<?xml version='1.0' encoding='utf-8'?>
<regulation prefix="Regulation" num=".05-1" citation="COMAR 26.11.24.05-1" title_num="26" subtitle_num="11" chapter_num="24" heading="Inspections by a Certified Inspector.">
  <paragraph num="A.">
    <text>Operator Requirements.</text>
    <paragraph num="(1)">
      <text>A person that operates a gasoline dispensing facility or a gasoline storage tank with a vapor recovery system shall ensure that a certified inspector performs an inspection of each vapor recovery system.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Each vapor recovery system shall be inspected by a certified inspector in accordance with the schedules set forth in COMAR 26.10.03.10.</text>
    </paragraph>
  </paragraph>
  <paragraph num="B.">
    <text>Inspection Requirements.</text>
    <paragraph num="(1)">
      <text>The certified inspector shall inspect each vapor recovery system to confirm that:</text>
      <paragraph num="(a)">
        <text>All the necessary equipment has been installed;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The equipment is functioning properly; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>There is no defective equipment in use.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>The certified inspector shall review the facility files to confirm that:</text>
      <paragraph num="(a)">
        <text>All testing required by this chapter has been completed;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The operator has performed daily inspections of the Stage II equipment;</text>
      </paragraph>
      <paragraph num="(c)">
        <text>The records required by this chapter are complete and maintained onsite; and</text>
      </paragraph>
      <paragraph num="(d)">
        <text>All other requirements of this chapter are being met.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(3)">
      <text>The certified inspector shall complete an inspection form provided by the Department and submit the completed form to the Department within 30 days after completing the inspection.</text>
    </paragraph>
  </paragraph>
</regulation>