<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".25" citation="COMAR 26.11.19.25" title_num="26" subtitle_num="11" chapter_num="19" heading="Control of Volatile Organic Compounds From Explosives and Propellant Manufacturing.">
  <paragraph num="A.">
    <text>Applicability.</text>
    <paragraph num="(1)">
      <text>This regulation applies to a person who owns or operates existing equipment at a premises that has a potential to emit 25 tons or more of VOC per year from all explosives and propellant manufacturing equipment at the premises.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Section C(2) of this regulation applies to a person who constructs, owns, or operates new equipment that has or will have total actual VOC emissions of 50 pounds or more per day.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Definitions. In this regulation, the following terms have the meaning indicated:</text>
    <paragraph num="(1)">
      <text>“Existing equipment” means explosives and propellant manufacturing equipment placed in operation before January 1, 1991.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>“Explosives and propellant manufacturing equipment” means process equipment used to preheat, grind, mix, blend, cure, dry, cut, press, extrude, or cast materials to produce energetic materials such as rocket fuels and gun propellants.</text>
    </paragraph>
    <paragraph num="(3)">
      <text>“New equipment” means explosives and propellant manufacturing equipment placed in operation on or after January 1, 1991.</text>
    </paragraph>
    <paragraph num="(4)">
      <text>“Nitramine propellant manufacturing equipment” means explosives and propellant manufacturing equipment used to mix, blend, dry, cut, press, or otherwise manufacture nitramine-based propellants such as low vulnerability ammunition.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>General Requirements.</text>
    <paragraph num="(1)">
      <text>A person who owns or operates existing explosives and propellant manufacturing equipment subject to this regulation shall:</text>
      <paragraph num="(a)">
        <text>Install a VOC control device, having a VOC destruction or removal efficiency of 85 percent or more overall, on all active nitramine propellant mixing equipment that has a capacity of 150 gallons or more;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Prepare and submit for approval by the Department by not later than September 1, 1997, a good operating practices manual that when implemented will minimize VOC emissions from all other existing explosive, propellant, and nitramine propellant manufacturing equipment; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Implement the good operating practices within 30 days after approval by the Department.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>A person who constructs, owns, or operates new equipment subject to this regulation shall reduce emissions from the new equipment by 85 percent or more, overall.</text>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Reporting and Testing Requirements. A person subject to this regulation shall:</text>
    <paragraph num="(1)">
      <text>By not later than October 1, 1997, submit to the Department:</text>
      <paragraph num="(a)">
        <text>A VOC emissions inventory for calendar year 1990 and for each subsequent year through calendar year 1996 for all explosives and propellant manufacturing equipment at the premises, and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>A complete permit to construct application for the control device required in §C(1)(a) of this regulation;</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Not later than 90 days after the control device required in §C(1)(a) of this regulation has been installed, perform a stack test to demonstrate compliance with the requirements of §C of this regulation; and</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Submit to the Department a stack test report within 60 days after completing the test.</text>
    </paragraph>
  </paragraph>
</regulation>