<regulation prefix="Regulation" num=".19" citation="COMAR 26.13.06.19" title_num="26" subtitle_num="13" chapter_num="06" heading="Surface Impoundments.">
  <paragraph num="A.">
    <text>Applicability. This regulation applies to owners and operators of facilities that use surface impoundments to treat, store, or dispose of hazardous waste, except as Regulation .01 of this chapter otherwise provides.</text>
  </paragraph>
  <paragraph num="B.">
    <text>An owner or operator of a surface impoundment subject to this regulation shall comply with the following:</text>
    <paragraph num="(1)">
      <text>COMAR 26.13.05.11C(2), concerning freeboard, except as provided in §C of this regulation;</text>
    </paragraph>
    <paragraph num="(2)">
      <text>COMAR 26.13.05.11D(1), concerning protective covers for earthen dikes;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>COMAR 26.13.05.11E, concerning waste analysis and trial test;</text>
    </paragraph>
    <paragraph num="(4)">
      <text>COMAR 26.13.05.11G(1) and (2), concerning closure and post-closure care, except that the owner or operator:</text>
      <paragraph num="(a)">
        <text>Shall, for the purposes of COMAR 26.13.05.11G(2), comply with the post-closure requirements of Regulations .12—.15 of this chapter instead of the requirements of COMAR 26.13.05.07G;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Is not required to comply with the requirement of COMAR 26.13.05.11G(2)(b) to maintain and monitor the leak detection system; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Shall, for the purposes of compliance with COMAR 26.13.05.11G(2)(c), comply with the ground water monitoring requirements of Regulation .06 of this chapter instead of the requirements of COMAR 26.13.05.06—.06-7;</text>
      </paragraph>
    </paragraph>
    <paragraph num="(5)">
      <text>COMAR 26.13.05.11I, concerning ignitable or reactive wastes, except that the owner or operator may also place ignitable or reactive waste in a surface impoundment if the owner or operator:</text>
      <paragraph num="(a)">
        <text>Manages the waste in such a way that it is protected from any material or conditions which may cause it to ignite or react;</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Obtains a certification from a qualified chemist or engineer that, to the best of the chemist's or engineer's knowledge and opinion, the design features or operating plans of the facility will prevent ignition or reaction; and</text>
      </paragraph>
      <paragraph num="(c)">
        <text>Maintains, at the facility, the certification required by §B(5)(b) of this regulation and the basis for the certification; and</text>
      </paragraph>
    </paragraph>
    <paragraph num="(6)">
      <text>COMAR 26.13.05.11J, concerning incompatible wastes.</text>
    </paragraph>
  </paragraph>
  <paragraph num="C.">
    <text>Alternate Requirements Concerning Freeboard. The owner or operator:</text>
    <paragraph num="(1)">
      <text>May maintain a freeboard level less than 60 centimeters (2 feet) in a surface impoundment if the owner or operator obtains certification by a qualified engineer that alternate design features or operating plans will, to the best of the engineer's knowledge and opinion, prevent overtopping of the dike; and</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Shall, if the owner or operator maintains a freeboard level of less than 60 centimeters, maintain at the facility:</text>
      <paragraph num="(a)">
        <text>The certification required by §C(1) of this regulation; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Written identification of alternate design features or operating plans which will prevent overtopping.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="D.">
    <text>Design Requirements.</text>
    <paragraph num="(1)">
      <text>This section applies to each new surface impoundment unit, replacement of an existing surface impoundment unit, or lateral expansion of an existing surface impoundment unit that is within the area identified in the part A permit application, which receives hazardous waste on or after May 8, 1985.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The owner or operator of a unit identified in §D(1) of this regulation shall install two or more liners and a leachate collection system between the liners in accordance with the requirements of COMAR 26.13.05.11D(4)—(8) and D-1.</text>
    </paragraph>
  </paragraph>
  <paragraph num="E.">
    <text>Notification.</text>
    <paragraph num="(1)">
      <text>The owner or operator of each unit referred to in §D(1) of this regulation shall notify the Secretary in writing at least 60 days before receiving waste into the unit.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>Persons submitting a written notice under §E(1) of this regulation shall file a part B application with the Department within 6 months of the date that the Secretary receives the written notice.</text>
    </paragraph>
  </paragraph>
  <paragraph num="F.">
    <text>Liner and Leachate Collection System Requirements for Initial Permits.</text>
    <paragraph num="(1)">
      <text>Except as provided in §F(2) of this regulation, the Secretary, when issuing the first permit to a facility for a unit subject to this regulation, may not require the installation of a liner or leachate collection system different from that which was installed under §D(2) of this regulation if the owner or operator performed the installation in good faith compliance with:</text>
      <paragraph num="(a)">
        <text>The requirements of §D(2) of this regulation; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>Guidance documents governing liners and leachate collection systems under §D(2) of this regulation that have been issued by the Department or the U.S. Environmental Protection Agency, and which were the latest guidance at the time of installation of the system.</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>The Secretary may require the installation of a new liner if the Secretary has reason to believe that a liner installed in response to the requirements of §D(2) of this regulation is leaking.</text>
    </paragraph>
  </paragraph>
  <paragraph num="F-1.">
    <text>Action Leakage Rate and Response Actions.</text>
    <paragraph num="(1)">
      <text>This section applies to the owner or operator of a surface impoundment unit identified in 40 CFR &gt;S1&gt;265.221(a).</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The owner or operator shall:</text>
      <paragraph num="(a)">
        <text>Comply with the requirements of 40 CFR §265.222 and 40 CFR §265.223, subject to §F-1(2)(b) of this regulation; and</text>
      </paragraph>
      <paragraph num="(b)">
        <text>In complying with 40 CFR §265.222 and 40 CFR §265.223, substitute “Secretary” for “Regional Administrator”.</text>
      </paragraph>
    </paragraph>
  </paragraph>
  <paragraph num="G.">
    <text>Inspections. The owner or operator of a surface impoundment shall:</text>
    <paragraph num="(1)">
      <text>Inspect, at least once each operating day:</text>
      <paragraph num="(a)">
        <text>The freeboard level to ensure compliance with COMAR 26.13.05.11C(2); or</text>
      </paragraph>
      <paragraph num="(b)">
        <text>The compliance with alternate design features or operating plans that serve to prevent overtopping if freeboard is allowed to be less than 60 centimeters in accordance with §C of this regulation;</text>
      </paragraph>
    </paragraph>
    <paragraph num="(2)">
      <text>Inspect, at least once a week, the surface impoundment, including dikes and vegetation surrounding the dikes, to detect any leaks, deterioration, or failures in the impoundment;</text>
    </paragraph>
    <paragraph num="(3)">
      <text>Comply with the requirements of 40 CFR §265.226(b) concerning the recording of information about the removal of liquids from leak detection system sumps, subject to §G(4) of this regulation; and</text>
    </paragraph>
    <paragraph num="(4)">
      <text>In complying with 40 CFR §265.226(b), substitute “Secretary” for “Regional Administrator”.</text>
    </paragraph>
  </paragraph>
  <paragraph num="H.">
    <text>Compliance Schedule — Newly Regulated Impoundments.</text>
    <paragraph num="(1)">
      <text>The owner or operator of a surface impoundment that is newly subject to §3005(j)(1) of RCRA due to the promulgation of additional listings or characteristics for the identification of hazardous waste shall assure that the surface impoundment is in compliance with §D of this regulation not later than 48 months after the promulgation of the additional listing or characteristic.</text>
    </paragraph>
    <paragraph num="(2)">
      <text>The compliance period of §H(1) of this regulation may not be cut short as a result of the promulgation of land disposal restrictions under 40 CFR Part 268 or the granting of an extension to the effective date of a prohibition under 40 CFR §268.5 within the 48-month period identified in §H(1) of this regulation.</text>
    </paragraph>
  </paragraph>
</regulation>