile of the property line of the source or the proposed location of the source;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Each member of the General Assembly representing any part of a county in which any portion of the source is located or proposed to be located; and</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Each member of the General Assembly representing any part of each county within 1 mile of the property line of the source or the proposed location of the source.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>The Department shall ensure that the application is available to the public for inspection and copying.</text>
  </paragraph>
  <paragraph num="G.">
    <text>If an informational meeting is held regarding the application, the applicant shall attend the meeting and present information concerning the application.</text>
  </paragraph>
  <paragraph num="H.">
    <text>Tentative Determination.</text>
    <paragraph num="(1)">
      <text>The Department shall prepare a tentative determination regarding the application. The content of the tentative determination shall include:</text>
      <paragraph num="(a)">
        <text>A proposal to issue or deny the permit;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Any proposed permit terms and conditions;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>A brief explanation of the Department's tentative determination;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>Any proposed schedule of compliance;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>If the tentative determination is to issue the permit, a draft permit, which shall be available to the public for inspection and copying.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>In addition to the content of the tentative determination, the following documents shall be made available to the public for inspection and copying no later than the date of issuance of the tentative determination:</text>
      <paragraph num="(a)">
        <text>The permit application and all supporting documents submitted with the application;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>All nonprivileged documents the Department relied upon in making the tentative determination; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>A privilege log that identifies all withheld documents and states the reasons for withholding each document.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="I.">
    <text>Notice of Tentative Determination; Public Comment; Public Hearing. The Department shall publish or require the applicant to publish a notice regarding the tentative determination that satisfies the requirements of Environment Article, §1-602, Annotated Code of Maryland. The notice shall provide the opportunity for written public comment for a period of 30 days, which may be extended no more than once by an additional 60 days, upon written request received by the Department within the original comment period. As determined by the Department, the notice shall provide either that a public, nonadjudicatory hearing will be held regarding the tentative determination or that the public may request in writing within 20 days that a public hearing be held. If the Department decides to hold a public hearing because of requests for a hearing from the general public filed in writing within the 20-day request period, or from the applicant, the Department shall publish or require the applicant to publish a notice regarding the hearing that satisfies the requirements of Environment Article, §1-602(a), Annotated Code of Maryland.</text>
  </paragraph>
  <paragraph num="J.">
    <text>Public Comments. If a public hearing is held regarding the tentative determination, the applicant shall attend the hearing and present information concerning the application. Written public comments will be accepted if they are received by the Department at the public hearing or within 5 days after the public hearing or before the close of the public comment period. Oral public comments may be made at the public hearing. The Department shall consider all public comments that raise issues of law or material fact regarding an application for a permit or a tentative determination, but only if the issues are pertinent to requirements of the Clean Air Act or State air pollution control law applicable to the proposed permit to construct. Comments raising issues that relate to the location or nature of a proposed source may be considered only if the commenter first demonstrates to the satisfaction of the Department that the Department is required by law to consider the issues.</text>
  </paragraph>
  <paragraph num="K.">
    <text>Final Determination.</text>
    <paragraph num="(1)">
      <text>The Department shall prepare a final determination if:</text>
      <paragraph num="(a)">
        <text>Timely and pertinent written comments are received during the public comment period, or not later than 5 days after the public hearing, that are adverse to the tentative determination;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Oral comments are received at the public hearing that are adverse to the tentative determination and the Department prepared a transcript of those comments; or</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The final determination is substantively different from the tentative determination.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>The final determination shall constitute the Department’s final decision.</text>
    </paragraph>
  </paragraph>
  <paragraph num="L.">
    <text>Notice of Final Determination.</text>
    <paragraph num="(1)">
      <text>If the Department is required to prepare a final determination, as provided in §K of this regulation:</text>
      <paragraph num="(a)">
        <text>Subject to the requirements of §L(1)(b)(i)—(iii) of this regulation, the Department shall publish or require the applicant to publish a Notice of Final Determination that satisfies the requirements of Environment Article, §1-602(a), Annotated Code of Maryland; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>If the final determination differs substantively from the tentative determination, then prior to publishing a Notice of Final Determination pursuant to §L(1)(a) of this regulation the Department may:</text>
        <paragraph num="(i)">
          <text>Publish a Notice of Intent to Issue a Final Determination that includes a proposed final determination, and provides the opportunity for written public comment for a period of 30 days on the portion of the proposed final determination that differs substantively from the tentative determination;</text>
        </paragraph>
        <paragraph num="(ii)">
          <text>Consider all public comments submitted on the portion of the proposed final determination that differs substantively from the tentative determination, subject to the criteria set forth in COMAR 26.11.02.11J; and</text>
        </paragraph>
        <paragraph num="(iii)">
          <text>Prepare written responses to public comments submitted on the proposed final determination.</text>
        </paragraph>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>If the Department is not required to prepare a final determination under §K of this regulation, the Department shall issue or deny the permit and the tentative determination becomes the final determination and shall constitute the Department’s final decision.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>The Department shall electronically post notice that the tentative determination has become the final determination on the Department’s website.</text>
    </paragraph>
  </paragraph>
  <paragraph num="M.">
    <text>Judicial Review.</text>
    <paragraph num="(1)">
      <text>In accordance with Environment Article, §1-601(c), Annotated Code of Maryland, a final determination by the Department to issue or deny a permit to construct subject to Environment Article, §2-404, Annotated Code of Maryland, shall be subject to judicial review at the request of any person who:</text>
      <paragraph num="(a)">
        <text>Meets the threshold standing requirements under federal law; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Is the applicant or participated in a public participation process through the submission of written or oral comments, unless an opportunity for public participation was not provided.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Judicial review shall be on the administrative record before the Department and limited to objections raised during the public comment period, unless the petitioner demonstrates that:</text>
      <paragraph num="(a)">
        <text>The objections were not reasonably ascertainable during the comment period; or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Ground for objections arose after the comment period.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>Unless otherwise required by statute, a petition for judicial review shall be filed with the circuit court for the county where the application for the permit states that the proposed activity will occur.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>A person submitting a petition for judicial review shall file the petition within 30 days after publication of a Notice of Final Determination.</text>
    </paragraph>
    <paragraph num="(5)">
      <text>Except as expressly provided in Environment Article, §1-605(d), Annotated Code of Maryland, a party to the judicial review action may not challenge a facility’s compliance with zoning and land use requirements.</text>
    </paragraph>
    <paragraph num="(6)">
      <text>Judicial review under this regulation shall be limited to a record compiled by the Department consisting of:</text>
      <paragraph num="(a)">
        <text>Any permit application and any data submitted to the Department in support of the application;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Any draft permit issued by the Department;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Any notice of intent from the Department to deny the application or to terminate the permit;</text>
      </paragraph>
      <paragraph num="(d)">
        <text>A statement or fact sheet explaining the basis for the determination by the Department;</text>
      </paragraph>
      <paragraph num="(e)">
        <text>All documents referenced in the statement or fact sheet explaining the basis for the determination by the Department;</text>
      </paragraph>
      <paragraph num="(f)">
        <text>All documents, except documents for which disclosure is precluded by law or that are subject to privilege, contained in the supporting file for any draft permit;</text>
      </paragraph>
      <paragraph num="(g)">
        <text>All comments submitted to the Department during the public comment period, including comments made on the draft application;</text>
      </paragraph>
      <paragraph num="(h)">
        <text>Any tape or transcript of any public hearings held on the application; and</text>
      </paragraph>
      <paragraph num="(i)">
        <text>Any response to any comments submitted to the Department.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="N.">
    <text>For the purposes of this regulation, a notice that satisfies the requirements of Environment Article, §1-602(a), Annotated Code of Maryland, is a notice that is published at least once a week for 2 consecutive weeks in a daily newspaper of general circulation in the geographic area in which the source is, or will be, located. The Department may also require the applicant to mail notice to any other person who has requested the notice, or to the person's authorized representative, and may require the applicant to post the notice in the vicinity of the proposed source or at public facilities in the geographic area of the proposed source. The applicant shall bear all costs related to providing the notice.</text>